Construction Progress. If actual progress indicates that the Developer will not perform the work as scheduled, the Developer shall prepare and submit a revised schedule for the City’s reasonable approval.
AutoNDA by SimpleDocs
Construction Progress. If reasonably requested in writing by Owner at least three (3) Business Days prior to the making of an Interim Advance, attached hereto at Tab 1 is (a) an inspection report from an independent party and (b) true copies of unpaid invoices, receipted bills and Lien waivers and such other supporting information as may be requested by Owner.
Construction Progress. If reasonably requested in writing by Owner or any Assignee at least three (3) Business Days prior to the making of an Interim Advance, Owner shall have received and approved (i) an inspection report from an independent party satisfactory to Owner or any Assignee, if any, covering conformity of the work to the Unit Plans, quality of work completed, percentage of work completed and (ii) true copies of unpaid invoices, receipted bills and Lien waivers, and such other reasonably available supporting information as Owner or any Assignee may reasonably request.
Construction Progress. Owner and Assignee shall have received, if requested by Owner or Assignee, (i) all progress reports delivered under the EPC Contract, (ii) true copies of unpaid invoices, receipted bills and Lien waivers, and such other reasonably available supporting information as Owner or any Assignee may reasonably request and (iii) a certificate from Agent certifying to Owner and Assignee the amount of Unreimbursed Project Costs outstanding on the date of such Interim Advance.
Construction Progress. In the case of advances to pay costs of constructing and equipping of the Improvements, at Lender's option, Lender shall have received and approved a draw request signed by the Developer, satisfactory in form and substance to Lender, with appropriate insertions, accompanied by true copies of unpaid invoices, receipted bills and lien waivers, and such other supporting information as Lender may request.
Construction Progress. The TCF Administrative Agent shall have received satisfactory evidence that (i) that the construction of the Project is proceeding substantially in accordance with the construction schedule set out in the Construction Budget and Schedule or, if not so proceeding, any delays will not result in Substantial Completion under each P1 EPC Contract not being completed by the Date Certain and (ii) as to the existence of sufficient funds needed to achieve Substantial Completion under each P1 EPC Contract by the Date Certain.
Construction Progress. The P1 Administrative Agent shall have received satisfactory evidence that (i) that the construction of the Project is proceeding substantially in accordance with the construction schedule set out in the Construction Budget and Schedule or, if not so proceeding, any delays will not result in Substantial Completion under each P1 EPC Contract not being completed by the Date Certain and (ii) as to the existence of sufficient funds needed to achieve Substantial Completion under each P1 EPC Contract by the Date Certain.
AutoNDA by SimpleDocs
Construction Progress. Attached hereto at Tab 1 are (a) all progress reports delivered under the EPC Contract and requested by Owner or Assignee, (b) true copies of unpaid invoices, receipted bills and Lien waivers requested by Owner or Assignee, and such other reasonably requested supporting information as has been requested by Owner or Assignee and (c) a certificate from Agent certifying to Owner and Assignee the amount of Unreimbursed Project Costs outstanding on the date of this Interim Advance.
Construction Progress. Attached hereto at Tab 3 are (a) copies of all progress reports delivered under the EPC Contract and requested by Owner or Assignee and (b) true copies of unpaid invoices, receipted bills and Lien waivers requested by Owner or Assignee, and such other reasonably available supporting information as may have reasonably been requested by Owner or Assignee.
Construction Progress. Owner and Assignee shall have received, if requested by Owner, (i) all Monthly Progress Reports (as defined in the EPC Contract) delivered under the EPC Contract, (ii) true copies of unpaid invoices, receipted bills and Lien waivers (to the extent such Lien waivers are required under the EPC Contract or any other Project Contract), and such other reasonably available supporting information as Owner or Assignee may reasonably request and (iii) a certificate from Agent certifying to Owner and Assignee the amount of Unreimbursed Project Costs outstanding on the date of such Interim Advance.