Field Changes Sample Clauses

Field Changes. Notwithstanding any provision of this Contract to the contrary, the COR may make Field Changes to this Contract that do not change the Contract Sum or the Contract Time or the purpose or intent of the Specifications. Substitution requests as defined in Section 1.13.K will be approved in the form of a Field Change. Each Field Change shall be in writing and shall be signed by the COR and Contractor. All inquiries about Field Changes will be referred directly to the COR.
AutoNDA by SimpleDocs
Field Changes. 4.7.1 Changes in location of ADL-contaminated soil placement, quantities or protection measures from the original design (field changes) shall be noted in the Resident Engineer's Diary within five (5) days of the field change.
Field Changes. Landlord shall have the right to make non-material changes to Landlord’s Work based upon field conditions, provided that Landlord shall give Tenant prompt notice thereof.
Field Changes. Architect and Contractor will sign a Field Change order listing the Change In The Work and the Contract Sum including markups before Contractor proceeds with the Field Change.
Field Changes. (a) During the pendency of the construction of the Project, the Bills shall have the right to implement Field Changes in accordance with this Section 3.5(a). To the extent that the Bills seek a Field Change, the Bills shall orally notify the other Parties of the proposed Field Change and shall furnish the other Parties with an explanation of the rationale therefore. Within a reasonable period of time following the receipt of such notice given the magnitude and scope of the proposed Field Change [but in no event later than twenty-four (24) hours after the receipt of such notice], each of the other Parties shall orally notify the Bills of its approval or rejection of the proposed Field Change. In considering any proposed Field Change, each Party’s approval shall not be unreasonably withheld, conditioned or delayed. In the event any proposed Field Change is disapproved by the County, such disapproval shall not be considered unreasonable to the extent it is predicated on: (i) the failure of the proposed Field Change to comply with Applicable Law or (ii) the impact of the proposed Field Change on the County's Structural Repair obligations pursuant to the terms and conditions of the Lease Agreements.
Field Changes. The URS RPR shall coordinate the preparation and issuance of contract revisions, if required, during construction to resolve problems due to unanticipated field conditions or other field changes. The URS RPR shall coordinate revisions of the Contract Documents with the URS Project Manager and shall consult with and advise the City on contract changes and related issues. These contract revisions may or may not result in change orders. Task 5.2.12―Weekly Construction Progress Meetings XXX assumed no charge and that the efforts provided by URS under existing contract to modify the Hinckley treatment plant will be sufficient to handle the construction of the blending facility.
Field Changes. (a) The Coach Member will make a representative available to approve or disapprove Field Changes which are subject to the Coach Member’s approval in accordance with the provisions of Section 3.04 within no more than three (3) Business Days following the receipt of such information and materials as shall be reasonably required to consider such proposed Field Change (including the estimated cost and Schedule impact (if any) of the proposed Field Change). If the Coach Member does not approve or disapprove a Field Change which is subject to the Coach Member’s approval (in accordance with the provisions of Section 3.04) within such three (3) Business Day period, then the Coach Member will be deemed to have approved such Field Change.
AutoNDA by SimpleDocs
Field Changes. 13.1 During the course of the Work, certain changes in the Work may be required and completed pursuant to oral discussions between RAS and Continental's Field Representative. Such changes are those which do not affect the cost or the schedule of the Work or which do not result in a material change in the approved request and obtain authorization from Continental, as provided in Article 14 hereof. RAS should not have such authority.
Field Changes. In the event that a Product field change is mandatory, McDATA will promptly provide Buyer a full description of the problem and resolution, and any hardware or software required. Buyer will provide such information, hardware and software to Service Providers and End Users.
Field Changes. The Contractor shall provide for on-site Field Changes for all products supplied to FedEx on the same basis that they are furnished to other customers using the same type of equipment and software. Contractor shall report to FedEx on a periodic basis not greater than once each quarter the existence of all Field Changes that have been made available by Contractor for the products supplied to FedEx. For purposes of this paragraph, Field Changes shall refer to changes that are applied generally to the product line which FedEx's products are in and which are intended to correct a defect or omission, to increase reliability, to enhance the functionality, to improve the logic, or to make any other improvement in any equipment or software that is supplied to FedEx under this Agreement. Such periodic report shall include an estimate of the time necessary to install each such Field Change; the schedule for implementing, and the effect of installing each Field Change on the functionality of FedEx's VECSA System. FedEx reserves the right to require Contractor to modify the schedule for installing Field Changes to accommodate FedEx's needs.