Inspection and Out-of-Box Failures Sample Clauses

Inspection and Out-of-Box Failures. The Board reserves the right to inspect all Materials upon delivery to adequately demonstrate that the Materials meet all of the specifications. Materials that do not conform to the specifications or that are otherwise damaged must either, at the Board’s discretion, be retrieved by Provider (at Provider’s expense) for replacement at no charge to the Board.
AutoNDA by SimpleDocs
Inspection and Out-of-Box Failures. Following receipt, the Board will have a minimum of fifteen (15) business days to inspect the Hardware and perform any tests the Board deems necessary to adequately demonstrate that the Hardware meets the required specifications. Unless Provider receives written notification of defects, Provider will conclusively deem such Hardware accepted after the above-referenced inspection period; however, the Board will still have the right to return the Hardware through Provider’s or the manufacturer’s return policy.
Inspection and Out-of-Box Failures. The Board reserves the right to inspect all Products upon delivery and to perform any test the Board deems necessary to adequately demonstrate that the Products meet all of the specifications as more particularly described in the Scope of Products and Services attached and incorporated into this Agreement (“Specifications”). Final inspection resulting in acceptance or rejection of the Products will be made as soon as practicable, but failure to inspect shall not be construed as a waiver by the Board of its rights to reject Products or to claim reimbursement or damages for such Products that are later found to be defective or not in conformance with the Specifications. Products that do not conform to the Specifications or that are otherwise damaged must either, at the Board’s discretion, be retrieved by the Vendor (at Vendor’s expense) for replacement at no charge to the Board, or the Board may cancel that portion of the purchase order relating to nonconforming Products at no charge to the Board. For any such returned Products, the Board shall either debit or offset from Vendor the cost of such Product plus freight, or receive a refund for such, at Board’s discretion.
Inspection and Out-of-Box Failures. The Board reserves the right to inspect all Materials upon delivery to adequately demonstrate that the Materials meet all of the This Agreement will be posted on the CPS website.

Related to Inspection and Out-of-Box Failures

  • Inspection and Tests 3.8.1 The Procuring entity or its representative shall have the right to inspect and/or to test the goods to confirm their conformity to the Contract specifications. The Procuring entity shall notify the tenderer in writing in a timely manner, of the identity of any representatives retained for these purposes.

  • Inspection and Testing Each Constructing Entity shall cause inspection and testing of the Interconnection Facilities that it constructs in accordance with the provisions of this section. The Construction Parties acknowledge and agree that inspection and testing of facilities may be undertaken as facilities are completed and need not await completion of all of the facilities that a Constructing Entity is building.

  • Inspections The Servicer shall inspect the Mortgaged Property as often as deemed necessary by the Servicer in accordance with Accepted Servicing Practices to assure itself that the value of the Mortgaged Property is being preserved. In addition, if any Mortgage Loan is more than 45 days delinquent, the Servicer promptly shall inspect the Mortgaged Property and shall conduct subsequent inspections in accordance with Accepted Servicing Practices or as may be required by the primary mortgage guaranty insurer. Upon request, the Servicer shall produce an electronic report of each such inspection.

  • INSPECTION AND REJECTION 8.1 Purchaser shall have the right to inspect and test Products at any time prior to shipment, and within a reasonable time after delivery to the Purchaser’s Destination. Products not inspected within a reasonable time after delivery shall be deemed accepted by Purchaser. The payment for Products shall in no way impair the right of Purchaser to reject nonconforming Products, or to avail itself of any other remedies to which it may be entitled.

  • Equipment Testing and Inspection 2.1.1 The Interconnection Customer shall test and inspect its Small Generating Facility and Interconnection Facilities prior to interconnection. The Interconnection Customer shall notify the NYISO and the Connecting Transmission Owner of such activities no fewer than five Business Days (or as may be agreed to by the Parties) prior to such testing and inspection. Testing and inspection shall occur on a Business Day. The Connecting Transmission Owner may, at its own expense, send qualified personnel to the Small Generating Facility site to inspect the interconnection and observe the testing. The Interconnection Customer shall provide the NYISO and Connecting Transmission Owner a written test report when such testing and inspection is completed. The Small Generating Facility may not commence parallel operations if the NYISO, in consultation with the Connecting Transmission Owner, finds that the Small Generating Facility has not been installed as agreed upon or may not be operated in a safe and reliable manner.

  • Inspection and Approval All works embracing more than one process shall be subject to examination and approval at each stage thereof and the Contractor shall given due notice to the Engineer-in-Charge or his authorized representative when each stage is ready. In default of such notice the Engineer-in- Charge shall be entitled to appraise the quality and extent thereof.

  • Environmental Inspection at End of Agreement Term A. At Authority’s discretion, at least one hundred and twenty (120) days before the expiration or early termination of the Term as provided herein, Company will conduct an environmental inspection and examination of the Company Premises. At its discretion, Authority may complete environmental reviews to determine if recognized environmental conditions exist that could warrant soil and groundwater sampling. If warranted by the findings of Company or Authority’s inspection or if requested by Authority, a compliance audit or site assessment will be performed within the aforementioned time period by a qualified professional acceptable to Authority who will report the findings to Authority. The cost for professional consulting or engineering services required for such audit will be at the expense of Company. If a site assessment is conducted, Company agrees to pay all associated laboratory and testing fees incurred to test and analyze samples collected during the site assessment process. The Authority may also choose to conduct the compliance audit or site assessment. If the results of the assessment indicate that the Company Premises have been impacted by the release of Hazardous Substances, Company will immediately take such action as is necessary and will provide a substantial guaranty in a form and content acceptable to Authority that Company will clean up the contamination at its own expense, at no expense to Authority, and in accordance with Applicable Laws to the extent that it is obligated to do so by virtue of the foregoing provisions of this Article.

  • Inspection and Final Acceptance District may, at its discretion, inspect and accept or reject any of Consultant’s work under this Agreement, either during performance or when within sixty (60) days after submitted to District. If District does not reject work by a timely written explanation, Consultant’s work shall be deemed to have been accepted. District’s acceptance shall be conclusive as to such work except with respect to latent defects, fraud and such gross mistakes as amount to fraud. Acceptance of any of Consultant’s work by District shall not constitute a waiver of any of the provisions of this Agreement including, but not limited to indemnification and insurance provisions.

  • Response/Compliance with Audit or Inspection Findings A. Grantee must act to ensure its and its Subcontractors’ compliance with all corrections necessary to address any finding of noncompliance with any law, regulation, audit requirement, or generally accepted accounting principle, or any other deficiency identified in any audit, review, or inspection of the Contract and the services and Deliverables provided. Any such correction will be at Grantee’s or its Subcontractor's sole expense. Whether Xxxxxxx's action corrects the noncompliance shall be solely the decision of the System Agency.

  • Reporting and Inspection If you use the Software and/or Services outside the Vendor's Cloud, you are required to purchase Subscription Services in a quantity equal to the total number of Units of that Red Hat Product (including variants or components thereof) that you deploy, install, use or execute as set forth in Appendix 1. You will promptly notify Red Hat and Red Hat will invoice you for each Unit on a pro-rata basis and you will pay for such Units within thirty (30) days of the date of invoice or as otherwise set forth in the Agreement. Failure to comply with this Section 4 will be considered a material breach of this Agreement, and will entitle Red Hat and/or Vendor to suspend the Services or terminate this Agreement.