Examples of Execution of the Works in a sentence
TIME FOR COMPLETION 7.1 Execution of the Works The Contractor shall commence the Works on the Commencement Date and shall proceed expeditiously and without delay and shall complete the Works, subject to Sub-Clause 7.3 below, within the Time for Completion.
TIME FOR COMPLETION 237.1 Execution of the Works 237.1.1 Progress Review Meetings 237.2 Programme 237.2.1 Intended Construction Procedures, Order and Methods 237.2.2 Programme Updating 2310.
TIME FOR COMPLETION7.1 Execution of the Works The Contractor shall commence the Works on the Commencement Date and shall proceed expeditiously and without delay and shall complete the Works, subject to Sub-Clause 7.3 below, within the Time for Completion.
TIME FOR COMPLETION 7.1 Execution of the Works Add new sub-clause to 7.1.1: 7.1.1 Progress Review MeetingsRegular progress review meetings between the Employer and the Contractor shall be held at times decided by the Engineer.
TIME FOR COMPLETION 7.1 Execution of the Works The Contractor shall commence the Works on the Commencement Date and shall proceed expeditiously and without delay and shall complete the Works within the Time for Completion.
The Contractor shall be responsible for making all its arrangements, for and paying all charges in connection with the supply and consumption of electricity and water and the disposal of sewage and other waste as may be necessary for the design and Execution of the Works including the construction, erection, testing and commission of the Project Facility at a convenient point within the Project Site which enables the Contractor to carry on its obligations under this Contract without any hindrance.
The Contractor shall assume full responsibility for the design and Execution of the Works in accordance with the Contract so as to meet the Time for Completion.
We have been organized in connection with this offer and have not carried on any activities other than purchasing shares of Energy Partners, Ltd.
The Contractor shall with the said detailed programme, submit a supporting method statement and resource schedule, consistent with similar schedules submitted with the Tender, which shall include a programme narrative giving a general description of the methods which the Contractor intends to adopt in the Execution of the Works and details and measures that the Contractor has adopted to ensure its obligations under the Contract are fulfilled.
Within the first week of every month from the issue of the Notice to Proceed during the Execution Period or at such intervals as WAPCOS Limited Representative may direct, the Contractor shall meet with WAPCOS Limited Representative and any of the Relevant Authority and any Related Works Contractors and any of their respective advisers as will be reasonably entitled to attend, to review the development of the design and Execution of the Works (“Review Meetings”).