FGMP definition
Examples of FGMP in a sentence
All discounts, rebates, and refunds shall accrue to the Authority, and there shall be a commensurate reduction to the GMP (including a reduction in the FGMP by Change Order, as applicable).
Savages and Civility: Indians and Englishmen in Colonial Virginia.
The DB Contractor shall update and refine the FGMP Proposal by comparing the proposed FGMP against a revised estimate of projected costs prepared (a) at the approval by the Authority of 100% complete and approved Construction Documents for the entire Work (or earlier if agreed by the parties) and (b) upon receipt and acceptance of Subcontract bids for each Work Package (or for all major trade items included therein) in accordance with Subsection 10.2.3 (Subcontract Bidding and Award).
The State Parties, and the Program Manager on their behalf, shall each be entitled to full access to the details of the DB Contractor’s process for developing any proposed Work Package breakdown, Schedule of Values, Work Package bid documents, Work Package GMP Proposal, Work Package Authorization, GMP Amendment, FGMP Proposal, and FGMP Amendment, including all supporting documentation as described in Subsection 4.1.5.2(b) (Work Package GMP Proposal).
If the Authority refuses or fails to timely approve the FGMP Proposal, or rejects the FGMP Proposal, or the parties fail to timely execute the FGMP Amendment, the Authority may suggest modifications to the FGMP Proposal.
The DB Contractor shall make appropriate adjustments to the FGMP Proposal, its bases, or both, and return an updated FGMP Proposal package to the ADOC and Program Manager for review and comment by the Program Manager, the ADOC, and the Authority.
If such modifications are accepted in writing by the DB Contractor, the parties shall proceed with executing the FGMP Amendment (reflecting such modifications) in accordance with Subsection 4.1.5.8 (FGMP Amendment) above.
If projected cost to Project completion values exceed amounts remaining to Project completion, the Construction Manager shall provide a detailed proposal on how it will complete the Project within the General Conditions/Requirements value established at FGMP or as modified by previous Change Order to comply with the Standard of Care requirements of this Agreement.
In confirmation and furtherance of the terms and provisions of this Subsection 12.2.5, the DB Contractor acknowledges and agrees that each GMP (including the FGMP and each Work Package GMP) and the Contract Time may only be adjusted in accordance with, and to the extent permitted by, the terms and provisions of this Section 12.2 (Excusable Events).
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), assumptions and qualifications set forth in Exhibit J – IGMP and FGMP Estimates, Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein.