Common use of Excusable Delay Clause in Contracts

Excusable Delay. Delay that extends the completion of the Work and that is caused by circumstances beyond the control of Contractor or its Subcontractors, suppliers, or vendors are Excusable Delay. Contractor is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor shall document its claim for any time extension as provided in Article 40 hereof. Failure of Contractor to comply with Article 40 hereof as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.

Appears in 8 contracts

Samples: www.broward.org, www.southwestranches.org, www.southwestranches.org

AutoNDA by SimpleDocs

Excusable Delay. Delay that which extends the completion of the Work and that which is caused by circumstances beyond the control of Contractor or its Subcontractorssubcontractors, material persons, suppliers, or vendors are is Excusable Delay. Contractor is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor shall document its claim for any time extension extensions as provided in Article 40 hereofSection 9.1 herein. Failure of Contractor to comply with Article 40 hereof Section 9.1 herein as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.

Appears in 4 contracts

Samples: Construction Agreement, Construction Agreement, Construction Agreement

Excusable Delay. Delay that which extends the completion of the Work and that which is caused by circumstances beyond the control of Contractor or its Subcontractorssubcontractors, suppliers, suppliers or vendors are is Excusable Delay. Contractor is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor shall document its claim for any time extension as provided in Article 40 Section 39 hereof. Failure of Contractor to comply with Article 40 Section 39 hereof as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.:

Appears in 2 contracts

Samples: Contract, legistarweb-production.s3.amazonaws.com

Excusable Delay. Delay that which extends the completion of the Work and that which is caused by circumstances beyond the control of Contractor CONTRACTOR or its Subcontractors, material persons, suppliers, or vendors are Excusable Delay. Contractor CONTRACTOR is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor CONTRACTOR shall document its claim for any time extension extensions as provided in Article 40 hereofSection 6.5 herein. Failure of Contractor CONTRACTOR to comply with Article 40 hereof Section 6.5 herein as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.

Appears in 1 contract

Samples: Construction Agreement

Excusable Delay. Delay that which extends the completion of the Work and that which is caused by circumstances beyond the control of Contractor or its Subcontractors, suppliers, or vendors are Excusable Delay. Contractor is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor shall document its claim for any time extension as provided in Article 40 hereof. Failure of Contractor to comply with Article 40 hereof as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.

Appears in 1 contract

Samples: www.broward.org

AutoNDA by SimpleDocs

Excusable Delay. Delay that which extends the completion of the Work and that which is caused by circumstances beyond the control of Contractor or its Subcontractors, suppliers, or vendors are Excusable Delay. Contractor is entitled to a time extension of the Contract Time for each day the Work is delayed due to Excusable Delay. Contractor shall document its claim for any time extension as provided in Article 40 hereof. Failure of Contractor to comply with Article 40 hereof as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided belownon‐compensable.

Appears in 1 contract

Samples: 005200 Contract

Excusable Delay. Delay that which extends the completion of the Work and that work which is caused by circumstances beyond the control of Contractor CONTRACTOR or its Subcontractorssubcontractors, materials persons, suppliers, or vendors are is Excusable Delay. Contractor CONTRACTOR is entitled to a time extension of the Contract Time for each day the Work work is delayed due to Excusable Delayexcusable delay. Contractor CONTRACTOR shall document its claim for any time extension extensions as provided in Article 40 6.3 hereof. Failure of Contractor CONTRACTOR to comply with Article 40 6.3 hereof as to any particular event of delay shall be deemed conclusively to constitute a waiver, abandonment, abandonment or relinquishment of any and all claims resulting from that particular event of delay. Excusable Delay may be compensable or non-compensable, as provided below.

Appears in 1 contract

Samples: Contract by And