Construction Milestone Date definition

Construction Milestone Date means the date of completion of a defined part of the Work that is less than the entire Work and as particularly described in the Final Construction Schedule.
Construction Milestone Date means, in relation to the Development, each expected date for the completion of relevant Construction Milestone, as outlined in Schedule 10 (Construction Milestones) of the Paying Agency Agreement, including, for the avoidance of doubt, the First Construction Milestone Date and the Second Construction Milestone Date;
Construction Milestone Date shall be set to ninety (90) Days following the Effective Date with regards to Early Termination in Section 2.3.

Examples of Construction Milestone Date in a sentence

  • Within ten (10) Days after the end of each Month during the Consents Period of the Project, Seller shall deliver a written report to Buyer describing the progress and current schedule of permitting activities of the Project, including any events of material significance to Seller’s ability to develop the Project or meet the Construction Milestone Date.

  • The Concessionaire shall commence the Construction Works on the Commencement Date and hereby undertakes to perform and complete the same: in accordance with the Applicable Standards and the Construction Requirements; and within the Construction Time For Completion including completion of each Project Construction Milestone on or prior to its respective Project Construction Milestone Date.

  • It was proposed by Cllr Hurley and Cllr Moody Jones that the minutes be accepted.

  • The Department wants to see how the date submitted (Construction Milestone Date) in conjunction with the Gantt chart portray an accurate and obtainable date for this project milestone.

  • It remains understood that if the Second Construction Milestone is not met by the Second Construction Milestone Date, the Petrella 6 Distribution Proceeds will be transferred, for an amount which is equal to the difference between paragraphs (i) and (ii) above, on the fifth Business Day following Second Construction Milestone Date, into the Cash Reserve Account, for application in accordance to paragraph (iv) of Condition 14.6.2.

  • The Construction Milestone Date is defined as the date at which as a minimum the following activities shall be completed: All exterior building work, all base and binder paving of the site work area, all construction of the curbed island areas, concrete sidewalk entrance to building including concrete area that envelopes the building perimeter.

  • The Contractor will be scored based on the fewest calendar days from 10 days following Award to Construction Milestone Date.

  • Submittals will be evaluated based on a 50-50 Price – Technical based weighting, and according to the criteria and elements as shown in the following “Best Value Selection Scoring Criteria” table and as outlined in this Section: Best Value Selection Scoring Criteria This is almost strictly a mathematical scoring to determine the “Best value” and is based on Price and Construction Milestone Date,.

  • Technical submissions shall be bound, with tabs for the Cover Letter and the Technical Section (Construction Milestone Date),.

  • If Buyer fails to achieve the Construction Commencement Milestone by the Construction Milestone Date, then Buyer shall provide a Remedial Action Plan to Seller and shall use commercially reasonable efforts to implement the Remedial Action Plan.

Related to Construction Milestone Date

  • Milestone Date means the date set against the relevant Milestone in the Implementation Plan;

  • Project Milestone means the project milestone set forth in Schedule-J;

  • Project Milestones means the project milestones set forth in Schedule-G;

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Construction Completion Date means the date by which the overall development of the Project is completed in accordance with the provisions of this Agreement and when the Construction Completion Certificate is issued by the Independent Engineer as per Article 14.1.

  • Substantial Completion Date means the date on which Substantial Completion occurs.

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Final Completion Date means the date on which Final Completion occurs.

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Milestone 2 means achievement of annual Net Sales of at least $35,000,000 during any Calendar Year ending on or before December 31, 2024.

  • Milestone Dates means the dates for completion of specified Project activities as contained in the Project Schedule.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Project Completion means completion of the Redevelopment in accordance with this Agreement to the state where the whole of the Morley Shopping Centre, as so redeveloped, is capable of occupation for its intended purpose;

  • Development Milestone Event has the meaning set forth in Section 7.1.

  • Milestone 1 means achievement of annual Net Sales of at least $20,000,000 during the Calendar Year ending on December 31, 2021.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Milestone Event has the meaning set forth in Section 8.4.

  • Scheduled Project Completion Date shall have the meaning specified in Section 6.3 (c);

  • Construction Completion means physical construction of a cleanup action component is complete.

  • Successful Completion means that in the reasonable opinion of the Customer, Deliverables completed by the Supplier are fit for purpose, completed on time and otherwise meet all the criteria defined under this Contract;

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Milestone Events has the meaning set forth in Section 3.3 (Milestone Payments).