Commissioning of Critical Systems Sample Clauses

Commissioning of Critical Systems. The following systems of the Work, and any other systems designated in the Contract Documents, are considered “Critical Systems”:
AutoNDA by SimpleDocs
Commissioning of Critical Systems. 6.8.1 Certain systems of the Work designated in the Contract Documents are designated "Critical Systems." When Design-Builder considers that the Critical Systems are up and running and ready for normal operation, Design-Builder shall schedule a pre-commissioning inspection of these systems to determine whether the Critical Systems are complete and ready for normal operation. If the inspection discloses that the Critical Systems are not Substantially Complete or that any item which is not in accordance with the requirements of the Contract Documents, Design-Builder shall expeditiously, and before the Date of Commissioning, complete or correct outstanding items. When the Critical Systems are considered complete, Design-Builder shall notify Owner in writing, and Owner will conduct a commissioning inspection, Owner's approval of which shall establish the Date of Commissioning. Warranties on the Critical Systems required by the Contract Documents shall commence on the Date of Commissioning, unless otherwise provided. The Date of Commissioning shall be separate from the duties of the parties at Substantial Completion.

Related to Commissioning of Critical Systems

  • Project acronym Use the project acronym as indicated in the submitted proposal. It cannot be changed, unless agreed during the negotiations. The same acronym should appear on each page of the grant agreement preparation documents to prevent errors during its handling.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Project Website The State will develop and maintain a website that will be made available in advance of the first public meeting for this project. The Engineer shall provide project information for the project website to the State including documents related to project background, study area limits, study objectives, project photos, study area maps, material presented at public meetings, and contact information for requesting additional information. The project website will be updated with the documents and other information provided by the Engineer to the State after each set of public meetings and the final report in PDF format provided by the Engineer will be posted by the State to give the general public access to the document.

  • Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.

  • Building Commissioning Services The Owner may provide as a part of its testing services the Building Commissioning services involving the project’s HVAC and exhaust systems, temperature control systems, fire detection and alarm systems, emergency power and lighting system, fire suppression system, security locks and security locking control systems, food service equipment (if applicable), and laundry equipment (if applicable). In the event the Using Agency’s Program specifies additional commissioning services, the Owner shall procure such services as well. The Owner, through its Executive Administrator, may engage an independent Commissioning Authority. It is the intent of this Article that the Commissioning Authority enforce the requirements mentioned herein and certify that the systems and equipment listed all function properly prior to the initiation of each final inspection.

  • Technical Standards Applicable to a Wind Generating Plant i. Low Voltage Ride-Through (LVRT) Capability A wind generating plant shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the standard below. The LVRT standard provides for a transition period standard and a post-transition period standard.

  • Electrical Safety Only UL approved items are permitted in Housing & Residence Life. Extension and multi-use cords must be heavy duty, single plug, and be UL approved. Altering or adapting electrical outlets and equipment and overloading circuits jeopardize safety and thus are not permitted.

  • Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Operations Support Systems Functions CBT shall provide CLEC, upon CLEC's request, nondiscriminatory access to CBT's Operations Support Systems functions for pre-ordering, ordering, provisioning, maintenance and repair and billing, in accordance with the terms and schedules established in the Commission’s Arbitration Award in Case No. 97-152-TP-ARB, August 14, 1997 (“Arbitration Award”). CBT shall provide CLEC advance written notice of any material changes to CBT operating support systems functions.

  • Outpatient emergency and urgicenter services within the service area The emergency room copay applies to all outpatient emergency visits that do not result in hospital admission within twenty-four (24) hours. The urgicenter copay is the same as the primary care clinic office visit copay.

Time is Money Join Law Insider Premium to draft better contracts faster.