Time-Only Changes. The DB Contractor may request a Change Order for time extensions, subject to the limitations set forth in Section 15.6.3, for additional time for Completion Deadlines, only for the following:
A. Force Majeure Events as described in Section 18.2.
B. Failure or inability of the District to provide responses to proposed schedules, design submittals or other submittals and matters for which response by the District is required within the time periods indicated in the Contract Documents, so long as such schedules, design submittals, or other submittals and matters meet all of the applicable requirements of the Contract Documents.
Time-Only Changes. The DB Contractor may request a Change Order for time extensions, subject to the limitations set forth in Section 15.6.3, for additional time for Completion Dates, only for the following:
1. Force Majeure Events as described in Section 18.2.
2. Failure or inability of the District to provide responses to proposed schedules, design submittals or other submittals and matters for which response by the District is required within the time periods indicated in the Contract Documents, so long as such schedules, design submittals, or other submittals and matters meet all of the applicable requirements of the Contract Documents. Any increase in the contract completion date past the date specified in the RFP will negate the incentive payment portion of the design build fee as detailed in the RFP and Section 19.4 of this DB Agreement.
3. Additional costs and/or time directly attributable to failure or inability of the District to provide the DB Contractor with access to ROW identified on the Intermediate Plans on or before the deadline for such access set forth in this DB Agreement.
4. Additional costs and/or time directly attributable to Differing Site Conditions, to the extent provided in Section 15.8.
5. Certain additional costs (in the case of added Utility Work as described in Section 8) or time relating to discovery of unknown Utilities or uncooperative Utilities, as described in Section 8, to the extent provided therein.
6. Certain additional costs and/or time relating to material errors in the ROW Drawings, as described in Section 15, to the extent provided therein. Changes in the Work This Section 15 sets forth the requirements for obtaining all Change Orders under the Contract. The DB Contractor hereby acknowledges and agrees that the Contract Price constitutes full compensation for performance of all Work, subject only to those exceptions specified in this Section 15, and that the District is subject to constraints which limit its ability to increase the Contract Price or extend the Completion Dates. The DB Contractor hereby waives the right to make any Claim for a time extension or for any monetary compensation in addition to the Contract Price and other compensation specified in the Contract, except as set forth in this Section 15.