Updates and Revisions. Not less than once per month (starting with the second month after the Work commences), the Contractor must update and, as necessary, revise the Master Construction Schedule to accommodate authorized changes in the Work and/or Contract Time, as well as any other authorized modifications to the Master Construction Schedule. Each update of the Master Construction Schedule must also specify the actual commencement and completion dates for the scheduled activities. The Contractor must submit a narrative explaining any schedule modifications along with each monthly schedule update. The Contractor must submit copies of each such updated and/or revised Master Construction Schedule and narrative to the District and Architect as provided in Subsection 19.6.
Appears in 1 contract
Sources: Construction Services Agreement
Updates and Revisions. Not less than once per month (starting with the second month after the Work commences), the Contractor must update and, as necessary, revise the Master Construction Schedule to accommodate authorized changes in the Work and/or Contract Time, as well as any other authorized modifications to the Master Construction Schedule. Each update of the Master Construction Schedule must also specify the actual commencement and completion dates for the scheduled activities. The Contractor must submit a narrative explaining any schedule modifications along with each monthly schedule update. The Contractor must submit copies of each such updated and/or revised Master Construction Schedule and narrative to the District and Architect as provided in Subsection 19.619.6.2 of these General Provisions.
Appears in 1 contract
Sources: Construction Services Agreement