Final Acceptance Certificate Sample Clauses

Final Acceptance Certificate. Final Acceptance Certificate has the meaning set out in GC 5.8.1.
AutoNDA by SimpleDocs
Final Acceptance Certificate. 5.8.1 The Contract Administrator shall issue the final acceptance certificate (“Final Acceptance Certificate”) after the later of the:
Final Acceptance Certificate. Certificate(s) issued by the Engineer to the Contractor at the end of the defects notification period stating that the Contractor has completed his obligations to construct, complete, and maintain the works concerned.
Final Acceptance Certificate. To: [Name of Supplier] [Street] [City] [Country of origin] From: Israel Railways Ltd. 1 Yoseftal St. Lod 7136801 Israel We hereby certify that the R350HT Rails as defined in the Agreement No. , which was ordered by Israel Railways Ltd. ("ISR") according to the Agreement has been accepted and taken over by ISR after the performance of Acceptance Checks. THIS CERTIFICATE IS ISSUED WITHOUT PREJUDICE TO THE RIGHTS AND POWERS OF ISR UNDER THE AFORESAID CONTRACT. Signed: Israel Railways Ltd. Name Date Confirmed: Signed: for [Name of The Supplier] Name Date Annex E
Final Acceptance Certificate. The Principal, with the prior written consent of the Technical Adviser and of the Financing Entity, shall issue the Final Acceptance Certificate as per Annex 16 upon the satisfaction of the following conditions, · the System has passed successfully the First and Second Reassessment Test and/or any related Performance Liquidated Damages have been paid by the Contractor. · the IAC has been issued; · agreement with the GSE and the Incentive are in force with reference to the collection of the electrical energy produced by the System; · all the obligations related to the regulation of access to the grids have been fulfilled; · the O&M guarantee foreseen under the O&M Agreement is in place.
Final Acceptance Certificate. 33.1 Final acceptance certificate will be issued subject to the following: - “Thirty Six (36) months of satisfactory operation/performance after issuance of Provisional Acceptance Certificate, replacement of defective parts and material and removal of all discrepancies”.
Final Acceptance Certificate. When Contractor considers that the criteria for Final Acceptance for the Facility have been met, Contractor shall so notify Owner in writing by delivering to Owner a Final Acceptance Certificate. Within five (5) Business Days after Owner’s receipt of the Final Acceptance Certificate, Owner shall either (i) notify Contractor that Final Acceptance has been achieved and execute the Final Acceptance Certificate noting that the Final Acceptance Date is the date on which Owner received the Final Acceptance Certificate, or (ii) notify Contractor that Final Acceptance has not been achieved and provide a detailed explanation of the reasons therefor, except that if Owner requires additional time for review, then Owner shall provide Contractor written notice of the need for such additional time during the five (5) Business Day period recited above, and, if Owner subsequently rejects the Final Acceptance Certificate, then the Contractor may request a Change Order for a day for day adjustment to the Project Schedule for each day after the fifth (5th) Business Day until the day on which the Owner issues the rejection of the Final Acceptance Certificate. Owner shall in all events diligently cooperate with respect to Contractor’s ongoing performance of Work scheduled, if any, during the pendency of Owner’s review of the Final Acceptance Certificate. In the event Owner rejects a Final Acceptance Certificate delivered by Contractor, the Parties shall thereupon promptly and in good xxxxx xxxxxx and make all reasonable efforts to resolve the applicable issue. If such issue is not resolved within five (5) Business Days of the delivery by Owner of its notice of rejection to Contractor, the Parties shall refer the matter for determination in accordance with the dispute resolution provisions of Section 16.3. If Owner’s rejection is a result of identified defects or deficiencies in the Work, Contractor shall correct such defects or deficiencies and/or perform such Work and the foregoing notice procedure shall be repeated until the requirements for Final Acceptance have been met.
AutoNDA by SimpleDocs
Final Acceptance Certificate. 10.10 The Developer shall give notice to the Municipality of the expiration of the Warranty Period and request a Final Acceptance Certificate and inspection in respect of the Local Improvements not more than sixty (60) days prior to the expiration of any Warranty Period.
Final Acceptance Certificate. When the conditions set forth in Section 17.6.1 have occurred, Contractor shall submit to Owner a duly executed and completed Final Acceptance Certificate, which certificate shall set forth the date that Final Acceptance is deemed to have occurred as described above.
Final Acceptance Certificate. Once the Software has completed Simulations successfully, the CBOT shall promptly sign and deliver to LIFFE's Project Manager a Final