Application for Final Payment Certificate Sample Clauses

Application for Final Payment Certificate. Within 56 days after receiving the Performance Certificate, the Contractor shall submit, to the Engineer, six copies of a draft final statement with supporting documents showing in detail in a form approved by the Engineer:
AutoNDA by SimpleDocs
Application for Final Payment Certificate. Within 56 days after receiving the Performance Certificate, unless otherwise stated in the SCC, the Contractor shall submit to the Project Manager, six copies of a final statement with supporting documents showing in detail in a form approved by the Project Manager: (a) the value of all work done in accordance with the Contract, and (b) Any further sums which the Contractor considers to be due to him under the Contract or otherwise. If the Project Manager disagrees with or cannot verify any part of the final statement, the Contractor shall submit such further information as the Project Manager may reasonably require within 28 days from receipt of the said draft and shall make such changes in the draft as may be agreed between them. The Contractor shall then prepare and submit to the Project Manager the final statement as agreed. This agreed statement is referred to in these Conditions as the “Final Statement”. However if, following discussions between the Project Manager and the Contractor and any changes to the final statement which are agreed, it becomes evident that a dispute exists, the Project Manager shall deliver to the Employer (with a copy to the Contractor) an Interim Payment Certificate for the agreed parts of the draft final statement. Thereafter, if the dispute is finally resolved under GCC 20.4 [Obtaining Dispute Board‟s Decision] or GCC 20.5 [Amicable Settlement], the Contractor shall then prepare and submit to the Employer (with a copy to the Project Manager) a Final Statement.
Application for Final Payment Certificate. Unless otherwise stated in the Particular Conditions, when the Taking-Over Certificate has been issued for the Works and the first half of the Retention Money has been certified for payment by the Engineer, the Contractor shall be entitled to substitute a guarantee, in the form annexed to the Particular Conditions or in another form approved by the Employer and issued by a reputable bank or financial institution selected by the Contractor, for the second half of the Retention Money. The Contractor shall ensure that the guarantee is in the amounts and currencies of the second half of the Retention Money and is valid and enforceable until the Contractor has executed and completed the Works and remedied any defects, as specified for the Performance Security in Sub- Clause 4.2. On receipt by the Employer of the required guarantee, the Engineer shall certify and the Employer shall pay the second half of the Retention Money. The release of the second half of the Retention Money against a guarantee shall then be in lieu of the release under the second paragraph of this Sub-Clause. The Employer shall return the guarantee to the Contractor within 21 days after receiving a copy of the Performance Certificate. If the Performance Security required under Sub-Clause 4.2 is in the form of a demand guarantee, and the amount guaranteed under it when the Taking-Over Certificate is issued is more than half of the Retention Money, then the Retention Money guarantee will not be required. If the amount guaranteed under the Performance Security when the Taking-Over Certificate is issued is less than half of the Retention Money, the Retention Money guarantee will only be required for the difference between half of the Retention Money and the amount guaranteed under the Performance Security. Within 84 days after receiving the Taking-Over Certificate for the Works, the Contractor shall submit to the Engineer six copies of a Statement at completion with supporting documents, in accordance with Sub-Clause 14.3 [Application for Interim Payment Certificates], showing:
Application for Final Payment Certificate. In the 2nd line of the 1st paragraph delete “six” and replace with “three”.

Related to Application for Final Payment Certificate

  • Payment Certificates 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.

  • Final Certificate, Design Professional’s Certificate of Final Completion The Certificate issued by the Design Professional stating that all work has been completed in accordance with the terms of the Contract Documents. See Section 6,

  • Exhibit D - Debarment Certification By signing and submitting this Contract, the Contractor is agreeing to abide by the debarment requirements as set out below. • The certification in this clause is a material representation of fact relied upon by County. • The Contractor shall provide immediate written notice to County if at any time the Contractor learns that its certification was erroneous or has become erroneous by reason of changed circumstances. • Contractor certifies that none of its principals, affiliates, agents, representatives or contractors are excluded, disqualified or ineligible for the award of contracts by any Federal agency and Contractor further certifies to the best of its knowledge and belief, that it and its principals: • Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded by any Federal Department or Agency; • Have not been convicted within the preceding three-years of any of the offenses listed in 2 CFR 180.800(a) or had a civil judgment rendered against it for one of those offenses within that time period; • Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, or Local) with commission of any of the offenses listed in 2 CFR 180.800(a); • Have not had one or more public transactions (Federal, State, or Local) terminated within the preceding three-years for cause or default. • The Contractor agrees by signing this Contract that it will not knowingly enter into any subcontract or covered transaction with a person who is proposed for debarment, debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction. • Any subcontractor will provide a debarment certification that includes the debarment clause as noted in preceding bullets above, without modification.

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • CONTRACT EXHIBIT I PREFERRED PRICING AFFIDAVIT This preferred-pricing affidavit is entered into in accordance with section 216.0113, F.S., and as required by Contract No. 80101507-21-STC-ITSA (“Contract”) between (“Contractor”) and the Department of Management Services. As the person authorized by Contractor to sign this affidavit, I attest that the Contractor is in full compliance with the preferred-pricing clause of the Contract. Contractor’s Name: By: Signature Printed Name/Title Date: STATE OF COUNTY OF Sworn to (or affirmed) and subscribed before me this day of , by . Signature of Notary Vendor Name: FEIN# Vendor’s Authorized Representative Name and Title: Address: City, State, and Zip code: Phone Number: ( ) - E-mail: CORPORATE SEAL (IF APPLICABLE) (Print, Type, or Stamp Commissioned Name of Notary Public) [Check One] Personally Known OR Produced the following I.D.

  • Replacement Certificates If, on the date a Securityholder’s escrow securities are to be released, the Escrow Agent holds a share certificate or other evidence representing more escrow securities than are to be released, the Escrow Agent will deliver the share certificate or other evidence to the Issuer or its transfer agent and request replacement share certificates or other evidence. The Issuer will cause replacement share certificates or other evidence to be prepared and delivered to the Escrow Agent. After the Escrow Agent receives the replacement share certificates or other evidence, the Escrow Agent will send to the Securityholder or at the Securityholder’s direction, the replacement share certificate or other evidence of the escrow securities released. The Escrow Agent and Issuer will act as soon as reasonably practicable.

  • Non-compliance Penalty Certificate h) If any Non-compliance Penalty arises, the Supplier Development Manager shall issue a Non- compliance Penalty Certificate on the last day of each month during such Non-compliance indicating the Non-compliance Penalties which have accrued during that period.

  • Class Certification Solely for the purposes of this Settlement, the Parties stipulate and agree to certification of the claims asserted on behalf of Class Members. As such, the Parties stipulate and agree that in order for this Settlement to occur, the Court must certify the Class as defined in this Agreement.

  • Settlement Class Certification The Settling Parties agree, for purposes of this settlement only, to the certification of the Settlement Class. If the settlement set forth in this Settlement Agreement is not approved by the Court, or if the Settlement Agreement is terminated or cancelled pursuant to the terms of this Settlement Agreement, this Settlement Agreement, and the certification of the Settlement Class provided for herein, will be vacated and the Litigation shall proceed as though the Settlement Class had never been certified, without prejudice to any Person’s or Settling Party’s position on the issue of class certification or any other issue. The Settling Parties’ agreement to the certification of the Settlement Class is also without prejudice to any position asserted by the Settling Parties in any other proceeding, case or action, as to which all of their rights are specifically preserved.

  • Resume Self-Certification Form When submitting a response to an RFQ the Contractor shall submit with its response a completed and signed Resume Self-Certification Form (Contract Exhibit F) to the Customer for each proposed Staff member identified in the RFQ response.