Common use of Delay Liquidated Damages Clause in Contracts

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 4 contracts

Samples: Engineering, Procurement and Construction Agreement (Cheniere Energy Inc), Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC), Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC)

AutoNDA by SimpleDocs

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 3 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 4 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 3 contracts

Samples: Escrow Agreement, Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC), Escrow Agreement (Cheniere Energy Partners, L.P.)

AutoNDA by SimpleDocs

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 5 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 1 contract

Samples: Escrow Agreement (Cheniere Energy Partners, L.P.)