Applications for Utility Permits Sample Clauses

Applications for Utility Permits. 7.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners will apply for utility permits to install new Utilities that would cross or longitudinally occupy the Facility Right of Way, or to modify, upgrade, repair, relocate or expand existing Utilities within the Facility Right of Way for reasons other than accommodation of the Facility. The provisions of Sections 7.5.8.2 through 7.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 7.5.8.5. Except as otherwise provided in Section 7.5.8.4(b) or in Section 11.2, no accommodation of new Utilities or of modifications, upgrades, repairs, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation or time extension hereunder.
AutoNDA by SimpleDocs
Applications for Utility Permits. 5.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners may apply to IFA for utility permits to install new Utilities that would cross or longitudinally occupy the Project Right of Way, or to modify, upgrade, relocate or expand existing Utilities within the Project Right of Way for reasons other than accommodation of the Project. The provisions of Sections 5.5.8.2 through 5.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 5.5.8.5. Except as otherwise provided in Section 5.5.8.4(b) or in Article 15 with respect to a Relief Event under clause (h) of the definition of Relief Event (development or operation of a Business Opportunity), no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation, time extension or other Claim hereunder.
Applications for Utility Permits. 6.7.8.1. It is anticipated that during the Work, from time to time Utility Owners will apply for utility permits to install New Utilities that would cross or longitudinally occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within the Project ROW for reasons other than accommodation of the Project. The provisions of this Section 6.7.8 shall apply to all such permit applications. TxDOT shall provide DB Contractor with a copy of each such permit application received after the Effective Date, within 30 days after TxDOT’s receipt of such application. Except as otherwise provided in Section 6.7.1, no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle DB Contractor to additional compensation or time extension hereunder.
Applications for Utility Permits. 32 5.10.9.1 It is anticipated that, during the D&C Period, Utility 33 Companies will apply to ADOT for utility permits and other agreements and approvals to 34 install new Utilities that would cross or longitudinally occupy the Project ROW, or to 35 modify, upgrade, relocate or expand existing Utilities within the Project ROW for 36 reasons other than to accommodate the Project. The provisions of Sections 5.10.9.2 37 through 5.10.9.5 shall apply to all such Utility Company applications. No work or 38 services required of Developer, and no accommodation of new Utilities or of 39 modifications, upgrades, relocations or expansions of existing Utilities, pursuant hereto, 40 shall entitle Developer to additional compensation, Completion Deadline adjustment or 41 other Claim or relief.
Applications for Utility Permits. 6.8.8.1. It is anticipated that during the Work, Utility Owners will apply for utility permits to install Utilities that would cross or longitudinally occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within the Project ROW for reasons other than accommodation of the Project. The provisions of this Section 6.8.8 shall apply to all such permit applications. TxDOT shall provide DB Contractor with a copy of each such permit application received after the Effective Date, within 30 days after TxDOT’s receipt of such application.
Applications for Utility Permits. 6.8.8.1 It is anticipated that during the Work, Utility Owners will apply for utility permits to install Utilities that would cross or longitudinally occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within the Project ROW for reasons other than accommodation of the Project. The provisions of this Section
Applications for Utility Permits. (a) It is anticipated that during the Work, from time to time Utility Owners will apply for utility permits to install new Utilities that would cross or longitudinally occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within the Project ROW for reasons other than accommodation of the Project. The provisions of this Section 3.14.8 shall apply to all such permit applications. TxDOT shall provide Developer with a copy of each such permit application received after the Effective Date, within 30 days after TxDOT’s receipt of such application. Except as otherwise provided in Section 3.14.1, no accommodation of New Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation or time extension hereunder.
AutoNDA by SimpleDocs
Applications for Utility Permits. 17 It is anticipated that, during the Work Utility Companies will apply to ADOT for utility permits and other 18 agreements and approvals to install new utilities that would cross or longitudinally occupy the Project ROW, 19 or to modify, upgrade, relocate or expand existing utilities within the Project ROW for reasons other than to 20 accommodate the Project. Encroachment Permit Coordinator shall review and mitigate any conflicts and 21 schedule impacts with the Utility Company or ADOT to allow for such permits to be granted. Such 22 applications shall be governed by Section 5.4.9 of the Agreement.
Applications for Utility Permits. ‌ 20 (a) Utility Companies may apply to ADOT for utility permits and other agreements and 21 approvals to install new Utilities that would cross or longitudinally occupy the 22 Project ROW, or to modify, upgrade, relocate or expand existing Utilities within 23 the Project ROW for reasons other than to accommodate the Project. The 24 provisions of this Section 7.4.10 shall govern such Utility Company applications. 25 (b) For all Utility Company applications described in Section 7.4.10(a) and pending as 26 of or submitted after the Effective Date, Developer shall:
Applications for Utility Permits. 13 5.4.9.1 Utility Companies may apply to ADOT for utility permits and 14 other agreements and approvals to install new Utilities that would cross or longitudinally 15 occupy the Project ROW, or to modify, upgrade, relocate or expand existing Utilities within 16 the Project ROW for reasons other than to accommodate the Project. The provisions of 17 Sections 5.4.9.2 through 5.4.9.5 and Section 107.15.06.06 of the Technical Provisions 18 shall govern such Utility Company applications. Except as provided in this Section 5.4.9, 19 no work or services required of Developer, and no accommodation of new Utilities or of 20 modifications, upgrades, relocations or expansions of existing Utilities, pursuant hereto, 21 shall entitle Developer to an increase in the Contract Price, a Completion Deadline 22 adjustment or other Claim or relief.