Common use of Constraints Clause in Contracts

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 complete any Project activity unless calendar dates are shown in the TPs or other 32 relevant Contract Documents. The Project Schedule must not contain unspecified 33 milestones, constraints, Float suppression techniques, or use of Project activity 34 durations, logic ties, and/or sequences deemed unreasonable by ADOT. Any schedule 35 showing an early completion date must show the time between the scheduled 36 completion date(s) and the applicable Completion Deadline(s) as Float.

Appears in 3 contracts

Samples: apps.azdot.gov, apps.azdot.gov, apps.azdot.gov

AutoNDA by SimpleDocs

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 15 complete any Project activity unless calendar dates are shown in the TPs or other 32 16 relevant Contract Documents. The Project Schedule must not contain unspecified 33 17 milestones, constraints, Float suppression techniques, or use of Project activity 34 18 durations, logic ties, and/or sequences deemed unreasonable by ADOT. Any schedule 35 19 showing an early completion date must show the time between the scheduled 36 20 completion date(s) and the applicable Completion Deadline(s) as Float.

Appears in 3 contracts

Samples: apps.azdot.gov, apps.azdot.gov, apps.azdot.gov

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 18 complete any Project activity unless calendar dates are shown in the TPs or other 32 19 relevant Contract Documents. The Project Schedule must not contain unspecified 33 20 milestones, constraints, Float suppression techniques, or use of Project activity 34 21 durations, logic ties, and/or sequences deemed unreasonable by ADOT. Any schedule 35 22 showing an early completion date must show the time between the scheduled 36 23 completion date(s) and the applicable Completion Deadline(s) as Float.

Appears in 2 contracts

Samples: apps.azdot.gov, apps.azdot.gov

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 19 complete any Project activity unless calendar dates are shown in the TPs or other 32 20 relevant Contract Documents. The Project Schedule must not contain unspecified 33 21 milestones, constraints, Float suppression techniques, or use of Project activity 34 22 durations, logic ties, and/or sequences deemed unreasonable by ADOT. Any schedule 35 23 showing an early completion date must show the time between the scheduled 36 24 completion date(s) and the applicable Completion Deadline(s) as Float.

Appears in 1 contract

Samples: apps.azdot.gov

Constraints. Developer DoDeveloper shall not use calendar dates or constraints to logically begin 17 or 31 complete any Project activity unless calendar dates are shown in the TPs or other 32 18 relevant Contract Documents. The Project Schedule must not contain unspecified 33 19 milestones, constraints, Float suppression techniques, or use of Project activity 34 20 durations, logic ties, and/or sequences deemed unreasonable by ADOT. Any schedule 35 21 showing an early completion date must show the time between the scheduled 36 22 completion date(s) and the applicable Completion Deadline(s) as Float.

Appears in 1 contract

Samples: apps.azdot.gov

AutoNDA by SimpleDocs

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 17 complete any Project activity unless calendar dates are shown in the TPs or other 32 relevant 18 Contract Documents. The Project Schedule must not contain unspecified 33 milestones, 19 constraints, Float suppression techniques, or use of Project activity 34 durations, logic ties, 20 and/or sequences deemed unreasonable by ADOT. Any schedule 35 showing an early 21 completion date must show the time between the scheduled 36 completion date(s) and the 22 applicable Completion Deadline(s) as Float.

Appears in 1 contract

Samples: azdot.gov

Constraints. Developer shall Do not use calendar dates or constraints to logically begin or 31 complete any 22 Project activity unless calendar dates are shown in the TPs or other 32 relevant Contract 23 Documents. The Project Schedule must not contain unspecified 33 milestones, constraints, 24 Float suppression techniques, or use of Project activity 34 durations, logic ties, and/or 25 sequences deemed unreasonable by ADOT. Any schedule 35 showing an early completion 26 date must show the time between the scheduled 36 completion date(s) and the applicable 27 Completion Deadline(s) as Float.

Appears in 1 contract

Samples: apps.azdot.gov

Constraints. Developer shall not use calendar dates or constraints to logically begin or 31 complete 15 any Project activity unless calendar dates are shown in the TPs or other 32 relevant Contract 16 Documents. The Project Schedule must shall not contain unspecified 33 milestones, constraints, Float 17 suppression techniques, or use of Project activity 34 durations, logic ties, and/or sequences 18 deemed unreasonable by ADOT. Any schedule 35 showing an early completion date must shall show 19 the time between the scheduled 36 completion date(s) and the applicable Completion Deadline(s) 20 as Float.;

Appears in 1 contract

Samples: apps.azdot.gov