INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES Sample Clauses

INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) 108 SP1 G14 K The Contractor shall complete the work required of Map #11 and shall place and maintain traffic on same. The date of availability for this intermediate contract time is April 1, 2019. The completion date for this intermediate contract time is July 1, 2019. The liquidated damages are Two Hundred Fifty Dollars ($ 250.00) per calendar day.
AutoNDA by SimpleDocs
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (5-21-13) 108 SP1 G14 I The Contractor shall complete the work required of installing each new inductive loop after the removal of each existing loop by the milling, patching or resurfacing operations and shall place and maintain traffic on same. The date of availability for this intermediate contract time for each inductive loop installation will be the date when the Contractor elects to disturb the existing inductive loop. The completion date for this intermediate contract time for each inductive loop installation will be the date which is seven (7) consecutive calendar days after the date of availability. The liquidated damages are Five Hundred Dollars ($ 500.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for road closures and restoring traffic to the existing traffic pattern. The Contractor shall not close I-77 (Ramps) during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday 6:00 AM - 11:00 PM The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern The liquidated damages are Five Thousand Dollars ($ 5,000.00) per hour.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow three lanes of traffic on I-40/I-85 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday From 6:00 a.m. to 12:00 a.m. (Midnight) The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Two Thousand Five Hundred Dollars ($ 2,500.00) per fifteen (15) minute time period.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow a lane of traffic on US 220 / I-73 / I-74 for Bridge Rehabilitation (LMC Overlay) on Bridges #235 & #236 as shown on TMP-6 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday 7:00 a.m. to 7:00 p.m. (Every Day) The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are One Thousand Dollars ($1000.00) per hour.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 B The Contractor shall not narrow or close a lane of traffic on I-40 and SR 1103 (Catawba Avenue/ Bat Cave Road), detain and /or alter the traffic flow on or during holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 A The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow three (3) lanes of traffic on I-40 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday, 6:00 a.m. to 11:00 p.m. In addition, the Contractor shall not close or narrow a lane of traffic on I-40, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
AutoNDA by SimpleDocs
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) 108 SP1 G14 K The Contractor shall complete the work required on Map(s) #87 thru #90 and shall place and maintain traffic on same. The date of availability for this intermediate contract time is August 31, 2015. The completion date for this intermediate contract time is May 31, 2016. The liquidated damages are One Thousand Dollars ($ 1,000.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) (Rev. 2-28-22) 108 SP1 G14 L The Contractor shall complete the work required of removing the temporary alignment for Culvert BP-024-2270, and shall place and maintain traffic on same. The date of availability for this intermediate contract time is the completion date for Intermediate Contract Time Number 2. The completion date for this intermediate contract time is June 1, 2023. The liquidated damages are Six Hundred Dollars ($ 600.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for road closures and restoring traffic to the existing traffic The Contractor shall complete the work required of NC54 and Highgate Drive Trail Construction shown on Sheet TCP-5 and shall place and maintain traffic on same. The date of availability for this intermediate contract time will be the date the Contractor elects to begin the work. The completion date for this intermediate contract time will be the date which is 14 consecutive calendar days after and including the date the Contractor begins this work. The liquidated damages are Five Thousand Dollars ($5000.00) per calendar day.