When Bonds Are Due Sample Clauses
When Bonds Are Due. 5.1.3.1 Security bonds are due before execution of a Construction Manager-at-Risk or Design-Build Contract.
5.1.3.2 Payment and performance bonds are due before execution of a contract on competitively bid or competitively sealed proposal projects or before execution of a GMP proposal on Construction Manager-at-Risk projects or Design-Build projects.
When Bonds Are Due. 5.1.3.1 Security bonds are due within ten (10) days of signing a Construction Manager-at-Risk or Design-Build Contract.
5.1.3.2 Payment and performance bonds are due within ten (10) days of 8 Revised by TFC 2018 Supplementary General Conditions to the state of Texas 2015 edition of the Uniform General Conditions for Contracts. 9 Revised by TFC 2018 Supplementary General Conditions to the state of Texas 2015 edition of the Uniform General Conditions for Contracts. Contractor’s receipt of a fully executed GMP on a Construction Manager-at-Risk project or the Contract Sum for a Design-Build project, or within ten (10) days of Contractor’s receipt of a fully executed Contract on competitively bid or competitive sealed proposal projects.
When Bonds Are Due. 5.1.3.1 Security bonds are due within ten (10) days of signing before execution of a Construction Manager-at-Risk or Design-Build Contract.
5.1.3.2 Payment and performance bonds are due before execution of a contract on competitively bid or competitively sealed proposal projects or before execution of a GMP proposal on Construction Manager‐at‐Risk projects or Design‐Build projects within ten (10) days of Contractor’s receipt of a fully executed GMP on a Construction Manager-at-Risk project or the Contract Sum for a Design-Build project, or within ten (10) days of Contractor’s receipt of a fully executed Contract on competitively bid or competitive sealed proposal projects.
When Bonds Are Due. 5.1.3.1 Security bonds are due within ten (10) days of signing a Construction Manager-at-Risk or Design-Build Contract.
5.1.3.2 Payment and performance bonds are due within ten (10) days of Contractor’s receipt of a fully executed GMP on a Construction Manager-at-Risk project or the Contract Sum for a Design-Build project, or within ten (10) days of Contractor’s receipt of a fully executed Contract on competitively bid or competitive sealed proposal projects.
When Bonds Are Due. Payment and performance bonds are due before Contractor commences any Work.