Common use of Maintenance Programme Clause in Contracts

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 29 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

AutoNDA by SimpleDocs

Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 10 contracts

Samples: Draft Contract Agreement, And Construction), Epc Agreement

Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s Authority‟s Engineer and submit the same to the Authority’s Authority‟s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Authority‟s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 5 contracts

Samples: Procurement and Construction, Procurement and Construction Agreement, Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:: Drafit Contract Agreement

Appears in 4 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Engineering Procurement and Construction

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertakenChainage from Km 297+700 to Km 308+460) of NH-39 in the state of Manipur on EPC Mode. The Maintenance Programme shall contain the following:July 2020

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the "Maintenance Programme") in consultation with the Authority’s 's Engineer and submit the same to the Authority’s 's Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s 's Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection in- spection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance ProgrammeMaintenanceProgramme”) in consultation with the Authority’s Engineer and submit the same to the tothe Authority’s Engineer not later than 10 (ten) days prior to the commencement of the ofthe month in which the Maintenance is to be carried out. For this purpose a joint monthly jointmonthly inspection by the Contractor and the Authority’s Engineer shall be undertakenbeundertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (i) 14.3.1. The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s Authority‟s Engineer and submit the same to the Authority’s Authority‟s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Authority‟s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Agreement

Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the AuthorityEmployer’s Engineer and submit the same to the AuthorityEmployer’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the AuthorityEmployer’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Contract Agreement for Design and Construction

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the followingthefollowing:

Appears in 1 contract

Samples: Draft Contract Agreement

AutoNDA by SimpleDocs

Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s AUTHORITY’S/GMDAs Engineer and submit the same to the Authority’s AUTHORITY’S/GMDAs Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s AUTHORITY’S/GMDAs Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Engineering Procurement And

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:of

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:: Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance Programme. (icliii) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: nhidcl.com

Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the Maintenance Programme”) in consultation with the Authority’s Employer‟s Engineer and submit the same to the Authority’s Employer‟s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose purpose, a joint monthly inspection by the Contractor and the Authority’s Employer‟s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Procurement and Construction Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme Maintenance Programme (the Maintenance Programme”) in consultation with the AuthorityEmployer’s Engineer and submit the same to the AuthorityEmployer’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the AuthorityEmployer’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:

Appears in 1 contract

Samples: Epc Contract Agreement

Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:: Draft Contract Agreement

Appears in 1 contract

Samples: Draft Contract Agreement