Contractor Applications for Payment Sample Clauses

Contractor Applications for Payment. By the 15th of each month the Contractor shall submit to the Architect/Engineer an itemized Application for Payment in accordance with the Schedule of Values. Such application shall be supported by data substantiating the Contractor's right to payment as the Owner or Architect/Engineer may require. Payment shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation into Work. If approved in writing by the Owner, payment may similarly be made for materials and equipment suitably stored off the site. Applications for Payment shall not include: • Request payments on account of changes in the Work which have not been approved by the Owner in a Change Order; and • Payment of amounts the Contractor does not intend to pay to a Subcontractor or Supplier because of a dispute or other reason. The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that all work, equipment and materials included in the Application for Payment are to the best of the Contractor's knowledge, information and belief, free from liens, claims, security interests or encumbrances.
AutoNDA by SimpleDocs
Contractor Applications for Payment. Based on the Consultant’s observation of the progress of the work for conformance with the Construction Documents and completion to the extent indicated by the Contractor, and evaluations of the Contractor’s Applications for Payments, the Consultant shall promptly review and certify the amounts due the Contractor, to the best of the Consultant’s knowledge and information.
Contractor Applications for Payment. By the 15th of each month the CONTRACTOR shall submit to the City’s Representative an itemized Application for Payment in accordance with the Schedule of Prices. Such application shall be supported by date substantiating the CONTRACTOR’s right to payment as the CITY or Project Engineer may require. Payment shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation into work. If approved in writing by the CITY, payment may similarly be made for materials and equipment suitably stored off the site. Applications for Payment not include: • Payments on account of changes in the Work which have not been approved by the CITY in a Change Order; and • Payment of amounts the CONTRACTOR does not intend to pay to a SubCONTRACTOR or Supplier because of a dispute or other reason. The CONTRACTOR warrants that the title to all Work covered by an Application for Payment will pass to the CITY no later than the time of payment. The CONTRACTOR further warrants that all work, equipment and materials included in the Application for Payment are to the best of the CONTRACTOR’s knowledge, information and belief, free from liens, claims, security interests or encumbrances.
Contractor Applications for Payment. Based on the Consultant’s observation of the progress of the work for conformance with the Construction Documents and completion to the extent indicated by the Contractor, and evaluations of the Contractor’s Applications for Payments, the Consultant shall promptly review and certify, within 5 working days, the amounts due the Contractor, to the best of the Consultant’s knowledge and information. Consultants shall complete review and provide written response within 5 business days of receipt of revised pay applications from contractors.
Contractor Applications for Payment. 2.7.3.1 Development of Payment Procedures.
Contractor Applications for Payment. By the 15th of each month the CONTRACTOR shall submit to the OWNERS AUTHORIZED REPRESENTATIVE an itemized Application for Payment in accordance with the Schedule of Values. Such application shall be supported by data substantiating the CONTRACTOR's right to payment as the OWNER or OWNERS AUTHORIZED REPRESENTATIVE may require. Payment shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation into Work. If approved in writing by the OWNER, payment may similarly be made for materials and equipment suitably stored off the site. Applications for Payment shall not include: Request payments on account of changes in the Work which have not been approved by the OWNER in a Change Order; and Payment of amounts the CONTRACTOR does not intend to pay to a Subcontractor or Supplier because of a dispute or other reason. The CONTRACTOR warrants that title to all Work covered by an Application for Payment will pass to the OWNER no later than the time of payment. The CONTRACTOR further warrants that all work, equipment and materials included in the Application for Payment are to the best of the CONTRACTOR's knowledge, information and belief, free from liens, claims, security interests or encumbrances.
Contractor Applications for Payment 
AutoNDA by SimpleDocs

Related to Contractor Applications for Payment

  • Applications for Payment 9.3.1 At least ten days before the date for each progress payment established in the State- Contractor Agreement, the Contractor shall submit to the Architect an itemized Application for Payment, notarized if required, supported by such data substantiating the Contractor's right to payment as the State or the Architect may require. The application for payment must, at a minimum, reflect retainage and the required waivers of lien and any other support documentation enumerated elsewhere in the Contract Documents.

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • REQUESTS FOR PAYMENT Payments shall be made in accordance with Article I.4 of the Special Conditions.

  • Contractor’s Submittals The Contract shall submit with reasonable promptness consistent with the Work Project Schedule and in orderly sequence all Shop Drawings, Samples, or other information required by the Contract Documents, or subsequently required by Change Order. Prior to submitting, the Contractor shall review each submittal for compliance with the Contract Documents and certify its approval by an approval stamp affixed to each copy. Submittal data presented without the Contractor’s certification will be returned without review or comment, and any delay resulting from such certification is the Contractor's responsibility.

  • Subcontractor Payments Subject to Agency’s prior approval, Agency will reimburse Outside Counsel for the actual, reasonable and necessary expenses relating to Outside Counsel’s use of subcontractors. Outside Counsel shall be responsible for any payments and other claims due to subcontractors for work performed under this OCC. Outside Counsel, in subcontracting for any performances or in support of any of the performances specified herein (e.g., expert services, local counsel, and other services), expressly understands and agrees that Agency shall not be directly liable in any manner to Outside Counsel’s subcontractor(s).

  • PAYMENT OF SUBCONTRACTORS The Contractor is obligated to take one of the two following actions within seven days after receipt of payment by the County for work performed by any subcontractor under this Contract:

  • Basis for Payment Payment(s) to Consultant for services performed under this Contract shall be made as follows and shall [not] include payment for reimbursable expenses:

  • INSTRUCTIONS FOR COMPLETING FORM A AND B Form A and Form B should be completed for Contracts for consulting services in accordance with Section XI.18.C of the Office of the State Comptroller’s Guide to Financial Operations (xxxx://xxx.xxx.xxxxx.xx.xx/agencies/guide/MyWebHelp/), “Consultant Disclosure Legislation,” and the following:

  • Request for Payment A. Not more than once every thirty days the Consultant shall file its request for payment, accompanied by evidence satisfactory to the City justifying the request for payment, including a report of Work accomplished and tasks completed, and an itemization of Eligible Expenses with copies of receipts and invoices.

  • Time for Payment Interconnection Customer must provide the additional Security, in a form and with terms as required by Section 212.4, within 15 days after its receipt of Transmission Provider’s notice under this section. The requirement for additional Security under this section shall be treated as a milestone included in the Interconnection Service Agreement pursuant to Section 212.5.