Completion of the Work Sample Clauses

Completion of the Work. 83.1. The Commissioner, after declaring the Contractor in default, may then have the Work completed by such means and in such manner, by contract with or without public letting, or otherwise, as he/she may deem advisable, utilizing for such purpose such of the Contractor’s plant, materials, equipment, tools and supplies remaining on the Site, and also such Subcontractors, as he/she may deem advisable.
Completion of the Work. In addition, if the Contract is terminated for cause, PHB may complete the work either itself or by agreement with another subrecipient, or by a combination thereof. In the event the cost of completing the work exceeds the amount actually paid to Subrecipient hereunder plus the remaining unpaid balance of the compensation provided herein, then Subrecipient shall pay to PHB the amount of excess. Allowable costs shall be determined in accordance with 24 CFR 85.43(c).
Completion of the Work. The term “Completion of the Work” shall mean the date upon which all of the following shall have occurred, as acknowledged by Purchaser in writing:
Completion of the Work. The CONTRACTOR shall complete the Work within the time specified in the order, or as extended by written order.
Completion of the Work. 9.9.1 Close-Out Procedures
Completion of the Work. 1. The work to be performed under this contract shall be completed as requested, unless Vendor can show just cause for the delay of completion and obtains an extension of time in writing from the Land Bank.
AutoNDA by SimpleDocs
Completion of the Work. In the event of any termination for a Contractor Event of Default, Owner may, at its option and at its expense, finish the Work by whatever method Owner reasonably deems expedient; provided, however, that, as Contractor’s sole liability on account of such termination, Contractor shall be liable to Owner for the reasonable costs of cover and transitioning the Work to the Replacement Contractor. Owner shall be entitled to withhold payments which Contractor determines are due to it prior to the date of termination, along with other amounts for which Contractor is entitled to compensation under Section 13.4.1, until completion of the Work and determination by Owner that Contractor is entitled to such payments. Any amounts not paid hereunder if ultimately due shall bear interest at the Late Payment Rate. Owner may in its discretion employ the Replacement Contractor to finish the Work by whatever method or means Owner in its discretion may deem expeditious; provided, however, that the balance of Work will be completed utilizing reasonable methods of construction management and construction consistent, to the maximum feasible extent, with the Project Schedule and as otherwise provided herein. In the event that any termination of this Agreement by Owner because of a Contractor Event of Default pursuant to Section 13.2 is later adjudicated to have been improper, then Contractor shall be entitled to recover such amounts as Contractor is entitled to under Section 13.1.
Completion of the Work. 9.7.1 Close-Out Procedures When the Contractor considers that the Work, or a portion thereof which the District agrees to accept separately, is complete, the Contractor shall prepare and submit to the District a comprehensive list of minor items to be completed or corrected (Punch List). The Contractor and/or its Subcontractors shall proceed promptly to complete and correct items on the list. Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. Upon receipt of the Contractor’s list, the District will make an inspection to determine whether the Work, or designated portion thereof, is complete. If the District’s inspection discloses any item, whether or not included on the Contractor’s list, is not completed in accordance with the requirements of the Contract Documents, the Contractor shall, before District’s issuance of the Notice of Completion, complete or correct such item. The Contractor shall then submit a request for an additional inspection by the District to determine Completion. When the Work, or designated portion thereof, is complete, the District will prepare a Notice of Completion which shall establish the date of Completion, establish the responsibilities of the District and Contractor for security, maintenance, heat, utilities, damage to the Work and insurance, and fix the time within which the Contractor shall finish all items on the list accompanying the Notice of Completion. Warranties required by the Contract Documents shall commence on the date of Completion of the Work, or designated portion thereof, unless otherwise provided in the Notice of Completion. The Notice of Completion shall be submitted to the District and the Contractor for their written acceptance of responsibilities assigned to them in such Notice.
Completion of the Work. (a) The Author will prepare and deliver to the Institution on or before [date] the Author's contribution to the Work (with all illustrations, charts, graphs, and other material, including syllabi, handouts, reference lists, etc., in the medium mutually agreed upon for the Work) in form and content satisfactory to the Institution.