Commissioning and Completion Sample Clauses

Commissioning and Completion. 13.1 Agreeing Final Commissioning Programme Not less than nine (9) months before the Planned Service Commencement Date for each [Project Facility], PPP Co. will provide the Authority’s Representative and the Independent Tester with a draft of the Final Commissioning Programme in respect of that [Project Facility] as developed by PPP Co. in accordance with the provisions of Clause 13.2 (Standard of Final Commissioning Programme). The Authority’s Representative and the Independent Tester will provide PPP Co. with comments on the draft Final Commissioning Programme submitted to them no later than one (1) month after its receipt. The Parties and the Independent Tester will, within twenty (20) Business Days of receipt by PPP Co. of the Authority’s Representative’s and the Independent Tester’s comments agree the terms of the Final Commissioning Programme for the relevant [Project Facility]. If the Parties are unable to agree a Final Commissioning Programme the matter will be referred for determination in accordance with the Fast Track Procedure. If the Authority’s Representative and/or the Independent Tester do not issue comments within the required one (1) month period, the draft Final Commissioning Programme will be deemed to be accepted by the relevant Party.
AutoNDA by SimpleDocs
Commissioning and Completion. 16.1 [Intentionally Deleted]
Commissioning and Completion. 7.1 The Connection Provider shall ensure that all pre-commissioning tests and checks listed in the Service Information Form or ICP HV Cable Assessment Form (as the case may be) are satisfactorily completed and recorded prior to Energisation. The Connection Provider shall not make any connection which fails the pre- commissioning tests.
Commissioning and Completion 

Related to Commissioning and Completion

  • Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Project Completion Part 1 – Material Completion

  • Approval and Completion If any dispute regarding the design of the Tenant Improvements is not settled within 10 business days after notice of such dispute is delivered by one party to the other, Tenant may make the final decision regarding the design of the Tenant Improvements, provided (i) Tenant acts reasonably and such final decision is either consistent with or a compromise between Landlord’s and Tenant’s positions with respect to such dispute, (ii) that all costs and expenses resulting from any such decision by Tenant shall be payable out of the TI Fund (as defined in Section 5(d) below), and (iii) Tenant’s decision will not affect the base Building, structural components of the Building or any Building systems (in which case Landlord shall make the final decision). Any changes to the TI Construction Drawings following Landlord’s and Tenant’s approval of same requested by Tenant shall be processed as provided in Section 4 hereof.

  • Timeline Contractor must perform the Services and deliver the Deliverables according to the following timeline: • •

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • After Completion the Seller shall at its cost execute and deliver all such further documents and/or take such other action as the Purchaser may reasonably request in order to effect (i) the release and discharge in full of the relevant member of the Purchaser’s Group from any and all Retained Liabilities and any Liabilities related to the Retained Assets and (ii) the assumption by the Seller or any member of the Seller’s Group as the primary obligor in respect of any and all Retained Liabilities or Liabilities related to the Retained Assets in substitution for the relevant member of the Purchaser’s Group (in each case on a non-recourse basis to any member of the Purchaser’s Group).

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Check and complete if Transferee will take delivery of a beneficial interest in the IAI Global Note or a Restricted Definitive Note pursuant to any provision of the Securities Act other than Rule 144A or Regulation S. The Transfer is being effected in compliance with the transfer restrictions applicable to beneficial interests in Restricted Global Notes and Restricted Definitive Notes and pursuant to and in accordance with the Securities Act and any applicable blue sky securities laws of any state of the United States, and accordingly the Transferor hereby further certifies that (check one):

  • Decommissioning The expenditure for Decommissioning will be estimated on the basis of technical studies undertaken by the Contractor, to be agreed by the National Petroleum Agency, as part of each Field Development Program and revised as necessary.

  • Development Work The Support Standards do not include development work either (i) on software not licensed from CentralSquare or (ii) development work for enhancements or features that are outside the documented functionality of the Solutions, except such work as may be specifically purchased and outlined in Exhibit 1. CentralSquare retains all Intellectual Property Rights in development work performed and Customer may request consulting and development work from CentralSquare as a separate billable service.

Time is Money Join Law Insider Premium to draft better contracts faster.