Common use of Information Supplementation Clause in Contracts

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 93 contracts

Samples: Interconnection Agreement, Large Generator Interconnection Agreement, Caiso Tariff Appendix Hh

AutoNDA by SimpleDocs

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Connecting Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 85 contracts

Samples: Study Agreement, Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Connecting Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 26 contracts

Samples: Large Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 19 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built" Electric Generating Unit information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 17 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s 's Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 15 contracts

Samples: Agreement, Agreement, Revision History*

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 14 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Large Generating Unit Facility information or and “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Interconnecting Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the The Interconnection Customer shall provide the Participating TO Interconnecting Transmission Owner and the CAISO System Operator with any information changes due to proposed equipment replacement, repair, or adjustment. The Participating TO Interconnecting Transmission Owner shall provide the Interconnection Customer and System Operator with any information changes due to proposed equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOInterconnecting Transmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to in accordance with Article 5.195.19 of this Agreement.

Appears in 12 contracts

Samples: Via Electronic Filing, Large Generator Interconnection Agreement, Electronic Filing

Information Supplementation. Prior to the Trial Commercial Operation dateDate, or as soon as possible thereafter, the Parties shall supplement their information submissions described above in this Article 24 5 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Owner and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer and Transmission Provider any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.]

Appears in 12 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or or‌ “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 11 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Connecting Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 10 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Con Edison shall supplement their its information submissions described above in this Article 24 22 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Con Edison shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Con Edison shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Con Edison shall provide the Participating TO and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer , including any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirementssubstation. The Parties Con Edison shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 9 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s 's Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall use Reasonable Efforts to provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 8 contracts

Samples: Agreement, Agreement, Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s 's Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 5 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Standard Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO ISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO ISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 5 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 4 contracts

Samples: Large Generator Interconnection Agreement, www.transmissionhub.com, www.transmissionhub.com

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Distribution Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Distribution Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Distribution Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TODistribution Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 4 contracts

Samples: Service Agreement, Agreement, California Edison Company

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice Practice, such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent%) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric in Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Provider and the CAISO Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Provider and the CAISO Transmission Owner any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Customer, with copy to Transmission Provider, any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 3 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or and “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Interconnecting Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the The Interconnection Customer shall provide the Participating TO Interconnecting Transmission Owner and the CAISO System Operator with any information changes due to proposed equipment replacement, repair, or adjustment. The Participating TO Interconnecting Transmission Owner shall provide the Interconnection Customer and System Operator with any information changes due to proposed equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOInterconnecting Transmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to in accordance with Article 5.195.19 of this Agreement.

Appears in 3 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or " as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 3 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and National Grid shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-as- tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO National Grid and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO National Grid and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO National Grid shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owners’ substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and National Grid shall provide such information pursuant to Article 5.19.no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment. 64 SERVICE AGREEMENT NO. 1757

Appears in 3 contracts

Samples: Large Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission O 63 wner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 3 contracts

Samples: Agreement, Agreement, Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric the Generating Unit Facility operating at synchronous speed; (2) the automatic voltage regulator on and in voltage control mode; and (3) a five (5) percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide IPA validated test recordings showing the responses of Electric the Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO IPA for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO IPA any information changes due to equipment replacement, repair, repair or adjustment. The Participating TO IPA shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOIPA-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, ratings or protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) calendar days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or "as-tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s 's Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.no later than thirty

Appears in 2 contracts

Samples: Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Con Edison shall supplement their its information submissions described above in this Article 24 22 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Con Edison shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Con Edison shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Con Edison shall provide the Participating TO and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer , including any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirementssubstation. The Parties Con Edison shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Interconnecting Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Interconnecting Transmission Owner and the CAISO System Operator any information changes due to equipment replacement, repair, or adjustment. The Participating TO Interconnecting Transmission Owner shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOInterconnecting Transmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.no later than thirty

Appears in 2 contracts

Samples: Large Generator, Standard Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and National Grid shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-as- tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO National Grid and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO National Grid and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO National Grid shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owners’ substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and National Grid shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice Practice, such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent%) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric in Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Provider and the CAISO Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Provider and the CAISO Transmission Owner any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Customer, with copy to Transmission Provider, any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection (ITC Holdings Corp.)

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Large Generator, Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-TO- owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, www3.sce.com

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Con Edison shall supplement their its information submissions described above in this Article 24 22 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Con Xxxxxx shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Con Xxxxxx shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Con Edison shall provide the Participating TO and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer , including any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirementssubstation. The Parties Con Edison shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 1 contract

Samples: Service Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the each Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the each Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Each Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any other adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19.no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment. Issued by: Xxxxxx X. Xxxxxxxx, Dir. Reg. Affairs Effective: April 2, 2008 Issued on: April 23, 2008 New York Independent System Operator, Inc. FERC Electric Tariff, Original Volume Xx. 0 Xxxxxxxx Xxxxx Xx. 00 Service Agreement No. 1311

Appears in 1 contract

Samples: Service Agreement

AutoNDA by SimpleDocs

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Qualifying Facility Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by by‌ Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Large Generating Unit Facility information or and “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Interconnecting Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the The Interconnection Customer and Gen Lead Owner shall provide the Participating TO Interconnecting Transmission Owner and the CAISO System Operator with any information changes due to proposed equipment replacement, repair, or adjustment. The Participating TO Interconnecting Transmission Owner shall provide the Interconnection Customer Customer, Gen Lead Owner and System Operator with any information changes due to proposed equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOInterconnecting Transmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to in accordance with Article 5.195.19 of this Agreement.

Appears in 1 contract

Samples: Electronic Filing

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than 30 Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. regulator.‌ Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Qualifying Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Qualifying Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Qualifying Facility to verify proper operation of the Electric Generating Unit's Qualifying Facility’s automatic voltage regulator. regulator.‌ Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Qualifying Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Qualifying Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Qualifying Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitQualifying Facility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Qualifying Facility terminal or field voltages is provided. Electric Generating Unit Qualifying Facility testing shall be conducted and results provided to the Participating TO and the CAISO Company for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Company any information changes due to equipment replacement, repair, or adjustment. The Participating TO Company shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-Company- owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice Practice, such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent%) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric in Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Provider and the CAISO Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Provider and the CAISO Transmission Owner any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Customer, with copy to Transmission Provider, any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.)

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and National Grid shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO National Grid and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO National Grid and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO National Grid shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owners’ substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and National Grid shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, or as soon as possible thereafter, the Parties shall supplement their information submissions described above in this Article 24 5 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information performanceinformation that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Owner and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer and Transmission Provider any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.]

Appears in 1 contract

Samples: Second Revised Service Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer 52 Service Agreement No. 1662 Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Connecting Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Distribution Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Distribution Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Distribution Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-Distribution Provider- owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all "as-built” Electric " Large Generating Unit Facility information or “as-"as- tested" performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit "step voltage" test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating Unit’s Facility's terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Distribution Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Distribution Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Distribution Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TODistribution Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.‌‌‌

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, or as soon as possible thereafter, the Parties shall supplement their information submissions described above in this Article 24 5 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating UnitFacility's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Owner and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer and Transmission Provider any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Interim Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation datedateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit UnitFacility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit UnitFacility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit UnitFacility to verify proper operation of the Electric Generating Unit's Unit'sFacility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit UnitFacility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit UnitFacility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit UnitFacility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitUnit’sFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit UnitFacility terminal or field voltages is provided. Electric Generating Unit UnitFacility testing shall be conducted and results provided to the Participating TO and the CAISO CAISODistribution Provider for each individual Electric Generating Unit Unitgenerating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO CAISODistribution Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO TODistribution Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTODistribution Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.195.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation date, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Generating Unit to verify proper operation of the Electric Generating Unit's automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Generating Unit terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Generating Unit terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating Unit’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit terminal or field voltages is provided. Electric Generating Unit testing shall be conducted LARGE GENERATOR INTERCONNECTION AGREEMENT and results provided to the Participating TO and the CAISO for each individual Electric Generating Unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Generating Unit Facility as required by Good Utility Practice Practice, such as an open circuit “step voltage” test on the Electric Generating Unit Facility to verify proper operation of the Electric Generating UnitFacility's automatic voltage regulator. Original Sheet No. 61 Unless otherwise agreed, the test conditions shall include: (1) Electric Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent%) change in Electric Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric in Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Generating Unit Facility terminal or field voltages is provided. Electric Generating Unit Facility testing shall be conducted and results provided to the Participating TO Transmission Provider and the CAISO Transmission Owner for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO Transmission Provider and the CAISO Transmission Owner any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Owner shall provide the Interconnection Customer Customer, with copy to Transmission Provider, any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.)

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. regulator.‌ Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Distribution Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Distribution Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Distribution Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TODistribution Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Clustering Large Generator Interconnection

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties Developer and Connecting Transmission Owner shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that 55 no such differences exist. The Interconnection Customer Developer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer Developer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO Connecting Transmission Owner and the CAISO NYISO for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer Developer shall provide the Participating TO Connecting Transmission Owner and the CAISO NYISO any information changes due to equipment replacement, repair, or adjustment. The Participating TO Connecting Transmission Owner shall provide the Interconnection Customer Developer and NYISO any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TO-owned Connecting Transmission Owner substation that may affect the Interconnection Customer’s Interconnection Developer Attachment Facilities equipment ratings, protection or operating requirements. The Parties Developer and Connecting Transmission Owner shall provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-built” Electric Large Generating Unit Facility information or “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the tire voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Transmission Provider for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the Interconnection Customer shall provide the Participating TO and the CAISO Transmission Provider any information changes due to equipment replacement, repair, or adjustment. The Participating TO Transmission Provider shall provide the Interconnection Customer any information changes due to equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOTransmission Provider-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall use Reasonable Efforts to provide such information pursuant to Article 5.19no later than thirty (30) Calendar Days after the date of the equipment replacement, repair or adjustment.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Information Supplementation. Prior to the Trial Commercial Operation dateDate, the Parties shall supplement their information submissions described above in this Article 24 with any and all “as-as- built” Electric Large Generating Unit Facility information or and “as-tested” performance information that differs from the initial submissions or, alternatively, written confirmation that no such differences exist. The Interconnection Customer shall conduct tests on the Electric Large Generating Unit Facility as required by Good Utility Practice such as an open circuit “step voltage” test on the Electric Large Generating Unit Facility to verify proper operation of the Electric Large Generating Unit's Facility’s automatic voltage regulator. Unless otherwise agreed, the test conditions shall include: (1) Electric Large Generating Unit Facility at synchronous speed; (2) automatic voltage regulator on and in voltage control mode; and (3) a five percent (5 percent) change in Electric Large Generating Unit Facility terminal voltage initiated by a change in the voltage regulators reference voltage. The Interconnection Customer shall provide validated test recordings showing the responses of Electric Large Generating Unit Facility terminal and field voltages. In the event that direct recordings of these voltages is impractical, recordings of other voltages or currents that mirror the response of the Electric Large Generating UnitFacility’s terminal or field voltage are acceptable if information necessary to translate these alternate quantities to actual Electric Large Generating Unit Facility terminal or field voltages is provided. Electric Large Generating Unit Facility testing shall be conducted and results provided to the Participating TO and the CAISO Interconnecting Transmission Owners for each individual Electric Generating Unit generating unit in a station. Subsequent to the Commercial Operation Date, the The Interconnection Customer shall provide the Participating TO Interconnecting Transmission Owners and the CAISO System Operator with any information changes due to proposed equipment replacement, repair, or adjustment. The Participating TO Interconnecting Transmission Owners shall provide the Interconnection Customer and System Operator with any information changes due to proposed equipment replacement, repair or adjustment in the directly connected substation or any adjacent Participating TOInterconnecting Transmission Owner-owned substation that may affect the Interconnection Customer’s Interconnection Facilities equipment ratings, protection or operating requirements. The Parties shall provide such information pursuant to in accordance with Article 5.195.19 of this Agreement.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement