Milestones and Milestone Dates Sample Clauses

Milestones and Milestone Dates. 3.1 The Contractor shall perform its obligations so as to achieve each Milestone by the relevant Milestone Date.
AutoNDA by SimpleDocs
Milestones and Milestone Dates. 3.1. The Supplier shall perform its obligations so as to achieve each milestone by the associated date.
Milestones and Milestone Dates. Appendix B sets out a schedule of the milestones for the development of the Facility through the Commercial Operation Date (each milestone, a “Milestone”) and the Milestone Dates associated therewith, including the Expected Commercial Operation Date and the Guaranteed Commercial Operation Date. Seller shall use commercially reasonable efforts to achieve each Milestone, including the Expected Commercial Operation Date, by the Milestone Date specified therefor, and Seller guarantees that Commercial Operation will occur on or before the Guaranteed Commercial Operation Date. Until the Commercial Operation Date has been achieved, Seller shall provide Buyer with a progress report in the form included as Appendix O, Following the Effective Date until commencement of construction of the Facility, Seller will provide Buyer with quarterly progress reports, which shall be provided within fifteen (15) days of the close of each calendar quarter. After commencement of construction and until the Commercial Operation Date, Seller will provide Buyer with monthly progress reports, which shall be provided within fifteen (15) days of the close of each month.
Milestones and Milestone Dates. (Refer clause 17)
Milestones and Milestone Dates. (Refer clause Error! Reference source not found.) Note: Milestone Dates may need to be repeated if separate Milestones for separate Super Lots are required. Milestones Milestone Dates Milestone 1: Start Civil Construction [insert] Milestone 2: Practical Completion of all of the Homes on [each of the Super Lots] OR[[Super Lot 1] [Super Lot 2] [Super Lot 3]]. [insert] [ ] months after the date of the Agreement] [insert and other (if any)] [insert] Conditions
Milestones and Milestone Dates. The Supplier shall perform its obligations so as to achieve each Milestone by the Milestone Date. Changes to the Milestones and Milestone Dates set out in the Overarching Implementation Plan shall only be made in accordance with Clause 34 of this Framework Agreement and provided that the Supplier shall not attempt to postpone any of the Milestones or otherwise (except where a delay is due to Authority and/or potential Contracting Body or Contracting Body cause, in which case, the Supplier may apply to vary the Milestones or other implementation activities insofar as they relate to that potential Contracting Body or Contracting Body only).
Milestones and Milestone Dates. (a) Each of the following stages of completion of the Base Building Work is herein called a "Milestone": (I) Substantial Completion of the First-Half Dried-In Construction (hereinafter, the "First Milestone"); (II) Substantial Completion of the Dried-In Construction (hereinafter, the "Second Milestone"); (III) Substantial Completion of the Building Shell (hereinafter, the "Third Milestone"); and (IV) Substantial Completion of the Base Building Work (hereinafter, the "Fourth Milestone"). None of the foregoing Milestones shall be deemed to have been completed unless and until Tenant shall have received a statement, certified by Landlord's architect, stating that the Milestone in question has been completed and setting forth the date on which such Milestone was completed. Landlord shall use commercially reasonable efforts to give Tenant at least 5 days prior notice of Landlord's anticipated completion of each Milestone.
AutoNDA by SimpleDocs
Milestones and Milestone Dates. The Contractor shall perform its obligations so as to Achieve each Milestone by the Milestone Date. Changes to the Milestones set out in the table in paragraph 3 of this Schedule 10 shall only be made in accordance with the Change Control Procedure, provided that the Contractor shall not attempt to postpone any of the Milestones using the Change Control Procedure or otherwise (except in accordance with paragraph 9 of Part C of Schedule 12 (Governance, Information Governance and Service Management Regime)).
Milestones and Milestone Dates. 10.5.1. Appendix D sets out a schedule of the milestones for the development of the System (each milestone, a “Milestone”) and the Milestone Dates associated therewith. Seller shall use commercially reasonable efforts to achieve each Milestone. Until the Final Completion Notice has been sent, Seller shall, within fifteen (15) days after the close of each month following the Effective Date, provide Purchaser with a progress report in the form provided in Appendix D, setting forth the status of each Milestone, any issues that have arisen with respect to the timely achievement of such Milestone, and any change to any Milestone Date.

Related to Milestones and Milestone Dates

  • Milestones Subject to the provisions of the SGIP, the Parties shall agree on milestones for which each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations under this provision may be extended by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the other Parties of the reason(s) for not meeting the milestone and (1) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (2) requesting appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not unreasonably withhold agreement to such an amendment unless it will suffer significant uncompensated economic or operational harm from the delay, (1) attainment of the same milestone has previously been delayed, or (2) it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving (either itself or through the acts of a SUBLICENSEE) the following development milestones in its diligence activities under this AGREEMENT: (a) (b).

Time is Money Join Law Insider Premium to draft better contracts faster.