Common use of Computation of Time / Adverse Weather Clause in Contracts

Computation of Time / Adverse Weather. 15.1.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor and only if all of the following conditions are met:

Appears in 8 contracts

Samples: Site Lease, Master Site Lease, Master Site Lease

AutoNDA by SimpleDocs

Computation of Time / Adverse Weather. 15.1.116.3.6.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor within five (5) calendar days of the Adverse Weather event, and only if all of the following conditions are met:met – thereby making the resulting delay an Excusable Delay.

Appears in 6 contracts

Samples: Site Lease, Master Site Lease, Master Site Lease

Computation of Time / Adverse Weather. 15.1.1. 13.14.1 The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor in compliance with the time extension request procedures and only if all of the following conditions are met:

Appears in 5 contracts

Samples: Facilities Lease, Facilities Lease, Facilities Lease

Computation of Time / Adverse Weather. 15.1.1. The 16.3.6.1.The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Contractor within five (5) calendar days of the Adverse Weather event, and only if all of the following conditions are met:met – thereby making the resulting delay an Excusable Delay.

Appears in 2 contracts

Samples: Site Lease, Site Lease

AutoNDA by SimpleDocs

Computation of Time / Adverse Weather. 15.1.1. The Contractor Developer will only be allowed a time extension for Adverse Weather conditions if requested by Contractor and only if all of the following conditions are met:

Appears in 1 contract

Samples: Facilities Lease