If the Authority (acting reasonably) refuses its approval to the Operational Proposals and provides written reasons for such refusal in accordance with the provisions of Clause 12.2, the Contractor shall amend the Operational Proposals in accordance with the Authority’s written reasons and shall then seek approval of the Operational Proposals as so amended.
Clause 12.2 and this Clause 12.3 shall apply to such amended Operational Proposals as if they were the Operational Proposals originally submitted to the Authority except that the notice period shall be 7 days instead of the 14 days specified above.
The Contractor shall provide the Operational Proposals to the Authority in accordance with the timetable set out in Schedule G, together with such other information as the Authority reasonably requests.
Within 7 days of the completion of the last of such tests, the Authority shall either finally approve the Operational Proposals or shall provide the Contractor with written reasons why either the Operational Proposals did not satisfy the tests conducted or the Operational Proposals are not satisfactory notwithstanding the Authority’s earlier provisional approval of them.
Within 60 days (or in the event that prior written notice of the submission of the Operational Proposals has not been given by the Contractor as aforesaid, 74 days) of receipt of the last of the Operational Proposals, the Authority shall either give provisional approval to them (not to be unreasonably withheld) or refuse its approval to them, and in the latter case it shall provide the Contractor with written reasons as to why it has refused its approval.
Without prejudice to the stipulations as to time in Clause 12.1, the Contractor shall give the Authority at least 14 days prior written notice that it intends to submit the Operational Proposals to it, and shall submit the Operational Proposals on the expiry of the period of such notice.
Once the Authority has given provisional approval to the Operational Proposals in accordance with Clause 12.2, the Operational Proposals shall be tested in accordance with the proposals for testing in the Operational Proposals.
Any additional procedures provided to the Authority under this Clause 11.1 shall, for the purposes of Clause 11, be deemed to be Operational Proposals.
The Contractor shall provide to the Authority such other procedures relating to the performance of the Services as the Authority may reasonably request, provided that any such request is made by the Authority no later than 6 weeks after the date of delivery of the last Operational Proposal in accordance with Schedule G (for the sake of clarification, in calculating this 6 week period, the Parties shall disregard any amended Operational Proposals which are provided to the Authority pursuant to Clause 11.3).
The Authority shall be entitled to refuse to approve all or any part of the Operational Proposals until the Contractor has made such amendments.