Common use of Early Construction of Base Case Facilities Clause in Contracts

Early Construction of Base Case Facilities. In accordance with Section 12.2.2 of Transmission Provider’s GIP, Interconnection Customer may request Transmission Provider to construct all or any portion of any Network Upgrades required for Interconnection Customer to be interconnected to the Transmission System which are included in the Base Case of the Facilities Study for Interconnection Customer, and which also are required to be constructed for another Interconnection Customer, but where such construction is not scheduled to be completed in time to achieve Interconnection Customer's In-Service Date. In accordance with Section 12.2.3 of Transmission Provider’s GIP, Interconnection Customer also may request that Transmission Provider advance the construction of all or any portion of any Network Upgrades that are part of Transmission Provider’s most recent transmission planning assessment study, performed to comply with Applicable Reliability Standards, but would not otherwise be completed in time to support the Interconnection Customer’s In-Service Date. Provided that Interconnection Customer pays the costs for constructing such Network Upgrades, Transmission Provider shall use Reasonable Efforts to construct those Network Upgrades in accordance with Interconnection Customer's In-Service Date. Interconnection Customer shall be entitled to transmission rate credits for costs paid by Interconnection Customer to Transmission Provider for the construction of these Network Upgrades, including but not limited to the costs it paid to expedite construction, in accordance with Article 11.5 of this GIA.

Appears in 3 contracts

Samples: Generator Interconnection Agreement, Standard Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Early Construction of Base Case Facilities. In accordance with Section 12.2.2 of Transmission Provider’s GIP, Interconnection Customer may request Transmission Provider to construct all or any portion of any Network Upgrades required for Interconnection Customer to be interconnected to the Transmission System which are included in the Base Case of the Facilities Study for Interconnection Customer, and which also are required to be constructed for another Interconnection Customer, but where such construction is not scheduled to be completed in time to achieve Interconnection Customer's In-Service Date. In accordance with Section 12.2.3 of Transmission Provider’s GIP, Interconnection Customer also may request that Transmission Provider advance the construction of all or any portion of any Network Upgrades that are part of Transmission Provider’s most recent transmission planning assessment study, performed to comply with Applicable Reliability Standards, but would not otherwise be completed in time to support the Interconnection Customer’s In-Service Date. Provided that Interconnection Customer pays the costs for constructing such Network Upgrades, Transmission Provider shall use Reasonable Efforts to construct those Network Upgrades in accordance with Interconnection Customer's In-Service Date. Interconnection Customer shall be entitled to transmission rate credits for costs paid by Interconnection Customer to Transmission Provider for the construction of these Network UpgradesUpgrades identified in Appendix A, including but not limited to the costs it paid to expedite construction, in accordance with Article 11.5 of this GIA.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Early Construction of Base Case Facilities. In accordance with Section 12.2.2 of Transmission Provider’s GIP, Interconnection Customer may request Transmission Provider to construct all or any portion of any Network Upgrades required for Interconnection Customer to be interconnected to the Transmission System which are included in the Base Case of the Facilities Study for Interconnection Customer, and which also are required to be constructed for another Interconnection Customer, but where such construction is not scheduled to be completed in time to achieve Interconnection Customer's In-In- Service Date. In accordance with Section 12.2.3 of Transmission Provider’s GIP, Interconnection Customer also may request that Transmission Provider advance the construction of all or any portion of any Network Upgrades that are part of Transmission Provider’s most recent transmission planning assessment study, performed to comply with Applicable Reliability Standards, but would not otherwise be completed in time to support the Interconnection Customer’s In-Service Date. Provided that Interconnection Customer pays the costs for constructing such Network Upgrades, Transmission Provider shall use Reasonable Efforts to construct those Network Upgrades in accordance with Interconnection Customer's In-Service Date. Interconnection Customer shall be entitled to transmission rate credits for costs paid by Interconnection Customer to Transmission Provider for the construction of these Network Upgrades, including but not limited to the costs it paid to expedite construction, in accordance with Article 11.5 of this Transitional Cluster GIA.

Appears in 1 contract

Samples: Cluster Generator Interconnection Agreement