Contract Time / Construction Schedule Sample Clauses

Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall be [days in words] ([days in numbers]) calendar days, commencing with the date upon which the Facilities Lease and the Site Lease are fully executed and delivered to both Parties and ending with completion of the Work which will occur no later than [Date] (“Contract Time”). The Construction Schedule must be approved by the District.
AutoNDA by SimpleDocs
Contract Time / Construction Schedule. 12.2.2.1.The Construction shall be performed pursuant to the construction schedule(s), attached hereto as Exhibit F (“Construction Schedule(s)”). The time period between the Notice to Proceed and Completion shall be the total Contract time (“Contract Time”).
Contract Time / Construction Schedule. It hereby understood and agreed that assuming the District issues a Notice to Proceed on or before June 11, 2013, District and Developer may also approve additional changes in the Construction Schedule. District shall have beneficial occupancy on or before August 13, 2013, and Project Completion shall on or before August 23, 2013. The time period between the Notice to Proceed and Completion shall be the total Contract time (“Contract Time”). The Construction shall be performed pursuant to the construction schedule, attached hereto as Exhibit F (“Construction Schedule”). The Construction Schedule must be approved by the District prior to execution of this Facilities Lease.
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project Shall be Six-Hundred and Ninety-Three (693) calendar days, commencing on June 5, 2019, and ending with completion of the Work, which will occur no later than April 28, 2021 ("Contract Time"). The Construction Schedule must be approved by the District.
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall be Seventy-Seven (77) calendar days for construction, and be Sixty (60) calendar days for close-out, commencing with the Notice to Proceed construction phase and ending with completion of the construction work which will occur no later than [Date] and close-out [Date] (“Contract Time”). The Construction Schedule must be accepted by the District.
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for the Project shall be completed by November 20, 2020 (“Contract Time”). The Construction Schedule must be approved by the District.
Contract Time / Construction Schedule. D R A F T The Parties intend for this Project to proceed in two phases: Phase One – Abatement and Demolition; and Phase TwoNew Construction. It is hereby understood and agreed that the Contract Time for this Project shall be ( ) calendar days, commencing with the date upon which the District issues the Notice to Proceed with Construction for the first phase and ending with the date of Developer’s completion of the Work for the last phase of the Project (“Contract Time”). Contract Time for a phase will only run/accrue from the date District issues the Notice to Proceed with Construction for that phase through the date of Developer’s completion of the Work for that phase. The Construction Schedule must be approved by the District.
AutoNDA by SimpleDocs
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall commence with the date upon which the Facilities Lease and the Site Lease are fully executed and delivered to both Parties and ending with completion of the Work which will occur no later than [Date] (“Contract Time”). The Construction Schedule must be approved by the District.

Related to Contract Time / Construction Schedule

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Contract Construction 6.27.1 The parties acknowledge that each party and its counsel have reviewed this CONTRACT and that the normal rule of construction to the effect that any ambiguities are to be resolved against the drafting party shall not be employed in the interpretation of this CONTRACT or any amendment or exhibits hereto.

  • ADDITIONAL CONSTRUCTIONS The Promoter undertakes that it has no right to make additions or to put up additional structure(s) anywhere in the Project after the building plan has been approved by the competent authority(ies) except for as provided in the Act.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.