Common use of Equipment Procurement Clause in Contracts

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 48 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Provider's Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by Transmission OwnerProvider, then Transmission Owner Provider shall commence design of the Transmission Owner’s Provider's Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 36 contracts

Samples: Surplus Large Generator Interconnection Agreement, Agreement, Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades Attachment Facilities or System Upgrade Facilities is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, Attachment Facilities or System Upgrade Facilities and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties Developer and Transmission Owner otherwise agree in writing:

Appears in 23 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Interconnecting Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by the Interconnecting Transmission Owner, then the Interconnecting Transmission Owner shall commence design of the Interconnecting Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 21 contracts

Samples: Interconnection Agreement, Via Electronic Filing, Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades 's Attachment Facilities or System Upgrade Facilities is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, 's Attachment Facilities or System Upgrade Facilities and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties Developer and Transmission Owner otherwise agree in writing:

Appears in 18 contracts

Samples: Large Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 15 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Interim Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades Attachment Facilities or System Upgrade Facilities is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the the‌ Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, Attachment Facilities or System Upgrade Facilities and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties Developer and Transmission Owner otherwise agree in writing:

Appears in 9 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission OwnerProvider’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by Transmission OwnerProvider, then Transmission Owner Provider shall commence design of the Transmission OwnerProvider’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 9 contracts

Samples: Generator Interconnection Agreement, Study Agreement, Large Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 7 contracts

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.), Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Provider's Interconnection Facilities, Network Upgrades and/or Upgrades, or Distribution Upgrades is to be borne by Transmission OwnerProvider, then Transmission Owner Provider shall commence design of the Transmission Owner’s Provider's Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, or Distribution Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 3 contracts

Samples: Generator Interconnection Agreement, Standard Generator Interconnection Agreement, Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades Attachment Facilities or System Upgrade Facilities is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, Attachment Facilities or System Upgrade Facilities and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties Developer and Transmission Owner otherwise agree in writing:writing:‌

Appears in 2 contracts

Samples: Interconnection Agreement, Interconnection Agreement

Equipment Procurement. If responsibility for construction of the an Interconnecting Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by the Interconnecting Transmission Owner, then the Interconnecting Transmission Owner shall commence design of the Interconnecting Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or FERC Electric Tariff Generator Interconnection Agreement (GIA) ATTACHMENTS 92.0.0 Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 1 contract

Samples: Generator Interconnection Agreement

Equipment Procurement. If responsibility for construction of the Transmission Owner’s 's Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by the Transmission Owner, then the Transmission Owner shall commence design of the Transmission Owner’s 's Interconnection Facilities, Network Upgrades and/or Distribution Upgrades, and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:

Appears in 1 contract

Samples: Generator Interconnection Agreement