Two Week Look-ahead Schedule Clause Samples
Two Week Look-ahead Schedule. During the period commencing upon issuance of the NTP and ending upon Substantial Completion, Contractor shall submit to Owner on a weekly basis a two (2) week look-ahead schedule (“Two Week Look-ahead Schedule”), which shall be based on the CPM Schedule showing in detail the activities to be performed during the next fourteen (14) Days, and shall meet all other requirements of an updated CPM Schedule as described in Section 5.4.
Two Week Look-ahead Schedule. Upon commencement of initial construction activities, the Contractor shall provide on a weekly basis a Two Week Look Ahead Schedule. The Two Week Look Ahead Schedule shall be a sufficient detail to allow the Department to fully understand the anticipated to be on going and complete.