Common use of Betterment Clause in Contracts

Betterment. If, due to TRANSYSTEMS’s negligence, a required item or component of the Project is omitted from TRANSYSTEMS’s construction documents, TRANSYSTEMS shall not be responsible for paying the cost required to add such item or component to the extent that such item or component would have been required and included in the original construction documents. In no event will TRANSYSTEMS be responsible for any cost or expense that provides betterment or upgrades or enhances the value of the Project.

Appears in 6 contracts

Sources: Professional Services, Professional Services, Professional Services

Betterment. If, due to TRANSYSTEMS’s negligence, a required item or component of the Project is omitted from TRANSYSTEMS’s construction documents, TRANSYSTEMS shall not be responsible for paying the cost required to add such item or component to the extent that such item or component would have been required and included in the original construction documents. In no event will TRANSYSTEMS be responsible for any cost or expense that provides betterment or upgrades or enhances the value of the Project.

Appears in 2 contracts

Sources: Continuous Services Agreement (Highwater Ethanol LLC), Continuous Services Agreement (Highwater Ethanol LLC)

Betterment. If, due to TRANSYSTEMS’s negligence, a required item or component of the Project is omitted from TRANSYSTEMS’s construction documents, TRANSYSTEMS shall not be responsible for paying the cost required to add such item or component to the extent that such item or component would have been required and included in the original construction documents. In no event will TRANSYSTEMS be responsible for any cost or expense that provides betterment or upgrades or enhances the value of the Project.. Section 7.7.10

Appears in 1 contract

Sources: Engineering Services Agreement

Betterment. If, due to TRANSYSTEMS’s 's negligence, a required item or component of the Project is omitted from TRANSYSTEMS’s 's construction documents, TRANSYSTEMS shall not be responsible for paying the cost required to add such item or component to the extent that such item or component would have been required and included in the original construction documents. In no event will TRANSYSTEMS be responsible for any cost or expense that provides betterment or upgrades or enhances the value of the Project.

Appears in 1 contract

Sources: Professional Services