Construction Completion. Following achievement of Traffic Availability, the Contractor shall diligently proceed to Construction Completion. When the Contractor has advised that Construction Completion has been achieved, the Province will do a further inspection (which shall be carried out jointly with the Contractor if so requested by the Contractor) and, when all noted deficiencies from the Project Requirements have been rectified, will issue a certificate confirming Construction Completion.
Appears in 2 contracts
Samples: CNR Vegreville Agreement, www.transportation.alberta.ca
Construction Completion. Following achievement of Traffic Availability, the Contractor shall diligently proceed to Construction Completion. When the Contractor has advised that Construction Completion has been achieved, the Province will do a further inspection (which shall be carried out jointly with the Contractor if so requested by the Contractor) and, when all noted deficiencies from in the Project Requirements have been rectified, will issue a certificate confirming Construction Completion.
Appears in 2 contracts
Samples: www.transportation.alberta.ca, www.transportation.alberta.ca
Construction Completion. Following achievement of RNI Traffic Availability, the Contractor shall diligently proceed to Construction Completion. When the Contractor has advised that Construction Completion has been achieved, the Province will do a further inspection (which shall be carried out jointly with the Contractor if so requested by the Contractor) and, when all noted deficiencies from the Project Requirements have been rectified, will issue a certificate confirming Construction Completion.
Appears in 1 contract
Samples: www.transportation.alberta.ca
Construction Completion. Following achievement of Traffic Availability, the Contractor shall diligently proceed to Construction Completion. When the Contractor has advised that Construction Completion has been achieved, the Province will do a further inspection (which shall be carried out jointly with the Contractor if so requested by the Contractor) and, when all noted deficiencies from in the Project Requirements have been rectified, will issue a certificate confirming Construction Completion.
Appears in 1 contract
Samples: www.transportation.alberta.ca
Construction Completion. Following achievement of Traffic Availability, the Contractor shall diligently proceed to Construction Completion. When the Contractor has advised provided the Province with a written request to issue a certificate confirming that Construction Completion has been achieved, the Province will do a further inspection (which shall be carried out jointly with the Contractor if so requested by the Contractor) and, when all noted deficiencies from in the Project Requirements have been rectified, will issue a certificate confirming Construction CompletionCompletion (the “Construction Completion Certificate”).
Appears in 1 contract
Samples: www.transportation.alberta.ca