Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B of the General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX agrees to make every effort to recover "lost" time.
Appears in 4 contracts
Samples: www.deschuteslibrary.org, www.deschuteslibrary.org, www.deschuteslibrary.org
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B of the General Conditions, The Owner and the CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. During this CM/XX GC Contract for Pre-Construction Services and Contract Amendments for Construction Phase Services, the CM/GC agrees to make every effort to avoid delays and recover "“lost" time” time in a manner acceptable to the Owner.
Appears in 3 contracts
Samples: www.umpqua.edu, www.medford.k12.or.us, www.grantspass.k12.or.us
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the OSU General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX GC agrees to make every effort to recover "lost" time.
Appears in 3 contracts
Samples: bid.oregonstate.edu, bid.oregonstate.edu, bid.oregonstate.edu
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B of the General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX GC agrees to make every effort to recover "lost" time.
Appears in 3 contracts
Samples: www.lebanonfire.org, www.deschuteslibrary.org, westsidefire.com
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the Xxxxxx County General Conditions, Owner and the CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for a time extension shall be granted only as a last resort. The CM/XX GC agrees to make every effort to recover "lost" time.
Appears in 2 contracts
Samples: www.co.marion.or.us, www.co.marion.or.us
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the OUS General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX agrees to make every effort to recover "lost" time.
Appears in 2 contracts
Samples: bid.oregonstate.edu, bid.oregonstate.edu
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the OUS General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX GC agrees to make every effort to recover "lost" time.
Appears in 2 contracts
Samples: bid.oregonstate.edu, bid.oregonstate.edu
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX agrees to make every effort to recover "lost" time.
Appears in 1 contract
Samples: www.ci.oswego.or.us
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resort. CM/XX GC agrees to make every effort to recover "lost" time.
Appears in 1 contract
Samples: www.ci.oswego.or.us
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the General ConditionsExhibit A, Owner and CM/GC agree agrees that timely completion of the Work is essential to the success of the Project, and that approval for time extension shall be granted only as a last resortresort and only by written Change Order or Amendment. CM/XX agrees to GC will make every appropriate effort to recover "lost" time.
Appears in 1 contract
Samples: Contract
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the General Conditions, the Owner and the CM/GC agree that timely completion of the Work is essential to the success of the Project, and that the Owner may grant approval for a time extension shall be granted only as a last resort. The CM/XX GC agrees to make every effort to recover any "lost" timetime in the ordinary course of the CM/GC Contractor’s performance of the Work.
Appears in 1 contract
Samples: Sample Construction
Time Extensions. Notwithstanding provisions for Contract time extensions in Section 4.B D.2 of the General Conditions, Owner and CM/GC agree that timely completion of the Work is essential to the success of the Projectproject, and that approval for time extension shall be granted only as a last resort. CM/XX agrees Both parties agree to make every effort to recover "lost" time.
Appears in 1 contract
Samples: www.wou.edu