{"component": "definition", "props": {"groups": [{"snippet": "means all work performed or to be performed to prepare AT&T-22STATE\u2019s Conduit Systems, Poles or Anchors and related Facilities for the requested occupancy or attachment of CLEC\u2019s Facilities. Make-Ready Work includes, but is not limited to, clearing obstructions (e.g., by rodding Ducts to ensure clear passage), the rearrangement, transfer, replacement, and removal of existing Facilities on a Pole or in a Conduit System where such work is required solely to accommodate CLEC\u2019s Facilities and not to meet AT&T-22STATE\u2019s business needs or convenience. Make-Ready Work may require \u201cdig ups\u201d of existing Facilities and may include the repair, enlargement or modification of AT&T-22STATE\u2019s Facilities (including, but not limited to, Conduits, Ducts, Handholes and Manholes) or the performance of other work required to make a Pole, Anchor, Conduit or Duct usable for the initial placement of CLEC\u2019s Facilities.", "size": 66, "samples": [{"hash": "lvTYKDtkUEJ", "uri": "/contracts/lvTYKDtkUEJ#make-ready-work", "label": "Interconnection Agreement", "score": 30.3713283539, "published": true}, {"hash": "9pUhV1Jy5k0", "uri": "/contracts/9pUhV1Jy5k0#make-ready-work", "label": "Clec Agreement", "score": 27.6943054199, "published": true}, {"hash": "fsyU0Bq7NkL", "uri": "/contracts/fsyU0Bq7NkL#make-ready-work", "label": "Telecommunications", "score": 24.8432636261, "published": true}], "snippet_links": [{"key": "work-performed", "type": "definition", "offset": [10, 24]}, {"key": "related-facilities", "type": "definition", "offset": [108, 126]}, {"key": "work-includes", "type": "clause", "offset": [202, 215]}, {"key": "not-limited", "type": "clause", "offset": [224, 235]}, {"key": "to-ensure", "type": "clause", "offset": [286, 295]}, {"key": "removal-of", "type": "definition", "offset": [358, 368]}, {"key": "existing-facilities", "type": "clause", "offset": [369, 388]}, {"key": "conduit-system", "type": "definition", "offset": [407, 421]}, {"key": "business-needs", "type": "clause", "offset": [521, 535]}, {"key": "the-repair", "type": "definition", "offset": [629, 639]}, {"key": "modification-of", "type": "clause", "offset": [656, 671]}, {"key": "the-performance", "type": "clause", "offset": [774, 789]}, {"key": "work-required", "type": "clause", "offset": [799, 812]}, {"key": "placement-of", "type": "definition", "offset": [876, 888]}], "hash": "d2b331a58a6976e5833580c0fc2c33ba", "id": 1}, {"snippet": "means work necessary to enable an authority pole or utility pole to support collocation, which may include modification or replacement of utility poles or modification of lines.", "size": 43, "samples": [{"hash": "7WxgjgwMyLC", "uri": "/contracts/7WxgjgwMyLC#make-ready-work", "label": "Master License Agreement", "score": 31.0187644958, "published": true}, {"hash": "flBDJQ3M8jA", "uri": "/contracts/flBDJQ3M8jA#make-ready-work", "label": "Wireless Addendum to Standard Pole Attachment License Agreement", "score": 30.3097877502, "published": true}, {"hash": "dhcf5PGJST7", "uri": "https://zeus-milenia.legislature.mi.gov/documents/mcl/archive/2025/January/mcl-Act-365-of-2018.pdf", "label": "zeus-milenia.legislature.mi.gov", "score": 19.912853241, "published": false}], "snippet_links": [{"key": "pole-or-utility-pole", "type": "clause", "offset": [44, 64]}, {"key": "replacement-of", "type": "clause", "offset": [123, 137]}, {"key": "utility-poles", "type": "clause", "offset": [138, 151]}, {"key": "modification-of", "type": "clause", "offset": [155, 170]}], "hash": "d2917d1e95b93bbbd157ef964123a8e2", "id": 2}, {"snippet": "means all work performed or to be performed to prepare AT&T-21STATE\u2019s Conduit System, Poles or related Facilities for the requested Attachment of CLEC\u2019s Facilities. Make-Ready Work includes, but is not limited to, clearing obstructions (e.g., by rodding Ducts to ensure clear passage), and the rearrangement, transfer, replacement, and removal of existing Facilities on a Pole or in a Conduit System where such work is required solely to accommodate CLEC\u2019s Facilities and not to meet AT&T-21STATE\u2019s business needs or convenience. Make-Ready Work may require \u201cdig ups\u201d of existing Facilities and may include the repair, enlargement or modification of AT&T- 21STATE\u2019s Structure or the performance of other work required to make AT&T-21STATE\u2019s Structure usable for the initial placement of CLEC\u2019s Facilities.", "size": 27, "samples": [{"hash": "4XzrWrJpAXj", "uri": "/contracts/4XzrWrJpAXj#make-ready-work", "label": "Telecommunications", "score": 27.7229747772, "published": true}, {"hash": "bDXTf6oELIE", "uri": "/contracts/bDXTf6oELIE#make-ready-work", "label": "Wholesale Agreement", "score": 27.5481643677, "published": true}, {"hash": "6j1As2gP43L", "uri": "/contracts/6j1As2gP43L#make-ready-work", "label": "Wholesale Agreement", "score": 27.4922924042, "published": true}], "snippet_links": [{"key": "work-performed", "type": "definition", "offset": [10, 24]}, {"key": "conduit-system", "type": "definition", "offset": [70, 84]}, {"key": "related-facilities", "type": "definition", "offset": [95, 113]}, {"key": "work-includes", "type": "clause", "offset": [176, 189]}, {"key": "not-limited", "type": "clause", "offset": [198, 209]}, {"key": "to-ensure", "type": "clause", "offset": [260, 269]}, {"key": "removal-of", "type": "definition", "offset": [336, 346]}, {"key": "existing-facilities", "type": "clause", "offset": [347, 366]}, {"key": "business-needs", "type": "clause", "offset": [499, 513]}, {"key": "the-repair", "type": "definition", "offset": [607, 617]}, {"key": "modification-of", "type": "clause", "offset": [634, 649]}, {"key": "the-performance", "type": "clause", "offset": [679, 694]}, {"key": "work-required", "type": "clause", "offset": [704, 717]}, {"key": "placement-of", "type": "definition", "offset": [774, 786]}], "hash": "70325fbec26a1be1fdd2e084d26a4b36", "id": 3}, {"snippet": "means all engineering, inspection, design, planning, construction, or other work reasonably necessary to prepare poles for the installation of Licensee\u2019s Attachments, including without limitation, work related to transfers, rearrangements and replacements of existing poles or Equipment, and the addition of new poles or Equipment.", "size": 27, "samples": [{"hash": "31Q8jbFLJCt", "uri": "/contracts/31Q8jbFLJCt#make-ready-work", "label": "Pole Attachment Agreement", "score": 31.3390369415, "published": true}, {"hash": "gfuKYXoh4wi", "uri": "/contracts/gfuKYXoh4wi#make-ready-work", "label": "Pole Attachment Agreement", "score": 29.3332843781, "published": true}, {"hash": "gWPwLFNhl5V", "uri": "/contracts/gWPwLFNhl5V#make-ready-work", "label": "Pole Attachment Agreement", "score": 29.3325462341, "published": true}], "snippet_links": [{"key": "other-work", "type": "clause", "offset": [70, 80]}, {"key": "reasonably-necessary", "type": "clause", "offset": [81, 101]}, {"key": "of-licensee", "type": "clause", "offset": [140, 151]}, {"key": "including-without-limitation", "type": "clause", "offset": [167, 195]}, {"key": "related-to", "type": "definition", "offset": [202, 212]}, {"key": "addition-of-new-poles", "type": "clause", "offset": [296, 317]}], "hash": "35fdd8e3ce066ae711cbf7648f2cacd5", "id": 4}, {"snippet": "means the process of completing rearrangements on or in a support structure to create such surplus space or excess capacity as is necessary to make it usable for a pole attachment.", "size": 24, "samples": [{"hash": "6m8vQf9ch7z", "uri": "https://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M377/K391/377391014.PDF", "label": "docs.cpuc.ca.gov", "score": 14.0751886368, "published": false}, {"hash": "llVcQoroYHo", "uri": "https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M498/K026/498026496.PDF", "label": "docs.cpuc.ca.gov", "score": 11.4093084335, "published": false}, {"hash": "9didCSo6qL8", "uri": "https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M497/K809/497809350.docx", "label": "docs.cpuc.ca.gov", "score": 11.396987915, "published": false}], "snippet_links": [{"key": "the-process", "type": "clause", "offset": [6, 17]}, {"key": "support-structure", "type": "definition", "offset": [58, 75]}, {"key": "surplus-space", "type": "definition", "offset": [91, 104]}, {"key": "excess-capacity", "type": "clause", "offset": [108, 123]}, {"key": "pole-attachment", "type": "definition", "offset": [164, 179]}], "hash": "a15f5973fd0a26f2f49a73aa3e7773d5", "id": 5}, {"snippet": "means work necessary to connect a line extension to existing utility infrastructure. [PL 2011, c. 484, \u00a71 (NEW).]", "size": 16, "samples": [{"hash": "4itZhnBnO2D", "uri": "https://legislature.maine.gov/statutes/35-a/title35-A.docx", "label": "legislature.maine.gov", "score": 13.0519199371, "published": false}, {"hash": "acQvtg3jnWw", "uri": "https://legislature.maine.gov/statutes/35-a/title35-A.pdf", "label": "legislature.maine.gov", "score": 12.0388727188, "published": false}, {"hash": "kZzv5DrmGu2", "uri": "https://legislature.maine.gov/legis/statutes/35-A/title35-Ach3.pdf", "label": "legislature.maine.gov", "score": 9.9779891968, "published": false}], "snippet_links": [{"key": "line-extension", "type": "definition", "offset": [34, 48]}, {"key": "utility-infrastructure", "type": "definition", "offset": [61, 83]}], "hash": "a315be7a64c70998062ba10d4f1f5a2d", "id": 6}, {"snippet": "means the rearrangement or transfer of existing facilities, replacement of a pole, complete removal of any pole replaced or any other changes required to make space available for an additional attachment to a shared-use pole. [PL 2019, c. 127, \u00a71 (NEW).]", "size": 14, "samples": [{"hash": "4itZhnBnO2D", "uri": "https://legislature.maine.gov/statutes/35-a/title35-A.docx", "label": "legislature.maine.gov", "score": 13.0519199371, "published": false}, {"hash": "6hKRnUS1Dt8", "uri": "https://legislature.maine.gov/statutes/35-a/title35-Ach25.docx", "label": "legislature.maine.gov", "score": 11.0395975113, "published": false}, {"hash": "f72nv7oruzj", "uri": "https://www.mainelegislature.org/legis/statutes//35-A/title35-Ach25.pdf", "label": "www.mainelegislature.org", "score": 10.0395975113, "published": false}], "snippet_links": [{"key": "transfer-of", "type": "definition", "offset": [27, 38]}, {"key": "existing-facilities", "type": "clause", "offset": [39, 58]}, {"key": "replacement-of", "type": "clause", "offset": [60, 74]}, {"key": "removal-of", "type": "definition", "offset": [92, 102]}, {"key": "other-changes", "type": "definition", "offset": [128, 141]}, {"key": "space-available", "type": "definition", "offset": [159, 174]}, {"key": "an-additional", "type": "clause", "offset": [179, 192]}], "hash": "fb330ec0acbd6424309021fe349e4665", "id": 7}, {"snippet": "means the process of ensuring that an", "size": 13, "samples": [{"hash": "fnIFr1yPRfF", "uri": "https://pub.njleg.state.nj.us/Bills/2024/A1500/1133_I1.PDF", "label": "pub.njleg.state.nj.us", "score": 18.5418968201, "published": false}, {"hash": "7JDcWbRlT3O", "uri": "https://pub.njleg.gov/bills/2020/A1500/1116_R1.PDF", "label": "pub.njleg.gov", "score": 15.7384634018, "published": false}, {"hash": "3TvgU1T0WjD", "uri": "https://pub.njleg.gov/bills/2018/A9999/5560_I1.PDF", "label": "pub.njleg.gov", "score": 14.4575986862, "published": false}], "snippet_links": [{"key": "the-process", "type": "clause", "offset": [6, 17]}], "hash": "d83d23cc4b3ed78a04aa1ec4269e1a36", "id": 8}, {"snippet": "means administrative, engineering, or construction activities necessary to make a pole, conduit, or other support equipment available for a new attachment, attachment modifications, or additional facilities. Make ready work costs are nonrecurring costs, and are not contained in carrying charges.", "size": 13, "samples": [{"hash": "ckJybvLcvZF", "uri": "https://edocs.puc.state.or.us/efdocs/HAC/ar506hac122618.pdf", "label": "edocs.puc.state.or.us", "score": 11.2381925583, "published": false}, {"hash": "fGBcqZHXqn1", "uri": "https://edocs.puc.state.or.us/efdocs/HAC/ar506hac103223.pdf", "label": "edocs.puc.state.or.us", "score": 11.1957559586, "published": false}, {"hash": "7a8dnQM7Wit", "uri": "https://edocs.puc.state.or.us/efdocs/HAC/ar506hac15829.pdf", "label": "edocs.puc.state.or.us", "score": 11.1943874359, "published": false}], "snippet_links": [{"key": "construction-activities", "type": "clause", "offset": [38, 61]}, {"key": "equipment-available", "type": "clause", "offset": [114, 133]}, {"key": "additional-facilities", "type": "clause", "offset": [185, 206]}, {"key": "make-ready", "type": "clause", "offset": [208, 218]}, {"key": "work-costs", "type": "definition", "offset": [219, 229]}, {"key": "nonrecurring-costs", "type": "clause", "offset": [234, 252]}, {"key": "contained-in", "type": "definition", "offset": [266, 278]}, {"key": "carrying-charges", "type": "definition", "offset": [279, 295]}], "hash": "27f1efc0e9c4efde0ae1c1a2cad97590", "id": 9}, {"snippet": "means engineering or construction activities necessary to make a pole, duct, conduit, right of way, or other sup- port equipment available for a new attachment, attachment modifica- tions, or additional attachments. Such work may include rearrangement of existing attachments, installation of additional support for the utility pole, or creation of additional capacity, up to and including replacement of an existing pole with a taller pole.", "size": 13, "samples": [{"hash": "98EI2HY2aY5", "uri": "https://lawfilestestext.leg.wa.gov/lawtest/WACPDF/WAC%20480%20%20TITLE/WAC%20480%20-%2054%20%20CHAPTER/WAC%20480%20-%2054%20%20COMBINEDCHAPTER.pdf", "label": "lawfilestestext.leg.wa.gov", "score": 18.2830657959, "published": false}, {"hash": "2IbIMzAmDxW", "uri": "https://lawfilesext.leg.wa.gov/law/WACArchive/2023/pdf/WAC%20480%20%20TITLE/WAC%20480%20-%2054%20%20CHAPTER/WAC%20480%20-%2054%20%20COMBINEDCHAPTER.pdf", "label": "lawfilesext.leg.wa.gov", "score": 18.114610672, "published": false}, {"hash": "4Z7SvtNyI5w", "uri": "https://lawfilestestext.leg.wa.gov/lawtest/WACPDF/WAC%20480%20%20TITLE/WAC%20480%20-%2054%20%20CHAPTER/WAC%20480%20-%2054%20-020.pdf", "label": "lawfilestestext.leg.wa.gov", "score": 17.4452323914, "published": false}], "snippet_links": [{"key": "construction-activities", "type": "clause", "offset": [21, 44]}, {"key": "right-of-way", "type": "clause", "offset": [86, 98]}, {"key": "equipment-available", "type": "clause", "offset": [119, 138]}, {"key": "additional-attachments", "type": "clause", "offset": [192, 214]}, {"key": "installation-of", "type": "clause", "offset": [277, 292]}, {"key": "additional-support", "type": "clause", "offset": [293, 311]}, {"key": "utility-pole", "type": "definition", "offset": [320, 332]}, {"key": "additional-capacity", "type": "clause", "offset": [349, 368]}, {"key": "replacement-of", "type": "clause", "offset": [390, 404]}, {"key": "existing-pole", "type": "definition", "offset": [408, 421]}], "hash": "915083f81b639edee13667ffc05634d1", "id": 10}], "next_curs": "ClwSVmoVc35sYXdpbnNpZGVyY29udHJhY3RzcjgLEhpEZWZpbml0aW9uU25pcHBldEdyb3VwX3Y1NiIYbWFrZS1yZWFkeS13b3JrIzAwMDAwMDBhDKIBAmVuGAAgAA==", "definition": {"snippet": "means all work performed or to be performed to prepare AT&T-22STATE\u2019s Conduit Systems, Poles or Anchors and related Facilities for the requested occupancy or attachment of CLEC\u2019s Facilities. Make-Ready Work includes, but is not limited to, clearing obstructions (e.g., by rodding Ducts to ensure clear passage), the rearrangement, transfer, replacement, and removal of existing Facilities on a Pole or in a Conduit System where such work is required solely to accommodate CLEC\u2019s Facilities and not to meet AT&T-22STATE\u2019s business needs or convenience. Make-Ready Work may require \u201cdig ups\u201d of existing Facilities and may include the repair, enlargement or modification of AT&T-22STATE\u2019s Facilities (including, but not limited to, Conduits, Ducts, Handholes and Manholes) or the performance of other work required to make a Pole, Anchor, Conduit or Duct usable for the initial placement of CLEC\u2019s Facilities.", "size": 489, "title": "Make-Ready Work", "id": "make-ready-work", "examples": ["Any work to be performed to accommodate the requesting licensee shall be negotiated, coordinated and reimbursed directly between the Licensee and the requesting licensee; provided, however, that WAA shall be advised of such request and shall determine, in the exercise of sound engineering judgment whether or not <strong>Make-Ready Work</strong> is necessary or possible or if modification of any license is necessary.", "Customer shall place or have placed by the Company (at Customer\u2019s sole cost and expense) as <strong>Make-Ready Work</strong>, Identification Labels on all of Customer\u2019s Equipment including, but not limited to, cables located within or in close proximity to the Company\u2019s underground Structures and Customer handholes containing circuit Disconnect Devices.", "Customer shall pay the Company for all the Costs of all <strong>Make-Ready Work</strong> in accordance with the provisions of Section 7.2.2 of this Agreement, and shall also arrange with the owner(s) of other attachment(s) on the Pole or within the Structure or other Facility for the transfer or rearrangement of such facilities to accommodate the installation, reconfiguration or removal of the Attachment(s).", "The Company will schedule and perform the required <strong>Make-Ready Work</strong> following its receipt of the executed Authorization for <strong>Make-Ready Work</strong> form and Customer\u2019s advance payment of the estimated amount specified by the Company.", "The Company will endeavor to perform all <strong>Make-Ready Work</strong> to accommodate Customer\u2019s Authorized Attachments as a part of its normal, scheduled workload.", "An advance payment for estimated <strong>Make-Ready Work</strong> is payable prior to the commencement of any actual <strong>Make-Ready Work</strong>.", "Subject to Section 4.3.4 of this Agreement, Customer shall have no obligation to perform <strong>Make-Ready Work</strong> related to the pre-existing conditions of Authorized Attachments or Facilities at a location as of the Effective Date unless and until such time as Customer makes a Material Change that affects that location.", "If Licensee\u2019s request to modify its facilities located in any WAA Conduits or Duct Banks, requires WAA and/or other Licensees to rearrange their respective facilities in order for Licensee to make said modifications, Licensee shall advise WAA of the <strong>Make-Ready Work</strong> it believes necessary to enable the accommodation of Licensee\u2019s facilities and be subject to the terms set forth in Section 10.0 of this Agreement.", "The Parties agree that upon completion of the <strong>Make-Ready Work</strong> by the Company, no adjustment of the <strong>Make-Ready Work</strong> amount paid by Customer shall be made to reflect the Company\u2019s actual Costs of performing the <strong>Make-Ready Work</strong>, whether or not the Company\u2019s actual Costs are more or less than the estimated costs paid by Customer.", "<strong>Make-Ready Work</strong> performed by WAA to accommodate Licensee\u2019s facilities shall be included in the normal work load schedule of WAA."], "related": [["day-work", "DAY WORK", "DAY WORK"], ["job-work", "job work", "job work"], ["work-crew", "Work crew", "Work crew"], ["new-work", "New Work", "New Work"], ["the-work", "The Work", "The Work"]], "related_snippets": [], "updated": "2025-07-24T04:27:56+00:00"}, "json": true, "cursor": ""}}