Common use of Early Construction of Base Case Facilities Clause in Contracts

Early Construction of Base Case Facilities. Developer may request National Grid to construct, and National Grid shall construct, subject to a binding cost allocation agreement reached in accordance with Attachment S to the NYISO OATT, including Section 25.8.7 thereof, using Reasonable Efforts to accommodate Developer’s In-Service Date, all or any portion of any System Upgrade Facilities or System Deliverability Upgrades required for Developer to be interconnected to the New York State Transmission System which are included in the Base Case of the Facilities Study for the Developer, and which also are required to be constructed for another Developer, but where such construction is not scheduled to be completed in time to achieve Developer’s In-Service Date.

Appears in 8 contracts

Samples: Large Generator Interconnection Agreement, Service Agreement, Service Agreement