Work Both Added and Deleted Clause Samples

Work Both Added and Deleted. When the Change Order includes both Extra Work and deleted Work, Design-Builder shall prepare separate cost breakdowns for Extra Work and deleted Work in accordance with Sections 12.9.2 and 12.9.3. The difference between the Extra Work and deleted Work cost breakdowns will be the cost (or credit to VPRA) of the Change Order. If the change results in a net change of zero, the Contract Price will not be changed.
Work Both Added and Deleted. When the Change Order includes both added and deleted Development Work, Design/Builder shall prepare a statement of the cost of labor, material and equipment for both added and deleted work. (a) If the change results in a net increase in cost, the change shall be treated as work added and the provisions of Section 14.6.2 shall be used to determine mark-ups for overhead and profit. Mark-ups for overhead and profit will be allowed only for the net increase in cost in order to establish the amount to be added to the Development Price. (b) If the change results in a net decrease in cost, the change shall be treated as work deleted and the provisions of Section 14.6.3 shall be used on the net decrease in cost in order to establish the price to be deducted from the Development Price. (c) If the change results in a net change of zero, there will be no change in the Development Price.