DEVELOPMENT AGREEMENT NO. 00-000-00
FETCH & STUFF PHASE 2 -- 1997
-----------------------------
This Development Agreement is entered into on the 24TH day of JANUARY,
1997 by and between U S WEST Advanced Technologies, Inc., a Colorado
corporation ("USW-Technologies"), U S WEST Communications, Inc., a Colorado
corporation ("USW-Communications"), (hereinafter USW-Technologies,
USW-Communications and their Affiliates will be collectively referred to as
"Licensee"), and Carnegie Group, Inc., a Delaware corporation with a principal
place of business at Xxxx XXX Xxxxx, Xxxxxxxxxx, XX 00000 ("CGI").
ARTICLE 1 - RECITALS
--------------------
1.1 Licensee and CGI entered into a General License Agreement (the
"GLA") on December 17, 1992 in which the parties committed to enter into a
series of Artificial Intelligence ("AI") technology research, experimentation
and development agreements ("Development Agreements") over a period beginning
on the Effective Date, as defined in the GLA, and ending on the fourth
anniversary of the Effective Date, and extended through mutual consent through
March 15, 1997.
1.2 Licensee and CGI now desire to enter into this Development
Agreement pursuant to which the parties, as contemplated by the GLA, will
commit to a project of specific research, experimentation and development as
stated herein.
NOW, THEREFORE, in consideration of the mutual covenants set forth in
this Development Agreement, Licensee and CGI agree as follows:
ARTICLE 2 - DEFINITIONS
-----------------------
2.1 Defined terms used in this Development Agreement shall have the
meanings set forth in Article 2 of the GLA, unless different meanings are
specifically set forth in this Development Agreement.
2.2 "Project" means the specific research, experimentation and
development which CGI will perform for Licensee under this Development
Agreement.
00-000-00 1 JANUARY 24, 1997
3
2.3 "Project Description" means a detailed written description of
the Project, including but not limited to:
(a) any Deliverable Performance Specifications; and
(b) a listing which identifies and describes, as to the
Project:
(i) any Deliverables intended to be created in the
course of the Project; and
(ii) any Licensee Specific Technology intended to be
created in the course of the Project; and
(iii) any Licensee Proprietary Information or Licensee
Confidential Information to be made available to
CGI in the course of the Project; and
(iv) any Generic Research Technology intended to be
created in the course of the Project.
2.4 "Projected Cost" means that projected cost referred to in Article 9
of the GLA and set forth in Article 5 hereof.
2.5 "Projected Date" means the projected date for completion of the
Project agreed upon by the parties and set forth in Article 6 hereof, including
any Agreed Completion Date.
ARTICLE 3 - EFFECT OF THE GLA
-----------------------------
This Development Agreement is subject in all respects to the terms and
conditions of the GLA. Ownership of Generic Research Technology developed
hereunder is vested in U S WEST, in accordance with Article 3.3 of the GLA and
the payment of ALLIANCE rates by Licensee to CGI as provided in Exhibit 2,
attached hereto.
ARTICLE 4 - PROJECT DESCRIPTION
-------------------------------
4.1 The Project Description is set forth in Exhibit 1 attached hereto.
4.2 CGI shall use its best efforts to complete the Project in
accordance with the Project Description. Except for the warranties set forth in
Article 8 of the GLA regarding any Deliverable Performance Specifications set
forth in Exhibit 1 of this Development
00-000-00 2 JANUARY 24, 1997
4
Agreement, CGI hereby disclaims any express or implied warranty that all or any
portion of the Project intended to be created or developed pursuant to this
Development Agreement will perform in accordance with the Project Description
or any other criteria.
ARTICLE 5 - PROJECTED COST; PAYMENT
-----------------------------------
5.1 CGI's Projected Cost for the Project is $[ ]. An itemized
account of the Projected Cost including person-year rates applied as Alliance,
Technology and/or Co-Development Rates as defined in the GLA is set forth in
Exhibit 2 attached hereto. Modifications to the Projected Cost (and any payments
under Section 5.2) shall be governed by Sections 9.4 and 14.7 of the GLA.
5.2 Licensee shall pay to CGI, in consideration for CGI's performance
of its obligations under this Development Agreement, the sum of $ * in
accordance with the payment schedule set forth in Article 5 of the GLA.
"*" REPRESENTS TIME AND MATERIAL COSTS IN ACCORDANCE WITH EXHIBIT 2 OF THIS
DEVELOPMENT AGREEMENT.
ARTICLE 6 - PROJECTED DATE
--------------------------
6.1 The Projected Date for completion of the Project is DECEMBER 31,
1997. A time schedule listing projected dates for completion of interim stages
of the Project is set forth in Exhibit 3 attached hereto.
6.2 CGI shall use its best efforts to complete the Project by the
Projected Date. Except for the obligations set forth in Article 9 of the GLA
regarding any Agreed Completion Date set forth in Exhibit 3 of this Development
Agreement, CGI hereby disclaims any express or implied warranty that all or any
portion of the Project intended to be created or developed pursuant to this
Development Agreement will be completed on any date certain, including the
Projected Date.
ARTICLE 7 - TERMS OF DELIVERY AND RISK OF LOSS
----------------------------------------------
7.1 CGI will deliver, at its expense, to Licensee any Deliverables and
Licensee Specific Technology in accordance with the Exhibits hereto.
7.2 CGI will bear the risk of loss or destruction of such Deliverables
and Licensee Specific Technology until the delivery of such items to Licensee
at the location designated
00-000-00 3 JANUARY 24, 1997
5
by Licensee. For the purposes hereof, "delivery" shall mean physical delivery
to a facility and shall not include installation.
ARTICLE 8 - INSTALLATION
------------------------
8.1 CGI will provide, at Licensee's request and expense, technical
assistance to Licensee sufficient for the proper installation of Deliverables
and Licensee Specific Technology in Licensee facilities. Such assistance may
include, if deemed necessary by Licensee, the presence of one or more CGI
employees at Licensee facilities to assist in such installation. Licensee will
pay, in accordance with the GLA, travel, room and board expense incurred by
such employees of CGI.
8.2 Licensee will bear the risk of loss or destruction of the
Deliverables, Licensee Specific Technology or any other items delivered to
Licensee facilities during and after installation.
ARTICLE 9 - OPERATIONAL TRAINING
--------------------------------
CGI will provide, in accordance with Article 6 of the GLA, adequate
training to no more than 0 Licensee employees regarding the proper operation
and use of Deliverables, Licensee Specific Technology and Generic Research
Technology created in the course of the Project.
ARTICLE 10 - MAINTENANCE
------------------------
CGI will perform maintenance and repair services on Deliverables,
Licensee Specific Technology and Generic Research Technology in accordance with
the GLA.
ARTICLE 11 - MODIFICATIONS AND AMENDMENTS
-----------------------------------------
Any modifications to the Project or to this Development Agreement,
including but not limited to modifications to the Project Description, the
Projected Costs, or the Projected Date, to which the parties agree after the
date of execution of the Development Agreement, will be evidenced by a written
supplement to this Development Agreement executed by both parties.
00-000-00 4 JANUARY 24, 1997
6
ARTICLE 12 - DISPUTE RESOLUTION
-------------------------------
12.1 Any claim, controversy or dispute which arises between the
parties, their agents, employees, officers, directors or affiliates ("Dispute")
which the parties are unable to settle through consultation and negotiation may
be mediated under the Commercial Mediation Rules of the American Arbitration
Association ("AAA") by a mutually acceptable mediator. Any Dispute which cannot
be resolved through negotiation or mediation shall be resolved by binding
arbitration as provided in this Article. The arbitrability of claims shall be
determined under the Federal Arbitration Act, 9 USC Secs. 1-15. Notwithstanding
the foregoing, the parties may cancel or terminate this Agreement in accordance
with its terms and conditions without being required to follow the procedures
set forth in this Article.
12.2 A single arbitrator engaged in the practice of law, who is
knowledgeable about the subject matter of this Agreement and the matter in
Dispute, shall conduct the arbitration under the rules of the AAA then in
effect, except as otherwise provided herein. The arbitrator shall be selected
in accordance with AAA procedures from a list of qualified people maintained by
the AAA. The arbitration shall be conducted in Denver, Colorado, and all
expedited procedures prescribed by the AAA rules shall apply. The laws of
Colorado shall govern the construction and interpretation of this Agreement.
The arbitrator's decision and award shall be final, conclusive and binding, and
judgement may be entered upon it in accordance with applicable law in any court
having jurisdiction thereof.
12.3 Either party may request from the arbitrator injunctive relief to
maintain the status quo until such time as the arbitration award is rendered or
the Dispute is otherwise resolved. The arbitrator shall not have authority to
award punitive damages. Each party shall bear its own costs and attorneys'
fees, and the parties shall share equally the fees and expenses of the mediator
and arbitrator.
12.4 If any party files a judicial or administrative action asserting
claims subject to arbitration, as prescribed herein, and another party
successfully stays such action and/or compels arbitration of said claims, the
party filing said action shall pay the other party's costs and expenses
incurred in seeking such stay and/or compelling arbitration, including
reasonable attorneys' fees.
12.5 CGI agrees that in the event of any Dispute between the parties,
it will continue to provide Purchases without interruption.
12.6 CGI shall include in all contracts with its subcontractors
provisions similar to those in this Article, requiring that all disputes in any
way involving Licensee shall be settled by binding arbitration.
00-000-00 5 JANUARY 24, 1997
7
ARTICLE 13 - INTEGRATION
------------------------
This Development Agreement, the Exhibits attached hereto and the terms
of the GLA set forth the entire and exclusive agreement and understanding of
the parties relating to the subject matter contained herein, and supersede all
prior and contemporary discussions. Neither party will be bound by any
definition, condition, warranty or representation except as expressly set forth
in this Development Agreement or the GLA or as subsequently set forth in
writing signed by authorized representatives of each party.
IN WITNESS WHEREOF, Licensee and CGI have executed this Development
Agreement in duplicate by their respective authorized representatives.
CARNEGIE GROUP, INC. LICENSEE
By: /s/ Xxxxxx Xxxxxxxxx By: /s/ Xxxxxx X. Xxxxxxx
------------------------- ------------------------------
Title: President/CEO Title: VP/IAD
--------------------- --------------------------
Date: 1/31/97 Date: 1/31/97
--------------------- --------------------------
U S WEST Business Resources, Inc.
Acting as Agent for: LICENSEE
By:
-------------------------------
Title:
----------------------------
Date:
----------------------------
00-000-00 6 JANUARY 24, 1997
8
EXHIBIT 1 - PROJECT DESCRIPTION
-------------------------------
OVERVIEW
This Development Agreement outlines the proposed scope of consulting services
to be performed by Carnegie Group, Inc.(CGI) for U S WEST's Fetch & Stuff
Engine within the overall framework of the Developing Advanced Routine Tools
(DART) strategy. Xxxxxx Xxxxx 0 of the Fetch & Stuff project, CGI provided U S
WEST with a proof of concept "Fetch & Stuff" Engine and associated short term
deliverables that support U S WEST's overall development efforts for the DART
project. This Development Agreement outlines the Fetch & Stuff Phase 2 project
that will provide enhancements and modifications to the proof of concept Fetch
& Stuff Engine and associated client software. The Fetch & Stuff Phase 2
project transitions the Fetch & Stuff Engine into a production level system.
From a conceptual level, CGI proposes to provide 3 releases of software during
the 1997 Fetch & Stuff Phase 2 project. These will occur in 1997 and are
identified as Group A, B and C Project Work Items. These translate as shown
below:
------------- -------------------------------------------------------------------------------------------
GROUP PROJECT WORK ITEM DESCRIPTION
------------- -------------------------------------------------------------------------------------------
A Additional Messages (SONAR Transactions)
------------- -------------------------------------------------------------------------------------------
A Additional Legacy Systems (SONAR Transaction API)
------------- -------------------------------------------------------------------------------------------
A Inventory Control Services (Usage and Defect counts)
------------- -------------------------------------------------------------------------------------------
A Product Deployment (Alarming, Product Support and Mtce., etc.)
------------- -------------------------------------------------------------------------------------------
------------- -------------------------------------------------------------------------------------------
B Failover Enhancements (Hardware & Software)
------------- -------------------------------------------------------------------------------------------
B Dynamic routing (API priorities, Oracle rule-driven)
------------- -------------------------------------------------------------------------------------------
B Increase robustness of F/S server (Performance, Scaleability, # of
> users, etc.)
------------- -------------------------------------------------------------------------------------------
B Load Balancing
------------- -------------------------------------------------------------------------------------------
------------- -------------------------------------------------------------------------------------------
C New Routing Destinations (Interface/interact with Call Handling)
------------- -------------------------------------------------------------------------------------------
C Routing Administration Environment
------------- -------------------------------------------------------------------------------------------
C One Stop Shopping
------------- -------------------------------------------------------------------------------------------
------------- -------------------------------------------------------------------------------------------
ABC Documentation (SYAD guide, deployment guide, req doc, design doc updates)
------------- -------------------------------------------------------------------------------------------
00-000-00 7 JANUARY 24, 1997
9
High-level timeframes associated with the Project Work Item groupings shown
above are envisioned as follows:
* GROUP A - February, March, April - 1997
* GROUP B - April, May, June, July - 1997
* GROUP C - July through December - 1997
As Fetch & Stuff is deployed in a staged rollout to production in 1997, CGI
realizes that there may be unanticipated "engine" architecture or strategy
changes necessary to accommodate the needs of the U S WEST client user base.
As such, we are flexible to re-evaluate the Project Work Items scoped for
completion during the July-December timeframe as necessary. We envision any
significant scope substitutions to be mutually agreed to by U S WEST and CGI,
and, if changes to the resource mix or the overall work hours estimate occurs,
the two companies will mutually execute a Change Order to formally amend this
Development Agreement. As each group of Project Work Items is completed, CGI
and U S WEST will reassess the remaining planned work list for each subsequent
project stage before starting work on the next release group of Project Work
Items.
The CGI deliverables provided under this 3-release 1997 project will provide
U S WEST with a manageable long term production solution that puts an
architecture and framework in place to support current and future Service
Delivery functions. We believe that this incremental, "staged" approach to the
overall project allows U S WEST to continue to partner with CGI and leverage
business and technical resources to meet the organizational needs of the
project. It also positions both companies to be mutually successful in this
1997 effort.
CGI ROLES AND RESPONSIBILITIES
The following activities are to be performed by CGI:
* Develop an overall project schedule for this effort based on joint CGI/U S
WEST input.
* Create monthly status reports documenting project progress.
* Update (as needed) the inventory and interface protocol documents of
existing interfaces to selected legacy systems ([ ], [ ], [ ],
[ ] Transactions, etc.). The following information is provided for each
interface:
-> Purpose of the interface
-> Ownership organization
-> Project (business/technical purpose) for which the interface was
developed
-> Interface approach (e.g. TN3270 or API)
-> Current status (development, production, etc.)
* Update the following technical documentation for the enhanced Fetch & Stuff
production system:
-> High level Requirements Specification
-> High level Design Specification
-> Integration Test Plan
00-000-00 8 JANUARY 24, 1997
10
-> Interface Message Specification Document
-> Architecture Document
* Design/develop/implement the planned enhancements or modifications to major
components of the Fetch & Stuff Engine system. These are detailed in the
Scope and Deliverables section below.
* Conduct unit and integration testing for the enhanced Fetch & Stuff Engine.
* Provide knowledge transfer to U S WEST for maintenance, training, and
ongoing support.
* Support system and acceptance testing.
* Provide software support and technical assistance to fix Problem Reports
identified in the software releases during 1997.
U S WEST ROLES AND RESPONSIBILITIES
The following activities are to be performed by U S WEST:
* Provide subject matter expertise on legacy systems as needed by the project
schedules.
* Acquire and install all development hardware and software required by the
end of Week 2 of each collection of Project Work Items as grouped into
category A, B or C in the preceding table.
* Provide communication network access from the development server to each
legacy system that U S WEST directs CGI to implement in the Fetch & Stuff
Engine during 1997.
* Provide system administration and database administration for software and
hardware platforms.
* Specify documentation standards, formats, and templates that CGI is required
to follow in all project deliverables by the end of week 2 of each Project
Work Item category grouping.
* Provide project management and appropriate sponsorship support to aid CGI in
gaining access to internal IT groups who provide either legacy system
expertise and/or software.
* Manage scope and expectations with end user clients.
* System test and acceptance test the DART system environment with the Fetch &
Stuff Engine incorporated.
* Conduct user training for the DART system environment with the Fetch & Stuff
Engine included.
JOINT CGI AND U S WEST ROLES AND RESPONSIBILITIES
CGI and U S WEST are jointly responsible for the following activities:
* Identification and acceptance decision on which legacy system interfaces are
in a production-ready state and are to be included in the enhanced Fetch &
Stuff Engine by the end of week 2, for each Project Work Item group.
* Develop high-level system administration notes for the enhanced production
Fetch & Stuff Engine.
* Hold weekly status meeting where time, progress, plans, and issues are
presented and action items are assigned for resolution.
00-000-00 9 JANUARY 24, 1997
11
* Follow change management procedures. (It is anticipated that U S WEST has
already defined change management procedures. Otherwise, CGI's standard
change management procedures can be incorporated into this project.)
* Define the success criteria for the project.
* Develop documentation and present information at Architecture and
operational readiness reviews.
* Monthly project review.
GENERAL PROJECT SCOPE AND DELIVERABLES
The following comprise the general scope and deliverables envisioned by CGI for
all releases of this project:
* High level System Requirements Specification. This documents the joint
success criteria for the project and the individual requirements that the
Fetch & Stuff Engine must provide.
* High level System Design Specification. This documents the development
hardware and software platforms and system design elements. This will be
delivered at the end of the development interval so that it includes the
final version of the software design.
* Interface Specification Document. This describes the various APIs supported
by the Fetch & Stuff Engine module.
* Provide enhanced NT OLE Server API to the front end interface to Fetch &
Stuff Engine facility.
* Monthly status report documenting the CGI team progress during that month.
* The enhanced Fetch & Stuff Engine software (developed in C++ on the UNIX
OS). This includes the legacy system interfaces.
* The delivered Fetch & Stuff Engine software which has been unit tested and
integrated with a test client program.
A detailed description and outline of the specific deliverables for this
project can be found in Exhibit 4 of this Development Agreement.
The deliverables embodied in this Development Agreement will contain portions
of CGI-proprietary technology known as XXX, which are being provided to U S
WEST as CGI Background Technology, for purposes of this Development Agreement.
SUMMARY
The consulting business and technical services outlined in this document
provide U S WEST with a cost-effective framework for rapid success while
incorporating a robust and scaleable production environment over 1997. As
envisioned by CGI, the Fetch & Stuff
00-000-00 10 JANUARY 24, 1997
12
Engine (to be enhanced and modified under this Development Agreement) and
associated environment is as shown in Figure 1 on the following page.
[ ]
Figure 1 - Fetch & Stuff Environment
This Development Agreement specifically covers the continuing Legacy Systems
Interface Code Inventory and Fetch & Stuff Engine enhancements and
modifications efforts to be performed by CGI from February 1, 1997 through
December 31, 1997.
CGI EXPERIENCE
CGI offers U S WEST a proven approach that allows for procurement and
acquisition of business/technical resources at the pace the business/project
needs, and a proven record of success in Legacy Systems Interface Project Work.
CGI has a long-standing track record of success with U S WEST that includes
successful project experience with the following:
Call Handling
* Fetch & Stuff Phase 1 (Proof of Concept)
* Interface to 5ESS, 1AESS, DMS100 switches on the Soft Dial Tone ASAP project
* Interface to SDT via ASAP project
* Teaming with U S WEST Soft Dial Tone team and INI to build SOAC interface
* Interface to [ ] pricing and availability tables on CASH project
* Interface to [ ] for C-LINK Sales Assistant
* CSSP evaluation of interfaces built using CONNAPI for Screen Scraping to
00-000-00 11 JANUARY 24, 1997
13
[ ], [ ], and [ ] for repair information
Interface to [ ], [ ], [ ] and Work
Manager via ARMAR
CGI has the seasoned, available talent to partner with U S WEST for this
project. We can continue to provide business and technical resources very
quickly to be flexible and responsive to U S WEST's needs. Finally, CGI brings
a track record of performance and success in the initial proof of concept
activities to continue the momentum for the 1997 production rollout of the
Fetch & Stuff project.
00-000-00 12 JANUARY 24, 1997
14
EXHIBIT 2 - ESTIMATED COST
--------------------------
COST OVERVIEW
The total cost of the work net of discounts is estimated at $[ ] based on
expected time and material expenses. No travel is anticipated for this project.
Should travel be required, U S WEST agrees to pay CGI travel expenses for all
pre-approved trips.
Work will be provided on a time and materials basis. The cost estimate and
applicable discount breakouts being extended are as shown below. The [ ]%
Alliance Discount has been extended pursuant to the GLA extension executed
between U S WEST and CGI in December, 1996. The [ ]% Facilities Discount
(includes [ ]% computer and [ ]% building discount) is extended under the
assumption that all work will be performed at U S WEST facilities for this
project. CGI has extended the [ ]% Volume Discount in recognition of this being
a significant follow-on to the original proof of concept project, and in
anticipation of this Development Agreement being signed by U S WEST in January
to keep the existing project team in place for the duration of 1997.
-----------------------------------------------------------------------------------------------------------
ITEMIZATION OF COSTS AMOUNTS
-----------------------------------------------------------------------------------------------------------
CONTRACT ENGINEERING COSTS (TIME AND MATERIALS) $[ ]
LESS: [ ]% ALLIANCE DISCOUNT [ ]
LESS: [ ]% VOLUME DISCOUNT [ ]
LESS: [ ]% FACILITIES DISCOUNT [ ]
-----------------------------------------------------------------------------------------------------------
TOTAL CONTRACT ENGINEERING [ ]
-----------------------------------------------------------------------------------------------------------
TRAVEL EXPENSES 0
-----------------------------------------------------------------------------------------------------------
TOTAL DA ESTIMATE: $[ ]
-----------------------------------------------------------------------------------------------------------
00-000-00 13 JANUARY 24, 1997
15
Estimated hours by skill category are as follows:
--------------------------------------------------------------------------------------------------------
CATEGORY NUMBER OF PEOPLE TOTAL ESTIMATED HOURS
--------------------------------------------------------------------------------------------------------
Manager .75 [ ]
Principal Engineer .5 [ ]
Sr. Engineer II 1 [ ]
Sr. Engineer I 3 [ ]
Engineer 1.5 [ ]
--------------------------------------------------------------------------------------------------------
TOTAL PEOPLE / HOURS: 6.75 [ ]
--------------------------------------------------------------------------------------------------------
U S WEST may, at its discretion, close the project or the involvement of CGI
resources by providing a written notice to the CGI Program Manager. If such an
eventuality occurs, the respective resources will be given a ramp down period
of [ ] weeks to find other work. Upon completion of the [ ] week ramp down
period, U S WEST will be obligated to CGI for the time and materials expended
up to and including the [ ] week ramp down.
00-000-00 14 JANUARY 24, 1997
16
EXHIBIT 3 - SCHEDULE & STATEMENT OF WORK
----------------------------------------
TASKS, SCHEDULE, AND STATEMENT OF WORK DELIVERABLES
The high level Fetch & Stuff Phase 2 project activities as proposed by CGI
appears in charts below. Each chart is intended to represent the major tasks
and deliverables over the estimated timeline. The overall schedule for the 3
releases assumes a Project Start Date of February 1, 1996 and an End Date of
December 31, 1997.
GROUP A TASKS [FEBRUARY--APRIL, 1997]
-------------------------- ----------------------- ------------------- ------------------ ----------------------
TASKS Responsibility START DATE END DATE DELIVERABLES
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Develop schedule CGI 2/1/97 2/6/97 schedule
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Define Success Joint 2/1/97 2/14/97 success criteria
Criteria
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Client SME U S WEST 2/1/97 3/15/97 SMEs assigned
Available
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Requirements Dev CGI 2/1/97 2/14/97 Requirements
& Analysis Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Req. Review U S WEST 2/15/97 2/21/97 feedback
-------------------------- ----------------------- ------------------- ------------------ ----------------------
HW & SW System U S WEST 2/14/97 Development
Available Platform
Available
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide HW/SW U S WEST 2/1/97 3/15/97 Support
system guidance &
Sys admin
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design CGI 2/15/97 2/28/97 Design Draft
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design Doc CGI 2/24/97 3/21/97 Design
Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design Review U S WEST 2/1/97 3/28/97 feedback
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Software CGI 2/1/97 3/14/97 Software
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Unit Test CGI 3/10/97 3/21/97 Unit tested
software
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Integration Test CGI 3/22/97 3/28/97 Int. tested
software
-------------------------- ----------------------- ------------------- ------------------ ----------------------
00-000-00 15 JANUARY 24, 1997
17
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide Support for U S WEST 3/22/97 3/28/97 Support
integration testing
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Interface CGI 2/1/97 3/28/97 Document
Specification
Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Test Team U S WEST 3/17/97 3/21/97 Test Team
in Place assigned
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Test Plan U S WEST 3/18/97 3/28/97 System Test Plan
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System CGI 3/17/97 3/28/97 System
Administration Administration
Document Document
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System U S WEST 3/31/97 4/4/97 Training
Administration
Training and
Documentation
Review
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Testing U S WEST 3/31/97 4/11/97 Testing
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide System CGI 3/31/97 4/11/97 Test Support &
Testing Support Software
Maintenance
Releases
-------------------------- ----------------------- ------------------- ------------------ ----------------------
GROUP B TASKS [APRIL--JULY, 1997]
-------------------------- ----------------------- ------------------- ------------------ ----------------------
TASKS Responsibility START DATE END DATE DELIVERABLES
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Develop schedule CGI 4/14/97 4/18/97 schedule
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Define Success Joint 4/14/97 4/25/97 success criteria
Criteria
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Client SME U S WEST 4/14/97 7/18/97 SMEs assigned
Available
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Requirements Dev CGI 4/14/97 5/2/97 Requirements
& Analysis Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Req. Review U S WEST 5/5/97 5/9/97 feedback
-------------------------- ----------------------- ------------------- ------------------ ----------------------
HW & SW System U S WEST 4/25/97 Development
Available Platform
Available
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide HW/SW U S WEST 4/14/97 7/18/97 Support
system guidance &
Sys admin
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design CGI 4/21/97 5/9/97 Design Draft
-------------------------- ----------------------- ------------------- ------------------ ----------------------
00-000-00 16 JANUARY 24, 1997
18
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design Document CGI 4/28/97 7/11/97 Design
Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Design Review U S WEST 5/12/97 5/16/97 feedback
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Software CGI 5/5/97 6/6/97 Software
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Unit Test CGI 6/2/97 6/27/97 Unit tested
software
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Integration Test CGI 6/30/97 7/4/97 Int. tested
software
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide Support for U S WEST 6/30/97 7/4/97 Support
integration testing
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Interface CGI 4/14/97 7/18/97 Document
Specification
Document
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Test Team U S WEST 6/20/97 6/20/97 Test Team
in Place assigned
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Test Plan U S WEST 6/23/97 7/4/97 System Test Plan
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System CGI 6/23/97 7/4/97 System
Administration Administration
Document Document
Development
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System U S WEST 7/7/97 7/11/97 Training
Administration
Training and
Documentation
Review
-------------------------- ----------------------- ------------------- ------------------ ----------------------
System Testing U S WEST 7/7/97 7/18/97 Testing
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Provide System CGI 7/7/97 7/18/97 Test Support &
Testing Support Software
Maintenance
Releases
-------------------------- ----------------------- ------------------- ------------------ ----------------------
GROUP C TASKS [JULY--DECEMBER, 1997]
-------------------------- ----------------------- ------------------- ------------------ ----------------------
TASKS Responsibility START DATE END DATE DELIVERABLES
-------------------------- ----------------------- ------------------- ------------------ ----------------------
Develop schedule CGI 7/21/97 7/25/97 schedule
---------------------------- --------------------- ----------------- ----------------- -----------------------
Define Success Joint 7/21/97 8/1/97 success criteria
Criteria
---------------------------- --------------------- ----------------- ----------------- -----------------------
Client SME Available U S WEST 7/21/97 12/31/97 SMEs assigned
---------------------------- --------------------- ----------------- ----------------- -----------------------
00-000-00 17 JANUARY 24, 1997
19
---------------------------- --------------------- ----------------- ----------------- -----------------------
Requirements Dev & CGI 7/21/97 8/15/97 Requirements
Analysis Document
---------------------------- --------------------- ----------------- ----------------- -----------------------
Req. Review U S WEST 8/18/97 8/22/97 feedback
---------------------------- --------------------- ----------------- ----------------- -----------------------
HW & SW System U S WEST 8/4/97 Development
Available Platform Available
---------------------------- --------------------- ----------------- ----------------- -----------------------
Provide HW/SW U S WEST 8/5/97 12/31/97 Support
system guidance &
Sys admin
---------------------------- --------------------- ----------------- ----------------- -----------------------
Design CGI 8/4/97 8/29/97 Design Draft
---------------------------- --------------------- ----------------- ----------------- -----------------------
Design Document CGI 8/11/97 12/31/97 Design Document
---------------------------- --------------------- ----------------- ----------------- -----------------------
Design Review U S WEST 9/1/97 9/5/97 feedback
---------------------------- --------------------- ----------------- ----------------- -----------------------
Software CGI 9/2/97 10/10/97 Software
Development
---------------------------- --------------------- ----------------- ----------------- -----------------------
Unit Test CGI 9/29/97 11/17/97 Unit tested
software
---------------------------- --------------------- ----------------- ----------------- -----------------------
Integration Test CGI 11/20/97 12/5/97 Int. tested software
---------------------------- --------------------- ----------------- ----------------- -----------------------
Provide Support for U S WEST 11/20/97 12/5/97 Support
integration testing
---------------------------- --------------------- ----------------- ----------------- -----------------------
Interface CGI 8/1/97 12/31/97 Document
Specification
Document
---------------------------- --------------------- ----------------- ----------------- -----------------------
System Test Team in U S WEST 11/28/97 11/28/97 Test Team
Place assigned
---------------------------- --------------------- ----------------- ----------------- -----------------------
System Test Plan U S WEST 12/1/97 12/12/97 System Test Plan
Development
---------------------------- --------------------- ----------------- ----------------- -----------------------
System CGI 12/3/97 12/14/97 System
Administration Administration
Document Document
Development
---------------------------- --------------------- ----------------- ----------------- -----------------------
System U S WEST 12/17/97 12/21/97 Training
Administration
Training and
Documentation
Review
---------------------------- --------------------- ----------------- ----------------- -----------------------
System Testing U S WEST 12/8/97 12/31/97 Testing
---------------------------- --------------------- ----------------- ----------------- -----------------------
Provide System CGI 12/8/97 12/31/97 Test Support &
Testing Support Software
Maintenance
Releases
---------------------------- --------------------- ----------------- ----------------- -----------------------
00-000-00 18 JANUARY 24, 1997
20
ASSUMPTIONS
The above tasks, schedule and deliverables were developed based on the
following assumptions.
1. The schedule is based on a project start date of February 1, 1997.
Delays in this start date may impact the estimated enhanced Fetch &
Stuff Engine production rollout and associated software delivery dates.
2. The work estimates are based on CGI Methodology and past experience.
CGI will continuously monitor the status and notify U S WEST of any
issues or jeopardy situations which may impact the delivery date.
3. CGI has timely access to U S WEST personnel (i.e. SMEs). CGI assumes
SME access will begin at Project Start and will continue through the
duration of the project schedule (i.e. through 12/31/97).
4. U S WEST to provide a sponsor and Project Manager to act as the liaison
between the U S WEST project team and the CGI project team.
5. CGI will work directly with subject matter experts (SMEs) to identify
highest priority legacy systems and the data required from those legacy
systems.
6. Function determination for inclusion in interface evaluation work for
different operations related to legacy system access will be
prioritized by U S WEST.
7. Weekly status reports and meetings to be held between the U S WEST
project manager the CGI project manager to measure progress against the
workplan. Any known issues and risks are also discussed and raised to
the next level if not resolved.
8. CGI development work will continue to be performed on a Hewlett-Packard
UNIX server to be provided by U S WEST, unless otherwise notified.
9. U S WEST to provide any necessary facilities, computer equipment,
server access, software, etc., by the end of Week 2 (February 15th).
10. Any delays in dependent tasks (i.e. U S WEST tasks) may impact the
delivery date.
11. Changes requests to be submitted using the CGI or U S WEST change
request process for analysts to provide estimates, costs, and impact on
current deliverables. Signed approval is required before implementation
of any changes requests.
00-000-00 19 JANUARY 24, 1997
21
EXHIBIT 4 - DELIVERABLES
------------------------
DELIVERABLES
A copy of the project deliverables, as outlined below, will be provided to the
appropriate U S WEST recipients. The master copy will contain a letter to be
mutually signed by the parties acknowledging delivery, receipt and acceptance
of the deliverables. Should CGI not receive the signed letter or a written list
of items which are not in compliance with the project specifications within ten
(10) business days after delivery, then the Deliverables shall be deemed
accepted.
DETAILED SCOPE ASSOCIATED WITH AFOREMENTIONED PROJECT WORK ITEMS
The following comprise the scope and deliverables envisioned by CGI for the
Project Work Items associated with each of the three planned software releases
of this project in 1997:
GROUP A PROJECT WORK ITEMS [FEBRUARY--APRIL, 1997]
A--1.0 Additional Interface Messages Developed for the Fetch & Stuff Server
Develop additional interface messages for the Fetch & Stuff server that
call existing [ ] Transaction APIs to obtain or update data. Examples of
new [ ] Transaction messages are:
* Set Billing Date
* Delete TN from Account
* Retrieve USOCs
There are approximately 50 [ ] Transaction messages. In the Fetch & Stuff
Phase 2, release associated with the Group A Project Work Items, there will
be time to develop approximately 20 of these messages. Prioritization will
be needed from the U S WEST DART team to identify the messages that will be
included in Fetch & Stuff Phase 2, release for Group A Items. The remaining
[ ] Transaction messages can be completed in future Fetch & Stuff
development releases, if desired.
00-000-00 20 JANUARY 24, 1997
22
The effort involved is on a per message basis. There are software changes
needed on the client application and on the Fetch & Stuff Server Engine to
define the appropriate message protocol. The Fetch & Stuff Server Engine
will also need modifications to install data in the routing tables which
direct each message to a specific API.
A--2.0 Additional Legacy Data Access Systems
Fetch & Stuff Phase 2 will provide access to the [ ] Transaction APIs. An
additional "server engine" will be added to the Fetch & Stuff Engine Server
to manage access to the [ ] Transaction APIs. It is assumed that the [ ]
Transactions API is in a stable state, and can be integrated into the Fetch
& Stuff Engine Server in the same manner as the [ ] APIs.
The software changes required are to the Fetch & Stuff Server Engine alone.
The work involves adding a new "server engine" for the [ ] Transaction
APIs. This work will be married with items described in section 1.0 above,
to add new interface messages that will request work for the new [ ]
Transaction engine.
A--3.0 Inventory Control (Usage Counts) and Defect Tracking Services
There is a need to maintain data which identifies what clients have been
using each interface message, along with the results of these usage
attempts. A data table will be used to collect usage count and defect
tracking data. Usage counts are the number of requests made for a
particular service. Defect tracking is how many times a specific interface
message failed for each possible API. Data will be collected on a per
message and per client basis. The interface message protocol will need to
be enhanced to include a client identifier in all messages. The different
kinds of counts collected will be:
* # of requests
* # of successes
* # of failures (reply returned but with failure code)
* # of time-outs (did not receive a reply from legacy API)
A Web based administration system will be developed that will provide a
mechanism to display the data collected, by way of "canned" reports. Data
will be stored in an Oracle database on request from the UNIX processes in
the Fetch & Stuff Engine Server.
There will be software changes to the Fetch & Stuff Server Engine to add
code to collect data. There will also be a totally new element developed to
provide the Web-based reporting system. A database schema will be defined
to detail how data will be saved. Pro*C code will be created to write data
into the new database.
00-000-00 21 JANUARY 24, 1997
23
A--4.0 Product Deployment
Develop items that will be used in support of product deployment, such as:
* Alarming - Fetch & Stuff was developed with the use of Service Layer
components in mind. These elements need to be added to the existing system.
* Resolve Problem Reports and make software updates on released software.
The Service Layer software changes are enhancements to the Fetch & Stuff Server
Engine. Administrative processes need to be developed on how to handle alarms.
Software maintenance changes may be in NT client or in the Fetch & Stuff Engine
software.
A--5.0 Documentation
Produce or update the following documents:
* Updated System Administration Guide
* Updated Requirements Document
* Updated Architecture Document
* Updated Design Document
* Updated Interface Inventory Document
* Updated Interface Message Protocol Document
* Deployment Guide
* Other documents, as directed by U S WEST
GROUP B PROJECT WORK ITEMS [APRIL--JULY, 1997]
B--1.0 Failover Enhancement
Hardware and Software modifications are needed to manage automatic failover to
another hardware device or software process when major failures occur to the
Interface Server machine or process. Actual HW/SW plans cannot be made until
after the production HW/SW environment is selected. One option is to add
additional hardware (servers) or separate processors on the same server along
with system software to manage the failover. Software tools from HP or Sequent
can be integrated into the Fetch & Stuff environment in order to implement
failover services.
Additional changes are desired to provide appropriate replies whenever there is
a need to communicate information relating to interface message changes or
system problems. The Fetch & Stuff Engine will send a msg back to the client as
each problem occurs. Examples of this are:
* msg replaced
* API OOS
00-000-00 22 JANUARY 24, 1997
24
B--2.0 Dynamic Routing
Routing tables are used to direct an incoming message to the appropriate server
engine for processing. The proof of concept system was implemented with the
routing tables "hard coded" into the software. Changes are needed to allow for
a dynamic implementation approach to the routing tables. The software changes
will take into account the following items:
* API Priorities (meaning go to AT API 1st, DA API 2nd, etc.)
* Whether the table is developed in Oracle or just maintained as a
matrixed array of data.
B--3.0 Increase Robustness of Fetch & Stuff Server
The current version of Fetch & Stuff Server Engine was implemented as a proof
of concept, to be trialed with a small number of users. In order to increase
robustness system improvements will be implemented for:
* Performance
* Scaleability (# of Users)
* Information Logging
* Port software to UNIX 10.x
Some items (e.g., information logging) can be implemented by adding Service
Layer elements to the Fetch & Stuff Engine Server. Other items need utilize
data collected about the system after it is completed and has stress tests
applied to it.
B--4.0 Documentation
Produce or update the following documents:
* Updated System Administration Guide
* Updated Requirements Document
* Updated Architecture Document
* Updated Design Document
* Updated Interface Inventory Document
* Updated Interface Message Protocol Document
* Deployment Guide
* Other documents, as directed by U S WEST
B--5.0 Load Balancing
Provide hardware or software mechanisms to balance the load of requests being
made to the Fetch & Stuff Interface Server. Load Balancing can be achieved
00-000-00 23 JANUARY 24, 1997
25
dynamically by developing a software process that monitors the arrival rate of
requests, and sends them to another system/processor once a threshold has been
reached. One approach may be to have specific clients' requests designated to
go to a specific server, possibly on a regional basis. Other approaches will
also be evaluated. A final approach will be heavily dependent on the hardware
chosen by U S WEST for the production environment.
GROUP C PROJECT WORK ITEMS [JULY--DECEMBER, 1997]
C--1.0 New Routing Destinations
Currently, the Fetch & Stuff Server Engine services fetch and stuff requests
from a client and returns a reply to the same client. A desired option for
Fetch & Stuff is that the application that requests data is not the application
to receive data. Additional message protocol and Fetch & Stuff Server Engine
modifications are needed to direct the resulting data to the appropriate
destination. An applications that this would be appropriate for is Call
Handling.
There will be "engine" functionality changes to recognize the protocol which
directs data to the receiving client. Software will also need to be changed on
the receiving client application's system, so that it knows what to do with a
data message being received. Finally, an effort will be required to define the
message protocol for each new interface message.
C--2.0 Routing Administration Environment
If dynamic routing tables are implemented as described above, then there will
be a need to make changes to these routing tables as production rollout
continues and data is obtained on the performance of specific APIs. A
presentation system should be implemented to add, change or delete routing
table entries. This could be done in JAVA or another GUI of U S WEST's
choosing.
Updating the routing tables will be a system administration task. A
presentation system will be very useful so that the routing table data does not
get inadvertently corrupted.
C--3.0 One Stop Shopping
This envisions the U S WEST software environment for DA and AT run on the same
hardware server as the Fetch & Stuff server engine. This, in turn, would
eliminate the need for an unnecessary "hop" to a DA or AT server before
accessing the legacy systems to process a client request. Integration test of
all software on the Fetch & Stuff production hardware is needed to successfully
complete this Project Work Item.
00-000-00 24 JANUARY 24, 1997
26
C--4.0 Documentation
Produce or update the following documents:
* Updated System Administration Guide
* Updated Requirements Document
* Updated Architecture Document
* Updated Design Document
* Updated Interface Inventory Document
* Updated Interface Message Protocol Document
* Deployment Guide
* Other documents, as directed by U S WEST
00-000-00 25 JANUARY 24, 1997