Common use of Level of Detail Clause in Contracts

Level of Detail. The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Schedule Milestone elements; and (iii) major sub-critical paths, from the data date to the end of the Project. No activity shall have duration of more than 20 calendar days except perhaps for procurement on a case-by-case basis. The Project Schedule shall identify each entity responsible for performing each activity and task on the critical path and the major sub-critical paths, and shall clarify the relationships among the trades or subtrades.

Appears in 13 contracts

Samples: Part I Agreement, Basic Ordering Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Level of Detail. The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Milestone Schedule Milestone elements; and (iii) major sub-critical paths, from the data date to the end of the Project. No activity shall have duration of more than 20 calendar days except perhaps for procurement on a case-by-case basis. The Project Schedule shall identify each entity responsible for performing each activity and task on the critical path and the major sub-critical paths, and shall clarify the relationships among the trades or subtrades.

Appears in 5 contracts

Samples: Boa Services, Boa Services, Part I Agreement

Level of Detail. The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Schedule Milestone elements; and (iii) major sub-critical paths, paths from the data date to the end of the Project. No activity shall have duration of more than 20 calendar days except perhaps for procurement on a case-by-case basis. The Project Schedule shall identify each entity responsible for performing each activity and task on the critical path and the major sub-critical paths, and shall clarify the relationships among the trades or subtrades.

Appears in 2 contracts

Samples: Part I Agreement, Ordering Agreement

Level of Detail. The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Milestone Schedule Milestone elements; and (iii) major sub-critical sub‐critical paths, from the data date to the end of the Project. No activity shall have duration of more than 20 calendar days except perhaps for procurement on a case-by-case case‐by‐case basis. The Project Schedule shall identify each entity responsible for performing each activity and task on the critical path and the major sub-critical sub‐critical paths, and shall clarify the relationships among the trades or subtrades.

Appears in 2 contracts

Samples: Boa Services, Part I Agreement

AutoNDA by SimpleDocs

Level of Detail. The Project Schedule shall be of sufficient detail to identify (i) a clear critical path of the overall Project Work; (ii) critical path through each of the Schedule Milestone elements; and (iii) major sub-critical paths, paths from the data date to the end of the Project. No activity shall have duration of more than 20 calendar days except perhaps for procurement on a case-by-case basis. The Project Schedule shall identify each entity responsible for performing each activity and task on the critical path and the major sub-critical paths, and shall clarify the relationships among the trades or subtrades.. MODELDOCUMEN

Appears in 1 contract

Samples: Part I Agreement