Force Maieure Clause Examples
A Force Majeure clause defines the circumstances under which parties to a contract are excused from fulfilling their obligations due to events beyond their reasonable control. Typically, this clause covers situations such as natural disasters, war, or government actions that make performance impossible or impracticable. Its core practical function is to allocate risk and provide relief from liability when unforeseen events prevent one or both parties from meeting contractual commitments.
POPULAR SAMPLE Copied 7 times
Force Maieure. Neither party shall be liable hereunder by reason of any failure or delay in the performance of its obligations (except for the payment of money) on account of strikes, shortages, riots, insurrection, fires, flood, storm, explosions, earthquakes, Internet outages, acts of God, acts of war, acts of terrorism, governmental action, or any other cause that is beyond the reasonable control of such party.
Force Maieure. No failure or omission by either party in the performance of any obligation of this Agreement shall be deemed a breach of this Agreement or create any liability if the same shall arise from any cause or causes beyond the control of the parties, including, but not limited to, the following, which, for the purposes of this Agreement, shall be regarded as beyond the control of the party in question: Act of God; act or omission of any government; any rule, regulation or order issued by any governmental authority or by any officer, department, agency, or instrumentality thereof; fire; storm; flood; earthquake; accident; war; rebellion; insurrection; riot; invasion; strike; and lockout.
Force Maieure. Neither party shall be responsible for any damages, delay in performance or failure to perform by Physician or Practice, if caused by any act or occurrence beyond its reasonable control such as embargoes, changes in government regulations or requirements (executive, legislative, judicial, military or otherwise), acts of war or terrorism, power failure, electrical surges or current fluctuations, lightning, earthquake, flood, the elements or other forces of nature, delays or failures of transportation, or acts or omissions of telecommunications common carriers. In particular, without limitation, neither Physician nor Practice shall be responsible for any interruption in Services caused by an interruption in or failure of Internet services. Physician recognizes that any such Internet or network outage if lasting more than a single 10 hour work shift may, if Practice scheduling allows, be credited against Physician’s vacation time or may otherwise result in a prorated reduction in the contract minimum cash payment to the Physician.
Force Maieure. Neither Party shall lose any rights hereunder or be liable to the other Party for damages or losses (except for payment obligations) on account of failure of performance by the defaulting Party if the failure is occasioned by war, strike, fire, act of terrorism, Act of God, earthquake, flood, lockout, embargo, governmental acts or orders or restrictions, failure of suppliers (including, without limitation, energy suppliers), or any other reason where failure to perform is beyond the reasonable control and not caused by the negligence, intentional conduct or misconduct of the nonperforming Party and the nonperforming Party has exerted reasonable efforts to avoid or remedy such force majeure; provided, however, that in no event shall a Party be required to settle any labor dispute or disturbance.
Force Maieure. In the event performance Of this Agreement, or any obligation hereunder, is either directly or indirectly prevented, restricted, or interfered by reason of tire, earthquake or acts of God, wars, revolution, commotion, explosion, acts of public enemy, embargo, acts of the government in its sovereign capacity, labor difficulties, including limitation, strikes, slowdowns, picketing, or boycotts, unavailability of equipment from vendor, changes requested by Customer, or any other circumstances beyond the reasonable control and without the fault or the Party affected, the Party affected, upon giving prompt notice to the other party, shall be excused from such performance on a day-today basis to the extent of such prevention, restriction, or interference (and the other Party shall likewise be excused from performance of its obligations on a day-to-day basis until the delay, restriction or interference has ceased): provided however, that the Party so affected shall use diligent efforts to avoid or remove such causes of nonperformance and both Parties shall proceed whenever such causes are removed or cease
Force Maieure. Notwithstanding anything to the contrary contained herein, Transfer Agent shall not be liable for any delays or failures in performance resulting from acts beyond its reasonable control including, without limitation, acts of God, terrorist acts, shortage of supply, breakdowns or malfunctions, interruptions or malfunction of computer facilities, or loss of data due to power failures or mechanical difficulties with information storage or retrieval systems, labor difficulties, war, or civil unrest; provided however, that Transfer Agent shall have taken commercially reasonable efforts to minimize the likelihood of occurrence of such circumstances or to mitigate any loss or damage to a Company caused by such circumstances.
Force Maieure. If by reason of strikes or other labor disputes, fire or other casualty (or reasonable delays in adjustment of insurance), accidents, orders or regulations of any Federal, State, County or Municipal authority, or any other cause beyond a party’s reasonable control, such party is unable to furnish or is delayed in furnishing any utility or service required to be furnished by such party under the provisions of this Lease or is unable to perform or make or is delayed in performing or making any installations, decorations, repairs, alterations, additions or improvements, or is unable to fulfill or is delayed in fulfilling any of such party’s other obligations under this Lease (other than the payment of Rent), no such inability or delay shall constitute an actual or constructive eviction, in whole or in part, or entitle the other party to any abatement or diminution of Fixed Rent, or relieve the other party from any of its obligations under this Lease, or impose any liability upon such party or its agents, by reason of inconvenience or annoyance to the other party, or injury to or interruption of the other party’s business, or otherwise.
Force Maieure. 13.01 In the event either party is unable to perform its obligations under the terms of this Agreement because of acts of God, strikes, equipment or transmission failure or damage reasonably beyond its control, or other causes reasonably beyond its control, such party shall not be liable for damages to the other for any damages resulting from such failure to perform or otherwise from such causes.
Force Maieure. Landlord and Tenant, except for the payment of rent, shall be excused for the period of any delay in the performance of any obligation hereunder when such delay is occasioned by causes beyond its control, including but not limited to work stoppages, boycotts, slowdowns or strikes; shortages of materials, equipment, labor or energy; unusual weather conditions; or acts or omissions of governmental or political bodies.
Force Maieure lt is expressly understood and agreed by the Parties to this Agreement that, if the performance of any provision of this Agreement is delayed by force majeure, defined as reason of war, civil commotion, act of God, governmental restriction, regulation or interference, fire, explosion, hurricane, flood, failure of transportation, court injunction, or any circumstances which are reasonably beyond the control of the Party obligated or permitted under the terms of this Agreement to do or perform the same, regardless of whether any such circumstance is similar to any of those enumerated herein, the Party so obligated or permitted shall be excused from doing or perfonning the same during such period of delay, so that the period of time applicable to such requirement shall be extended for a period of time equal to the period of time such Party was delayed. Each Party must infonn the other in writing within reasonable time of the existence of such force majeure.