COMPREHENSIVE MAINTENANCE CONTRACT (CMC) नमुना कलम
COMPREHENSIVE MAINTENANCE CONTRACT (CMC). (i) The complete Solar PV Power Plant must be guaranteed against any manufacturing / design/ installation defects for a minimum period of 5 years.
(ii) PV modules used in Solar PV Power Plant must be guaranteed for their output peak watt capacity, which should not be less than 90% at the end of 1 0 years and 80% at the end of 25 years.
(iii) During the CMC period, MNRE / MEDA / users will have all the rights to cross check the performance of the Solar PV Power Plant. MEDA may carry out the frequent inspections of the Solar PV Power Plant installed and randomly pick up its components to get them tested at Govt. / MNRE approved any test centre. If during such tests any part is not found as per the specified technical parameters, MEDA will take the necessary action. The decision of MEDA in this regard will be final and binding on the bidder.