Rescheduling of Tests Sample Clauses

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
AutoNDA by SimpleDocs
Rescheduling of Tests. If the Independent Expert certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Hospitality Services or issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. The provisions of this Article 14.2 shall apply mutatis mutandis to such re-scheduled Tests.
Rescheduling of Tests. If the Independent Engineer certifies to CEB and Seller that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the tests could not be held or had to be suspended, Seller shall be entitled to re-schedule the tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Commissioning Committee certifies to Railways and the SPD that it is unable to issue the Completion Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the SPD shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Authority is unable to issue the Completion Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Mine Operator shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Mine Operator shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Mine Operator.
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. NH-202 for Package-I (Design Chainage 283+000 Km to 325+440 Km) in the State of Nagaland on EPC mode under NH (O)-NE mode” Mar 2022
Rescheduling of Tests. 14.6.1 If the Independent Engineer or the Monitoring Agency, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Diagnostic Services and OPD Services or issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable.
AutoNDA by SimpleDocs
Rescheduling of Tests. 13 Change of Scope
Rescheduling of Tests. If the Independent Monitor certifies to the Authority and the Concessionaire that it is because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Contract AgreementPage 80 of 145 Construction of 2 lane Minor Bridge at Km 26.700 (Dhanikhadi) in CRZ area on NH-4 in the Union Territory of Andaman & Nicobar Islands on EPC basis. Oct 2021 Article 13 Change of Scope 13.1 Change of Scope (i) The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/ alterations to the Works (“Change of Scope”) within a period of six months counted from the Appointed Date. Upon the Authority making its intention known to the Contractor for the specific Change of Scope, be it positive or negative, the Contractor shall submit his proposal for the said Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13. (ii) Provided that any such Change of Scope, excluding major structures (e.g. Major Bridge/ ROB/ RUB/ Flyover/ elevated road of more than 50 m length) may be required and agreed to be executed between the parties beyond the period of six months of the Appointed Date but before expiry of 50% of the original Scheduled Construction Period of the Project Highway, subject to the condition that it shall not entail any claims (e.g. Extension of Time/ Prolongation related claims), against the Authority. (iii) The Change of Scope shall mean the following: (a) change in specifications of any item of Works; (b) omission of any work from the Scope of the Project except under Clause 8.3 (iii); provided that, subject to Clause 13.5, the Authority shall not omit any Work under this Clause in order to get it executed by any other authority; and / or (c) any additional Work, Plant, Materials or services which are not included in the Scope of the Project, including any associated Tests on completion of construction. 13.2