Common use of Filing of Claims Clause in Contracts

Filing of Claims. No extension of the Contract Time shall be made for delay occurring more than ten (10) days before claim therefor is made in writing to the Engineer with a copy to the Owner. In the case of a continuing cause of delay, only one claim is necessary, but no claim for a continuing delay shall be valid unless the Contractor, within ten (10) days of the commencement of the delay, shall have given notice in writing to the Engineer, with copy to the Owner.

Appears in 12 contracts

Samples: Contract Agreement, Macon Water Authority, Macon Water Authority

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.