Time period for claim Sample Clauses

Time period for claim. Within ten (10) days after receipt of a written change order under subparagraph 20a, unless the period is extended by the Agency procurement officer in writing, the CONTRACTOR shall respond with a claim for an adjustment. The requirement for a timely written response by CONTRACTOR cannot be waived and shall be a condition precedent to the assertion of a claim.
AutoNDA by SimpleDocs
Time period for claim. Except as otherwise prohibited or limited by Applicable Laws, any failure, neglect or delay of a Party to assert any breach or violation of any legal or equitable right arising from or in connection with this Agreement shall constitute a waiver of such right and shall preclude the exercise or enforcement of any legal or equitable remedy arising from such breach or violation, unless written notice specifying such breach or violation is provided to the other Party within 24 months after the later of: (a) the date of such breach or violation; or (b) the date of discovery of the facts (or the date the facts could have been discovered, using reasonable diligence) giving rise to such breach or violation. Such written notice shall not toll any applicable statute of limitations.
Time period for claim. Except as otherwise prohibited or limited by Applicable Law, any failure or delay of a Party in asserting any claim arising from or relating to this Agreement shall constitute a waiver of such claim and shall preclude the enforcement of any legal or equitable remedy with respect to such claim, unless written notice specifying such a claim is provided to the other Party within 24 months after the later of: (a) the date such claim arose; and (b) the date on which the facts giving rise to such a claim were first known (or reasonably should have been known) to the Party asserting the claim. Nothing in this Section 17.1.4 shall be deemed to extend or toll any applicable statute of limitations.
Time period for claim. Within THIRTY (30) days after receipt of a written change order under subparagraph 41.A, Change Order, unless the period is extended by the RCUH in writing, the Contractor shall file a notice of intent to assert a claim for an adjustment. The requirement for timely written notice cannot be waived and shall be a condition precedent to the assertion of a claim.
Time period for claim. Within 30 days after receipt of a written change order under Paragraph (1) (Change Order) of this clause, unless such period is extended by the Procurement Officer in writing, the Contractor shall file notice of intent to assert a claim for an adjustment. Later notification shall not bar the Contractor's claim unless the government of Guam is prejudiced by the delay in notification.

Related to Time period for claim

  • Office of Inspector General Investigative Findings Expert Review In accordance with Senate Bill 799, Acts 2021, 87th Leg., R.S., if Texas Government Code, Section 531.102(m-1)(2) is applicable to this Contract, Contractor affirms that it possesses the necessary occupational licenses and experience.

  • Right of Review Once Lessor shall have finally determined said Operating, Utility and Energy or Real Estate Tax Costs at the expiration of a Lease Year, then as to the item so established, Lessee shall only be entitled to dispute said charge as finally established for a period of six (6) months after such charge is finally established, and Lessee specifically waives any right to dispute any such charge at the expiration of said six (6) month period.

Time is Money Join Law Insider Premium to draft better contracts faster.