Failure of Utility Owners to Cooperate Sample Clauses

Failure of Utility Owners to Cooperate. 7.5.7.1 Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Adjustments. Developer shall notify TxDOT immediately if (a) Developer is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Utility Agreement within a reasonable time, (b) Developer reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Facility, (c) Developer becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-upon work or approvals, or (d) any other dispute arises between Developer and a Utility Owner with respect to the Facility, despite Xxxxxxxxx's diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such notice may include a request that TxDOT assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. Developer shall provide TxDOT with such information as TxDOT requests regarding the Utility Owner's failure to cooperate and the effect of any resulting delay on the Facility Schedule. After delivering to TxDOT any notice or request for assistance, Developer shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.
AutoNDA by SimpleDocs
Failure of Utility Owners to Cooperate. 6.8.4.1 DB Contractor shall use best efforts to obtain the cooperation of each Utility Owner as necessary for the Utility Adjustment. DB Contractor shall notify TxDOT immediately if: (a) DB Contractor is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Utility Agreement within a reasonable time, (b) DB Contractor reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project, (c) DB Contractor becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed- upon work or approvals, or (d) any other dispute arises between DB Contractor and a Utility Owner with respect to the Project, despite DB Contractor's diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such notice may include a request that TxDOT assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. DB Contractor shall provide TxDOT with such information as TxDOT requests regarding the Utility Owner's failure to cooperate and the effect of any resulting delay on the Project Schedule. After delivering to TxDOT any notice or request for assistance, DB Contractor shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.
Failure of Utility Owners to Cooperate. 7.5.7.1 Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Adjustments. Developer shall notify TxDOT immediately if
Failure of Utility Owners to Cooperate. 6.7.1 Design-Build Contractor shall make diligent efforts to obtain the cooperation of each Utility Owner as necessary for the Project. Design-Build Contractor shall notify IFA immediately if (a) Design-Build Contractor is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Utility Agreement within a reasonable time, (b) Design-Build Contractor reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project or in accordance with Governmental Rules, the Governmental Approvals or the PPA Documents, (c) Design-Build Contractor becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-upon work or approvals, or (d) any other dispute arises between Design-Build Contractor and a Utility Owner with respect to the Project, despite Design-Build Contractor’s diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such notice may include a request that IFA assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. Design-Build Contractor shall provide IFA with such information as IFA requests regarding the Utility Owner’s failure to cooperate and the effect of any resulting delay on the Project Schedule. After delivering to IFA any notice or request for assistance, Design-Build Contractor shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.
Failure of Utility Owners to Cooperate. (i) The Development Entity shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Relocations to be performed in connection with the Work. The Development Entity shall notify the Department promptly if the Development Entity reasonably believes that:
Failure of Utility Owners to Cooperate. 6.8.4.1 Developer shall use best efforts to obtain the cooperation of each Utility Owner as necessary for the Utility Adjustment. Developer shall notify TxDOT immediately if: (a) Developer is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Utility Agreement within a reasonable time, (b) Developer reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project, (c) Developer becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-upon work or approvals, or
Failure of Utility Owners to Cooperate. 6.7.4.1. DB Contractor shall use best efforts to obtain the cooperation of each Utility Owner as necessary for the Utility Adjustment. DB Contractor shall notify TxDOT immediately if: (a) DB Contractor is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Utility Agreement within a reasonable time, (b) DB Contractor reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project, (c) DB Contractor becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-upon work or approvals, or
AutoNDA by SimpleDocs
Failure of Utility Owners to Cooperate. (a) The Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for the Utility Adjustments to be performed in connection with the Work. The Developer shall notify the District promptly if the Developer reasonably believes that:

Related to Failure of Utility Owners to Cooperate

  • Subcontractor Insurance Requirements Consultant shall require each of its subcontractors that perform Services under this Agreement to maintain insurance coverage that meets all of the requirements of this Section.

  • Oversight of Subcontractors In the event that Vendor engages subcontractors or other authorized persons or entities to perform one or more of its obligations under the Master Agreement (including subcontracting hosting of the Protected Data to a hosting service provider), it will require those subcontractors or other authorized persons or entities to whom it will disclose the Protected Data to execute legally binding agreements acknowledging their obligation under Section 2-d of the New York Education Law to comply with all applicable data protection, privacy and security requirements required of Vendor under the Master Agreement and applicable state and federal law and regulations.