Commercial Operations Long Stop Date definition

Commercial Operations Long Stop Date means midnight on the date which is twelve (12) months after the Scheduled Commercial Operations Date;
Commercial Operations Long Stop Date means [•] or such

Examples of Commercial Operations Long Stop Date in a sentence

  • If for any New Shipper GLNG fails to cause the Commercial Operations Date to occur by the Commercial Operations Long Stop Date, then (without prejudice to GLNG’s obligation to pay liquidated damages pursuant to paragraph 1.7) the New Shipper may by notice in writing to GLNG elect to treat the delay as a Default which is not capable of being cured by GLNG for the purposes of Section C6.1.1(c) of the New Shipper GTCs.