Limitation on General Condition Costs Sample Clauses

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: Dollars ($ );
Limitation on General Condition Costs. 24.4.1 For General Conditions Cost, Owner will pay CM General Conditions Costs up to a maximum of Percent ( %) of the Construction Cost Limitation of the Project.
Limitation on General Condition Costs. 24.4.1 The maximum allowable amount of General Conditions Costs (as authorized to be reimbursed as Direct Construction Costs under Paragraph 13.1) payable to the Design/Build Contractor during the Construction Phase of the Project shall not exceed <<Percent>> (0.00%). of the GMP for the Project.
Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: One Million, Three Hundred Seventy-Nine and no/100 Dollars ($1,379,000.00 ); *Note:Flintco has not included any costs for Safety Professionals inside the General Condition Costs above. If TAMUS requires Flintco to provide Safety Professionals, there will be an equitable adjustment to the General Conditions.
Limitation on General Condition Costs. 18.6.1 Based on the anticipated GMP established at the time of this Contract, the maximum allowable amount of General Conditions Costs payable to Construction Manager during the Construction Phase of the Project will not exceed 6.342% of the GMP for the Project.
Limitation on General Condition Costs. The maximum allowable amount of General Conditions Costs payable to the Design/Build Contractor during the Construction Phase of the Project shall not exceed percent ( %) of the Construction Cost Limitation for the Project. Based on the anticipated CCL established at the time of this Agreement, the maximum allowable amount of General Conditions Costs would be the total amount of: Dollars ($ ). If the Owner agrees to an increase in the Guaranteed Maximum Price during the Construction Phase the maximum allowable amount of General Conditions Costs shall be equitably adjusted by applying the percentage established in paragraph 24.4.1 to the amount of the increase in the GMP. The percentage rate established in paragraph 24.4.1 of this Agreement for calculation of the maximum allowable amount of General Conditions Costs cannot be increased except with the express written approval of the Associate Director for Project Management, Office of Facilities Planning and Construction. If the Owner agrees to any increases in the Construction Cost Limitation during the Construction Phase without increasing the GMP (for example, change orders funded by Owner’s Special Cash Allowance or Owner’s Construction Contingency) the allowable General Conditions Costs for these increases shall be calculated accordance with the provisions of the Uniform General and Supplementary Conditions for Change Orders.
AutoNDA by SimpleDocs
Limitation on General Condition Costs. 18.5.1 Based on the anticipated GMP and the Cost of the Work established at the time of this Contract, the maximum allowable amount of General Conditions Costs would be the total amount of: $641,000.00;

Related to Limitation on General Condition Costs

  • General Conditions Costs Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar days. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to Proceed. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable General Conditions items are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule of values. Items not specifically included below or in the exhibit will not be allowed as a General Condition costs.

  • Limitation on Use Tenant shall use the Premises solely for the Permitted Use specified in Section N of the Summary. There shall not be any change in use without the prior written consent of Landlord which will not be unreasonably withheld. Tenant shall not do anything in or about the Premises which will (i) cause structural injury to the Building, or (ii) cause damage to any part of the Building except to the extent reasonably necessary for the installation of Tenant’s Trade Fixtures and Tenant’s Alterations, and then only in a manner which has been first approved by Landlord in writing. Tenant shall not operate any equipment within the Premises which will (i) materially damage the Building or the Common Area, (ii) overload existing electrical systems or other mechanical equipment servicing the Building, (iii) impair the efficient operation of the sprinkler system or the heating, ventilating or air conditioning (“HVAC”) equipment within or servicing the Building, or (iv) damage, overload or corrode the sanitary sewer system. Tenant shall not attach, hang or suspend anything from the ceiling, roof, walls or columns of the Building or set any load on the floor in excess of the load limits for which such items are designed nor operate hard wheel forklifts within the Premises. Any dust, fumes, or waste products generated by Tenant’s use of the Premises shall be contained and disposed so that they do not (i) create an unreasonable fire or health hazard, (ii) damage the Premises, or (iii) result in the violation of any Law. Except as approved by Landlord, Tenant shall not change the exterior of the Building or install any equipment or antennas on or make any penetrations of the exterior or roof of the Building. Tenant shall not commit any waste in or about the Premises, and Tenant shall keep the Premises in a neat, clean, attractive and orderly condition, free of any nuisances. If Landlord designates a standard window covering for use throughout the Building, Tenant shall use this standard window covering to cover all windows in the Premises. Tenant shall not conduct on any portion of the Premises or the Project any sale of any kind, including any public or private auction, fire sale, going-out-of-business sale, distress sale or other liquidation sale.

  • For General Conditions Costs Contractor’s Application for Payment shall be submitted on a Schedule of Values approved by the Owner and include complete copies of all receipts, invoices with check vouchers or other evidence of payment, payrolls, and any and all other evidence which Owner or its designated representatives shall deem necessary to support the amount requested. This information is subject to audit and payment for these costs is dependent on Owner’s receipt of accurate and complete records of all transactions. Owner may reduce the amount requested for General Conditions Costs in any Application for Payment if Owner, in its good faith judgment, determines that the unpaid balance of the General Conditions line item in the Schedule of Values is not sufficient to fund necessary General Conditions Costs for the remainder of the Project.

  • General Conditions (i) Each party will make each payment or delivery specified in each Confirmation to be made by it, subject to the other provisions of this Agreement.

  • General Conditions; Definitions 1.01. The General Conditions (as defined in the Appendix to this Agreement) constitute an integral part of this Agreement.

  • Application of General Conditions These General Conditions set forth the terms and conditions generally applicable to the Development Grant Agreement to the extent and subject to any modifications set forth in such agreement.”

  • Limitation on Out of-State Litigation - Texas Business and Commerce Code § 272 This is a requirement of the TIPS Contract and is non-negotiable. Texas Business and Commerce Code § 272 prohibits a construction contract, or an agreement collateral to or affecting the construction contract, from containing a provision making the contract or agreement, or any conflict arising under the contract or agreement, subject to another state’s law, litigation in the courts of another state, or arbitration in another state. If included in Texas construction contracts, such provisions are voidable by a party obligated by the contract or agreement to perform the work. By submission of this proposal, Vendor acknowledges this law and if Vendor enters into a construction contract with a Texas TIPS Member under this procurement, Vendor certifies compliance.

  • Limitation on Damage In the event of a breach of any provision of this contract by the State, the liability of the State shall be limited to return of the unused initial deposit and unapplied payments to the Purchaser. The State shall not be liable for any damages, whether direct, incidental, or consequential.

  • General Condition The Aircraft will:

  • Limitation on Remedies In addition to any other limitation on remedies or limitations of liability set forth in our Terms of Service or in applicable law or regulations, the Company shall not be liable for any delay or failure to provide Service at any time or from time to time, or any interruption or degradation of Service quality that is caused by any of the following: (a) an act or omission of an underlying carrier, service provider, vendor or other third party; (b) equipment, network or facility failure, including failure caused by the loss of power; (c) equipment, network or facility upgrade or modification; (d) force majeure events such as (but not limited to) acts of God, acts of nature, strikes, fire, war, riot, acts of terrorism and government actions; (e) equipment or facility shortage; (f) equipment or facility relocation; (g) any act or omission by you or any person using your Service; (h) theft, fraud or abuse of Service; or (i) any other cause that is beyond the Company’s reasonable control. THE EXTENT PERMITTED BY LAW, OUR TOTAL LIABILITY FOR ANY CLAIM UNDER THIS AGREEMENT, INCLUDING FOR ANY EXPRESS OR IMPLIED WARRANTIES, IS LIMITED TO THE AMOUNT YOU PAID US FOR THE AFFECTED SERVICE OR FACILITIES, WHETHER SUCH CLAIM OR REMEDY IS SOUGHT IN CONTRACT OR TORT, INCLUDING NEGLIGENCE, STRICT LIABILITY OR OTHERWISE. TO THE EXTENT PERMITTED BY LAW, WE SHALL NOT BE LIABLE TO YOU FOR ANY CONSEQUENTIAL, INCIDENTAL, INDIRECT, PUNITIVE, SPECIAL OR TREBLED OR ENHANCED DAMAGES, INCLUDING, BUT NOT LIMITED TO LOST PROFITS, LOST BUSINESS, OR OTHER COMMERCIAL OR ECONOMIC LOSS, WHETHER SUCH DAMAGES ARE CLAIMED FOR BREACH OF CONTRACT, NEGLIGENCE OR OTHERWISE AND WHETHER OR NOT WE HAVE BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES.