Monthly Schedule Update. 6.5.3.1. At monthly intervals, the Contractor shall update the schedule to reflect actual progress and submit the schedule update to the Construction Manager for review and acceptance in accordance with the Specification. The Monthly Schedule Update shall record progress for the period from the last Monthly Schedule Update through the current cutoff date set forth by the Construction Manager. The Monthly Schedule Update shall also forecast the remainder of the Work. The Monthly Schedule Update must not deviate significantly from the Baseline Schedule and shall not be used to delete or add activities, make title changes, and to make duration or logic changes. The Construction Manager may refuse to recommend the whole or part of any payment if, in the Construction Manager’s opinion, the Contractor’s failure, refusal or neglect to provide the required schedule information precludes a proper evaluation of whether or not the Contractor is prosecuting the work with the diligence that will ensure completion of the work within the Contract Time.
Monthly Schedule Update. The Contractor shall submit an updated schedule monthly by the Progress Payment cut-off date.

Related to Monthly Schedule Update

  • Schedule Updates the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and Contractor agrees not to charge the County.

  • Daily Schedule 1. Double Bus Runs - Teachers shall be required to be on duty a total of seventy-five (75) minutes in grades K-6 and sixty (60) minutes in grades 7-12 before and after the published regular pupil's school day.

  • Monthly Updates The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles 2.1.2 and 2.1.5).

  • Monthly Statement The Contractor shall submit a statement to the Engineer at the end of each month, in a tabulated form approved by the Engineer, showing the amounts to which the Contractor considers himself to be entitled. The statement shall include the following items, as applicable; - the value of the Permanent Work executed up to the end of previous month - such an amount (not exceeding 75 percent of the value) as the Engineer may consider proper on account of materials for permanent work delivered by the Contractor in the site - such amount as the Engineer may consider fair and reasonable for any Temporary Works for which separate amounts are provided in the Bill of Quantities - adjustments under Clause 70 - any amount to be withheld under retention provisions of Sub-clause 60.3 - any other sum to which the Contractor may be entitled under the Contract If the Engineer disagrees with or cannot verify any part of the statement, the Contractor shall submit such further information as the Engineer may reasonably require and shall make such changes and corrections in the statement as may be directed by the Engineer. In cases where there is difference in opinion as to the value of any item, the Engineer’s view shall prevail.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Service Updates Our Services may automatica ly download and insta l updates to your computer system from time to time and you hereby permit and consent to same. Updates are genera ly developed to improve our Services, including by providing enhanced functionality, bug fixes, and new software.

  • Monthly Status Reports 19.1.1 During the Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Program and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer or the Authority. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

  • Detailed Monthly Report Vendor shall electronically provide DIR with a detailed monthly report in the format required by DIR showing the dollar volume of any and all sales under the Contract for the previous calendar month period. Reports are due on the fifteenth (15th) calendar day of the month following the month of the sale. If the 15th calendar day falls on a weekend or state or federal holiday, the report shall be due on the next business day. The monthly report shall include, per transaction: the detailed sales for the period, Customer name, invoice date, invoice number, description, quantity, MSRP or List Price, unit price, extended price, Customer Purchase Order number, contact name, Customer’s complete billing address, the estimated administrative fee for the reporting period, subcontractor name, EPEAT designation (if applicable), configuration (if applicable), contract discount percentage, actual discount percentage, negotiated contract price (if fixed price is offered instead of discount off of MSRP), and other information as required by DIR. Each report must contain all information listed above per transaction or the report will be rejected and returned to the Vendor for correction in accordance with this section. Vendor shall report in a manner required by DIR which is subject to change dependent upon DIR’s business needs. Failure to do so may result in contract termination.

  • Pay Schedule 48.1 The regularly scheduled payday shall be bi-weekly, every other Thursday.

Time is Money Join Law Insider Premium to draft better contracts faster.