Cost Responsibility for Interconnection Facilities. 4.1 Each Interconnection Request submitted to the Public Utility must be accompanied by the required processing fee, pursuant to R746-312-6(4). The Interconnection Customer will bear the cost of any interconnection or other fees and charges provided for in the Rule. The Public Utility will not require any fees or charges for the Interconnection Customer to connect to the Public Utility’s Electric Distribution System or for operation and maintenance of a Generating Facility, except for the fees provided for in the Rule and this Interconnection Agreement, pursuant to R746-312-14(2).
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 13 4.1 Interconnection Facilities 13 4.2 Distribution Upgrades 13 Article 5. Cost Responsibility for Network Upgrades 13 5.1 Applicability 13 5.2 Network Upgrades 13 5.2.1 Repayment of Amounts Advanced for Network Upgrades 14 5.3 Special Provisions for Affected Systems 15 5.4 Rights Under Other Agreements 15 Article 6. Billing, Payment, Milestones, and Financial Security 15 6.1 Billing and Payment Procedures and Final Accounting 15 6.2 Milestones 15 6.3 Advance Payment 16 Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default 17 7.1 Assignment 17 7.2 Limitation of Liability 17 7.3 Indemnity 17 7.4 Consequential Damages 18 7.5 Force Majeure 18 7.6 Default 19 Article 8. Insurance 20 Article 9. Confidentiality 20 Article 10. Disputes 21 Article 11. Taxes 22
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 13 4.1 Interconnection Facilities 13 4.2 Distribution Upgrades 13 Article 5. Cost Responsibility for Network Upgrades 13 5.1 Applicability 13 5.2 Network Upgrades 14 5.2.1 Repayment of Amounts Advanced for Network Upgrades 14 5.3 Special Provisions for Affected Systems 15 5.4 Rights Under Other Agreements 15 Article 6. Billing, Payment, Milestones, and Financial Security 15 6.1 Billing and Payment Procedures and Final Accounting 15 6.2 Milestones 16 6.3 Financial Security Arrangements 16
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 13 4.1 Interconnection Facilities 13 4.2 Distribution Upgrades 13 Article 5. Cost Responsibility for Network Upgrades 13 5.1 Applicability 13 5.2 Network Upgrades 13 5.2.1 Repayment of Amounts Advanced for Network Upgrades 14 5.3 Special Provisions for Affected Systems 15 5.4 Rights Under Other Agreements 15 Article 6. Billing, Payment, Milestones, and Financial Security 15 6.1 Billing and Payment Procedures and Final Accounting 15 6.2 Milestones 15 6.3 Advance Payment 16 Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default 17 7.1 Assignment 17 7.2 Limitation of Liability 17 7.3 Indemnity 17 7.4 Consequential Damages 18 7.5 Force Majeure 18 7.6 Default 19 Article 8. Insurance 20 Article 9. Confidentiality 20 Article 10. Disputes 21 Article 11. Taxes 22 Article 12. Miscellaneous 22 12.1 Governing Law, Regulatory Authority, and Rules 22 12.2 Amendment 22 12.3 No Third-Party Beneficiaries 22 12.4 Waiver 22 12.5 Entire Agreement 23 12.6 Multiple Counterparts 23 12.7 No Partnership 23 12.8 Severability 23 12.9 Security Arrangements 23 12.10 Environmental Releases 23 12.11 Subcontractors 24 Article 13. Notices 25 13.1 General 25 13.2 Billing and Payment 25 13.3 Alternative Forms of Notice 25 13.4 Designated Operating Representative 26 13.5 Changes to the Notice Information 26 Article 14. Signatures 27 Attachment 1 – Glossary of Terms Attachment 2 – Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment Attachment 3 – One-line Diagram Depicting the Small Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades Attachment 4 – Milestones Attachment 5 – Additional Operating Requirements for the Transmission Provider's Transmission System and Affected Systems Needed to Support the Interconnection Customer’s Needs Attachment 6 – Transmission Provider's Description of its Upgrades and Best Estimate of Upgrade Costs This Interconnection Agreement ("Agreement") is made and entered into this day of , 20 , by Western Area Power Administration, a Federal power marketing administration organized under the United States Department of Energy ("Transmission Provider"), and , a organized and existing under the laws of the State/Commonwealth of ("Interconnection Customer"), each hereinafter sometimes referred to individually as "Party" or both referred to collectively as the "Parties." Transmission Provider Information
Cost Responsibility for Interconnection Facilities. 4.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The Transmission Owner shall provide the Parties a best estimate cost, including overheads, for the purchase and construction of the Transmission Owner Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, including the Transmission Owner and the Transmission Provider.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 5 4.1 Interconnection Facilities 5 4.2 Distribution Upgrades 5 Article 5. Cost Responsibility for Network Upgrades 5 5.1 Applicability 5 5.2 Network Upgrades 5
AutoNDA by SimpleDocs
Cost Responsibility for Interconnection Facilities 

Related to Cost Responsibility for Interconnection Facilities

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Interconnection Customer’s Interconnection Facilities Construction The Interconnection Customer’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Interconnection Customer agree on another mutually acceptable deadline, the Interconnection Customer shall deliver to the Participating TO and CAISO “as-built” drawings, information and documents for the Interconnection Customer’s Interconnection Facilities and the Electric Generating Unit(s), such as: a one-line diagram, a site plan showing the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities, plan and elevation drawings showing the layout of the Interconnection Customer’s Interconnection Facilities, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Interconnection Customer's step-up transformers, the facilities connecting the Large Generating Facility to the step-up transformers and the Interconnection Customer’s Interconnection Facilities, and the impedances (determined by factory tests) for the associated step-up transformers and the Electric Generating Units. The Interconnection Customer shall provide the Participating TO and the CAISO specifications for the excitation system, automatic voltage regulator, Large Generating Facility control and protection settings, transformer tap settings, and communications, if applicable. Any deviations from the relay settings, machine specifications, and other specifications originally submitted by the Interconnection Customer shall be assessed by the Participating TO and the CAISO pursuant to the appropriate provisions of this LGIA and the LGIP.

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner.

  • Information regarding Interconnection Facilities 4.2.1 The SPD shall be required to obtain all information from the STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.

  • Participating TO's Interconnection Facilities Construction The Participating TO's Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Interconnection Customer agree on another mutually acceptable deadline, the Participating TO shall deliver to the Interconnection Customer and the CAISO the following “as-built” drawings, information and documents for the Participating TO's Interconnection Facilities [include appropriate drawings and relay diagrams]. The Participating TO will obtain control for operating and maintenance purposes of the Participating TO's Interconnection Facilities and Stand Alone Network Upgrades upon completion of such facilities. Pursuant to Article 5.2, the CAISO will obtain Operational Control of the Stand Alone Network Upgrades prior to the Commercial Operation Date.

  • Interconnection Customer Interconnection Facilities Interconnection Customer shall design, procure, construct, install, own and/or control Interconnection Customer Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at its sole expense.

  • Cost Responsibility for Network Upgrades 9 5.1 Applicability 9 5.2 Network Upgrades 9

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.