Changes Requested by Contractor Sample Clauses

Changes Requested by Contractor. Should Contractor find it necessary to request any changes in the scope of work or any time extensions during the course of construction, Contractor shall submit a written request which includes a pricing and a scheduling proposal to the Owner within seven (7) days of the event giving rise to the change request. If Owner is in agreement, Owner shall issue a written change order or may request additional information within seven (7) days of receipt of Contractor's request. All pricing and scheduling proposals are subject to independent verification and audit. Contractor agrees to make all records relating to any pricing or scheduling proposal available for Owner's inspection. Absent written approval of the Owner, through the execution of a written change order, or issuance of a change directive, the Contractor shall not proceed with performing such additional work (unless Owner determines that such work is in the original scope of this contract). Contractor acknowledges that Owner's execution of a written change order or change directive under Article 4.3 is a condition precedent to any payment for work included in the Change Order or any adjustment in the Contractor's schedule. Contractor hereby waives any entitlement to additional compensation or extensions of time to the extent that Contractor performs any additional work without written approval of Owner.
AutoNDA by SimpleDocs
Changes Requested by Contractor. If Contractor believes a Change Order is necessary for any reason to complete the SOW, Contractor shall provide Corporation a proposed Change Order in writing including (a) Contractor’s proposed adjustment to the Construction Schedule, (b) Contractor’s proposed adjustment to the Compensation Schedule; and (c) a detailed description of the change and reason for the change. Corporation shall have the right to approve or disapprove the Change Order in its sole and absolute discretion. Any Change Order approved by Corporation and Contractor must be authorized in writing and executed by both Parties prior to commencement of any work on the Change Order.
Changes Requested by Contractor. (a) Subject to paragraphs (b) and (c) below, Contractor may request, during the performance of this Contract, any change within the general scope of this Contract, including any change that will add or delete Work, affect the design of the Satellites, change the method of shipping or packing, or the place or time of Delivery, or will affect any other requirement of this Contract.
Changes Requested by Contractor. (a) Subject to paragraphs (b) and (c) below, Contractor may request, during the performance of this Contract, any change within the general scope of this Contract, including any change that will add or delete Work, cause a revision to the Initial City Schedules or Acceptance Date or affect any other requirement of this Contract.
Changes Requested by Contractor. With respect to any matter that may involve or require an adjustment to the Contract Time or the Contract Price, Contractor shall provide written notice of the underlying facts and circumstances that gave rise to the potential change within seven (7) days or prior to the alteration of conditions, whichever is earlier. Failure to give notice shall constitute a waiver of Contractor’s right to a change order. If any costs are not capable of being determined within seven (7) days, then Contractor shall request a Change Order within seven (7) days of when the costs are capable of being determined.
Changes Requested by Contractor. (a) Subject to paragraphs (b) and (c) below, Contractor may request, during the performance of this Agreement, any change within the general scope of this Agreement, including any change that will add or delete Work, affect the design of the Satellites, change the DigitalGlobe Inc. Proprietary method of shipping or packing, or the place or time of Delivery, or will affect any other requirement of this Agreement.
Changes Requested by Contractor. 6.4.1 If (a) Contractor considers that a direction by MSG constitutes a Change, or (b) Contractor considers that a direction by MSG is likely to prevent Contractor from fulfilling any of its obligations, Contractor must notify MSG in what respect it considers the direction to involve a Change or that it is likely to prevent it from fulfilling its obligations. Such notice must be given within ten (10) Business Days of the date of the direction and before Contractor proceeds with the direction and must contain sufficient detail for MSG to assess the request. If Contractor fails to submit such notice as required, Contractor will not be entitled to submit any claim for a Change Order, recover as a Cost of the Work or be entitled to an adjustment to the Incentive Benchmark or to the Substantial Completion Date with respect to the direction.
AutoNDA by SimpleDocs
Changes Requested by Contractor. Contractor may at any time request a change in the Work. Any proposed change shall contain a written proposal identifying such change, the reasons therefore and the impact thereof on the price, Delivery schedule, or other terms of this Contract. Purchaser will attempt to respond to such change request from Contractor within thirty (30) days of receipt. If the Parties reach an agreement on such change request in writing, it shall be incorporated into the Contract by the execution of an amendment to this Contract in accordance with Article 37.5. If the Parties are unable to reach an agreement in writing on the proposed change request, then such request shall be deemed rejected.
Changes Requested by Contractor. Should Contractor find it necessary to request any changes in the scope of work or any time extensions during the course of construction, Contractor shall submit a written request which includes a pricing and a scheduling proposal to the Owner within seven (7) days of the event giving rise to the change request. If Owner is in agreement, Owner shall issue a written change order or may request additional information within seven (7) days of receipt of Contractor's request. All pricing and scheduling proposals are subject to independent verification and audit. Contractor agrees to make all records relating to any pricing or scheduling proposal available for CLARENDON COUNTY's inspection. Absent written approval of the Owner, through the execution of a written change order, or issuance of a change directive, the Contractor shall not proceed with performing such additional work (unless CLARENDON COUNTY determines that such work is in the original scope of this contract). Contractor acknowledges that Owner's execution of a written change order or change directive under Article 4.3 is a condition precedent to any payment for work included in the Change Order or any adjustment in the Contractor's schedule. Contractor hereby waives any entitlement to additional compensation or extensions of time to the extent that Contractor performs any additional work without written approval of Owner.
Changes Requested by Contractor. 41 10.3 Pricing of Changes......................................................... 42