Defects Notification Period Sample Clauses

Defects Notification Period. The period stated in the contract immediately following the date of provisional acceptance, during which the Contractor is required to complete the works and to remedy defects or faults as instructed by the Engineer.
AutoNDA by SimpleDocs
Defects Notification Period. The Defects Notification Period will commence on the Date of Practical Completion and will continue for six (6) months (unless some other period is stated in the Special Conditions) or until the issue of the Final Completion Certificate.
Defects Notification Period. The Defects Notification Period shall be: (3 Months unless otherwise stated) • For the Contract Works: 12 Months • For any Separable Portions: N/A
Defects Notification Period. The progress of Works is to be evidenced by the Contractor with each Payment Application and the Schedule of Payments shall be adjusted in case of non-compliance with the targets.
Defects Notification Period. 3 years.
Defects Notification Period. The Employer shall be entitled subject to Sub-Clause 2.5 [Employer’s Claims] to an extension of the Defects Notification Period for the Works or a Section if and to the extent that the Works, Section or a major item of Plant (as the case may be, and after taking over) cannot be used for the purposes for which they are intended by reason of a defect or by reason of damage attributable to the Contractor. However, a Defects Notification Period shall not be extended by more than two years. If delivery and/or erection of Plant and/or Materials was suspended under Sub-Clause 8.8 [Suspension of Work] or Sub- Clause 16.1 [Contractor’s Entitlement to Suspend Work], the Contractor’s obligations under this Clause shall not apply to any defects or damage occurring more than two years after the Defects Notification Period for the Plant and/or Materials would otherwise have expired.
Defects Notification Period. ‌ Defects Notification Period is 12 (twelve) months for the installations of moorings and 24 (twenty-four) months for the lanterns upon issuing the Taking-Over Certificate by the Employer. Following the Taking-Over Certificate, during the guarantee period, any defects, malfunctions, breakdowns occurring due to poor workmanship of the Contractor or due to supply of defective materials by the Contractor shall be notified to Contractor by Port Management. Contractor is obliged to remobilize to job site and correct such defects at its own cost. At the end of the defect liability period, all warranties by the Contractor are null and void. However, Contractor shall ensure that, upon call from Client regarding correction/repair of the Works, Contractor shall remobilize to job site and execute the repairs as part of a separate Job Order.
AutoNDA by SimpleDocs
Defects Notification Period. 7.1 Type of Contract The Contract is a [lump sum contract governed by 7.2.1 / cost reimbursement contract governed by 7.2.2]
Defects Notification Period. Good User Acceptance Testing is crucial to avoid issues in production. Where issues are found after a period of thirty (30) days from Go Live, identification and rectification will be invoiced in accordance with Schedule 2.

Related to Defects Notification Period

  • Union Notification The Union shall be notified of all appointments, hirings, layoffs, transfers, recalls and terminations of employment.

  • Termination Notice for Force Majeure Event If a Force Majeure Event subsists for a period of 180 (one hundred and eighty) days or more within a continuous period of 365 (three hundred and sixty five) days, either Party may in its discretion terminate this Agreement by issuing a Termination Notice to the other Party without being liable in any manner whatsoever, save as provided in this Article 34, and upon issue of such Termination Notice, this Agreement shall, notwithstanding anything to the contrary contained herein, stand terminated forthwith; provided that before issuing such Termination Notice, the Party intending to issue the Termination Notice shall inform the other Party of such intention and grant 15 (fifteen) days time to make a representation, and may after the expiry of such 15 (fifteen) days period, whether or not it is in receipt of such representation, in its sole discretion issue the Termination Notice.

  • Recall Notification Notice of recall shall be sent to the bargaining unit member by certified mail. The City shall be deemed to have fulfilled its obligation by mailing the recall notice by certified mail, return receipt requested, to the last address provided by the bargaining unit member.

  • Review Period The Asset Representations Reviewer will complete the Review of all of the Review Receivables within sixty (60) days after having received access to the Review Materials pursuant to Section 3.2(a). However, if additional Review Materials are provided to the Asset Representations Reviewer in respect of any Review Receivables pursuant to Section 3.2(b), the Review period will be extended for an additional thirty (30) days in respect of any such Review Receivables.

  • Employee Notification A copy of any disciplinary action or material related to employee performance which is placed in the personnel file shall be provided to the employee (the employee so noting receipt, or the supervisor noting employee refusal to acknowledge receipt) or sent by certified mail (return receipt requested) to the employee's last address appearing on the Employer's records.

Time is Money Join Law Insider Premium to draft better contracts faster.