Control Estimate Sample Clauses

Control Estimate. § 15.2.1 Where the Contract Sum is the Cost of the Work, plus the Contractor’s Fee without a Guaranteed Maximum Price pursuant to Section 3.3, the Contractor shall prepare and submit to the Owner a Control Estimate within 14 days of executing this Agreement. The Control Estimate shall include the estimated Cost of the Work plus the Contractor's Fee.
AutoNDA by SimpleDocs
Control Estimate. § 2.2.1 At a time to be mutually agreed upon by the Owner and the Construction Manager and in consultation with the Architect, the Construction Manager shall prepare a Control Estimate for the Owner’s review and acceptance. The Control Estimate shall be the sum of the Construction Manager’s estimate of the Cost of the Work and the Construction Manager’s Fee and shall include those items set forth in Section 2.2.4 below. When the Control Estimate is acceptable to the Owner, the Owner shall acknowledge it in writing.
Control Estimate. B.1.1 The Design-Builder shall develop and implement a detailed system of cost control that will provide the Owner with timely information as to the anticipated total Cost of the Work. The cost control system shall compare the Estimate with the actual cost for activities in progress and estimates for uncompleted tasks and proposed changes. This information shall be reported to the Owner, in writing, no later than the Design-Builder’s first Application for Payment and shall be revised monthly or at other intervals as mutually agreed. The Design-Builder shall also comply with Division 1 Design to Budget Specification.
Control Estimate. § 2.2.1 At a time to be mutually agreed upon by the Owner and the Construction Manager and in consultation with the Architect, the Construction Manager shall prepare a Control Estimate using current information to update the most-recently prepared Preliminary Cost Estimate for the Owner’s review and acceptance. The Control Estimate shall be the sum of the Construction Manager’s estimate of the Cost of the Work and the Construction Manager’s Fee and shall include those items set forth in Section 2.2.4 below. When the Control Estimate is acceptable to the Owner, the Owner shall acknowledge it in writing. deve deve lopment by the lopment consistent t does not include h, if required, shall be
Control Estimate. § 5.2.1 The Contractor shall prepare and submit to the Owner, in writing, a Control Estimate within 30 days of executing this Agreement. The Control Estimate shall include the estimated Cost of the Work plus the Contractor’s Fee. The Control Estimate shall be used to monitor actual costs and the timely performance of the Work. The Contractor shall update the Control Estimate with each Application for Payment as needed to reflect changes in the Work.
Control Estimate. B.1.1 Where the Contract Sum is the Cost of the Work, plus the Design-Builder’s Fee without a Guaranteed Maximum Price pursuant to Section 4.3 of the Agreement, the Design-Builder shall prepare and submit to the Owner prior to the Design-Builder’s first Application for Payment, in writing, a Control Estimate. The Control Estimate shall include the estimated Cost of the Work plus the Design-Builder's Fee. The Control Estimate shall be used to monitor actual costs.
Control Estimate. § 5.2.1 The Contractor has prepared and the Owner has approved the Control Estimate attached to this Agreement as “Control Estimate” addendum. The Control Estimate includes the estimated Cost of the Work plus the Contractor’s of thto ref the para d in Fee. The Control Estimate shall be used to monitor actual costs and the timely performance Contractor shall update the Control Estimate with each Application for Payment as needed Work.
AutoNDA by SimpleDocs

Related to Control Estimate

  • Volume Estimate The estimated volumes of timber by species designated for cutting under B2.3 and expected to be cut under Utilization Standards are listed in A2. If Sale Area Map indicates that there are incom- pletely Marked subdivisions, the objective of Forest Ser- vice shall be to designate for cutting in such subdivisions sufficient timber so that Sale Area shall yield the ap- proximate estimated volume by species or species groups stated in A2. However, the estimated volumes stated in A2 are not to be construed as guarantees or limitations of the timber volumes to be designated for cut- ting under the terms of this contract. Volume adjustments shall not be made under this Section after there is modification for Catastrophic Dam- age under B8.32.

  • Cost Estimate An estimate of the total project cost including but not limited to direct expenses, indirect expenses, land cost, and capital expenses.

  • Cost Estimates If this Agreement pertains to the design of a public works project, CONSULTANT shall submit estimates of probable construction costs at each phase of design submittal. If the total estimated construction cost at any submittal exceeds ten percent (10%) of CITY’s stated construction budget, CONSULTANT shall make recommendations to CITY for aligning the PROJECT design with the budget, incorporate CITY approved recommendations, and revise the design to meet the Project budget, at no additional cost to CITY.

  • Cost Estimating The Model may be used to develop cost estimates based on the approximate data provided and conceptual estimating techniques (e.g., volume and quantity of elements or type of system selected).

  • Acceptable Estimating System The Contractor shall maintain the acceptable status of their Estimating System and submit updates to the current status, if applicable

  • Estimates and Reconciliation of Estimates Where estimated expenditures are used to determine the amount of the drawdown, the State will indicate in the terms of the State unique funding technique how the estimated amount is determined and when and how the State will reconcile the difference between the estimate and the State's actual expenditures.

  • Construction Cost Estimate At 50% completion of the contract documents, the design team will present and submit copies of the project plans and manual. The Construction Administrator will prepare and issue the fourth of five construction cost estimates. The estimate shall be derived from actual takeoffs, subcontractor and vendor input, and material and labor cost data. All quantitative systems information shall be provided in detail.

  • Preliminary Cost Estimates The Engineer shall develop a preliminary cost estimate using the Average Low Bid Unit Price. The Engineer shall estimate the total project cost including preliminary engineering, final engineering, right-of-way (ROW) acquisition, environmental compliance and mitigation, construction, utility relocation, and construction engineering inspection (CEI).

  • Preliminary Cost Estimate Consulting Engineer/Architect shall furnish City an estimate of probable Construction Cost based on the preliminary design. Consulting Engineer/Architect's estimate of probable Construction Cost is to be made on the basis of Consulting Engineer/Architect's experience and qualifications and represent Consulting Engineer/Architect's best judgment as an experienced and qualified design professional, familiar with the construction industry.

  • Estimate The Engineer shall independently develop and report quantities necessary to construct the contract in standard State bid format at the specified milestones and Final PS&E submittals. The Engineer shall prepare each construction cost estimates using Estimator or any approved method. The estimate shall be provided at each milestone submittal or in DCIS format at the 95% and Final PS&E submittals per State’s District requirement.